Council Member Stoltz introduced the following resolution and moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 08 -25
RESOLUTION APPROVING CHANGE ORDER NO. 10
LAKE DRIVE /I35W IMPROVEMENT PROJECT
WHEREAS, pursuant to the resolution of the City Council adopted May 14, 2007, the City
awarded the construction contract for the Lake Drive /I -35W Improvement Project to Lunda
Construction Company, and
WHEREAS, the aggregate test reports and material disposition forms compiled by Mn /DOT
indicate that on August 20, 2007 the coarse aggregate for ready -mix concrete failed to meet the
gradation requirements for Mn /DOT Specification 3137 CA -50, and
WHEREAS, upon recommendation of the Mn /DOT Concrete Office, the concrete containing the
deficient material will be allowed to remain in place at a reduced price.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. Change Order No.10, deducting the amount of $360.00, is hereby approved.
Julian e Bartell, City Jerk
Adopted by the Lino Lakes City Council this 25th day of February, 2008.
J. B- •eson, Mayor
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member O'Donnell and upon vote being taken thereon, the following voted in favor
thereof: Stoltz, O'Donnell, Gallup, Reinert, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
Mn/DOT TP- 2460 - 0112 -92)
SHEET 1 OF 1 SHEETS
State of Minnesota - Department of Transportation
CHANGE ORDER # 10
State Project No.: 0280 -55
Contract No. Z07502
Contractor: Lunda Construction Co.
Address: 15601 Clayton Avenue S.
Rosemount, MN 55068
Location: In Lino Lakes on CSAH 23 (Lake Dr.) From 1000 ft. south of Town Center Parkway to Apollo Dr.
In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions.
The aggregate test reports and material disposition forms compiled by Mn/DOT indicate that on 8 -20 -07 the
coarse aggregate for ready -mix concrete supplied by Cemstone Plant #7 & #17 Blaine failed to meet the
gradation requirements for Mn/DOT Specification 3137 CA -50.
This concrete was used for Bridge No. 02817 Abutment.
Upon recommendation of the Concrete Office, the concrete containing the deficient material will be allowed to
remain in place at a reduced price. The dollar amount to be deducted from the Contractor's project payable
monies is computed as shown below in the Estimate of Costs.
,ecrease - Group No. #5 @ 100%
Description
Deduct for Failing Gradation
Lab. No. 66 =5Q
CHANGE IN CONTRACT TIME
Due to this change the Contract Time:
a. Is increased ( ) by Working Days
Is decreased ( ) by Working Days
Is increased ( ) by Calendar Days
Is decreased ( ) by Calendar Days
b. Is not changed (X )
c. May be revised if the work affected
the controlling operation ( )
Estimate of Costs
Unit Quantity Unit Price Amount
CY
120 -$3.00 - $360.00
Total Credit this Change Order - $360.00
Issued By:
11 -2,7
Project/Residen i ►ounty Engineer Date
Approved By:
City of Lino Lakes
Approved By:
Anoka County
Date
Accepted By: 10��� 1:3 1-z9-oz
Contractor's Authorized Representative Date
original to Project Engineer; copies to Contractor; City of Lino Lakes, Anoka County