HomeMy WebLinkAbout2008-025 Council Resolution• • Council Member Stoltz introduced the following resolution and moved its adoption: CITY OF LINO LAKES RESOLUTION NO. 08 -25 RESOLUTION APPROVING CHANGE ORDER NO. 10 LAKE DRIVE /I35W IMPROVEMENT PROJECT WHEREAS, pursuant to the resolution of the City Council adopted May 14, 2007, the City awarded the construction contract for the Lake Drive /I -35W Improvement Project to Lunda Construction Company, and WHEREAS, the aggregate test reports and material disposition forms compiled by Mn /DOT indicate that on August 20, 2007 the coarse aggregate for ready -mix concrete failed to meet the gradation requirements for Mn /DOT Specification 3137 CA -50, and WHEREAS, upon recommendation of the Mn /DOT Concrete Office, the concrete containing the deficient material will be allowed to remain in place at a reduced price. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO LAKES, MINNESOTA: 1. Change Order No.10, deducting the amount of $360.00, is hereby approved. Julian e Bartell, City Jerk Adopted by the Lino Lakes City Council this 25th day of February, 2008. J. B- •eson, Mayor The motion for the adoption of the foregoing resolution was duly seconded by Council Member O'Donnell and upon vote being taken thereon, the following voted in favor thereof: Stoltz, O'Donnell, Gallup, Reinert, Bergeson The following voted against same: none Whereupon said resolution was declared duly passed and adopted. Mn/DOT TP- 2460 - 0112 -92) SHEET 1 OF 1 SHEETS State of Minnesota - Department of Transportation CHANGE ORDER # 10 State Project No.: 0280 -55 Contract No. Z07502 Contractor: Lunda Construction Co. Address: 15601 Clayton Avenue S. Rosemount, MN 55068 Location: In Lino Lakes on CSAH 23 (Lake Dr.) From 1000 ft. south of Town Center Parkway to Apollo Dr. In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions. The aggregate test reports and material disposition forms compiled by Mn/DOT indicate that on 8 -20 -07 the coarse aggregate for ready -mix concrete supplied by Cemstone Plant #7 & #17 Blaine failed to meet the gradation requirements for Mn/DOT Specification 3137 CA -50. This concrete was used for Bridge No. 02817 Abutment. Upon recommendation of the Concrete Office, the concrete containing the deficient material will be allowed to remain in place at a reduced price. The dollar amount to be deducted from the Contractor's project payable monies is computed as shown below in the Estimate of Costs. ,ecrease - Group No. #5 @ 100% Description Deduct for Failing Gradation Lab. No. 66 =5Q CHANGE IN CONTRACT TIME Due to this change the Contract Time: a. Is increased ( ) by Working Days Is decreased ( ) by Working Days Is increased ( ) by Calendar Days Is decreased ( ) by Calendar Days b. Is not changed (X ) c. May be revised if the work affected the controlling operation ( ) Estimate of Costs Unit Quantity Unit Price Amount CY 120 -$3.00 - $360.00 Total Credit this Change Order - $360.00 Issued By: 11 -2,7 Project/Residen i ►ounty Engineer Date Approved By: City of Lino Lakes Approved By: Anoka County Date Accepted By: 10��� 1:3 1-z9-oz Contractor's Authorized Representative Date original to Project Engineer; copies to Contractor; City of Lino Lakes, Anoka County