Council Member Stoltz introduced the following resolution and moved its
adoption:
CITY OF LINO LAKES
RESOLUTION NO. 08 -26
RESOLUTION APPROVING CHANGE ORDER NO. 11
LAKE DRIVE /135W IMPROVEMENT PROJECT
WHEREAS, pursuant to the resolution of the City Council adopted May 14, 2007, the City
awarded the construction contract for the Lake Drive /I -35W Improvement Project to Lunda
Construction Company, and
WHEREAS, the south approach panel for Bridge No. 02817 was constructed as surveyed and
is in conflict with the new guardrail that is needed to be installed, and
WHEREAS, the Project Engineer has determined that a portion of the approach panel needs to
be removed to install the new guardrail.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. Change Order No.11, in the amount of $1,600.00, is hereby approved.
n Bartell, City ler
Adopted by the Lino Lakes City Council this 25th day of February, 2008
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member O'Donnell and upon vote being taken thereon, the following voted in favor
thereof:
Stoltz, O'Donnell, Reinert, Gallup, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
Mn /DOT TP- 2460- 0112 -92)
•
SHEET 1 OF 1 SHEETS
State of Minnesota - Department of Transportation
CHANGE ORDER # 11
Contractor: Lunda Construction Co.
Address: 15601 Clayton Avenue S.
Rosemount, MN 55068
State Project No.: 0280 -55
Contract No. Z07502
Location: In Lino Lakes on CSAH 23 (Lake Dr.) From 1000 ft. south of Town Center Parkway to Apollo Dr.
In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions.
Due to a staking error the south approach panel for Bridge No. 02817 stage I was constructed as surveyed and
now in conflict with the new guardrail that is needed to be installed. After review the Project Engineer has
determined that the approach panel needs to have the portion in conflict with the new guardrail removed.
This Change Order directs the Contractor to furnish all equipment, materials and labor necessary to remove the
portion of the approach panel in conflict with the new guardrail.
All work will be performed in accordance with the pertinent portions of the Special Provisions, Mn/DOT
Standard Specifications, Mn/DOT Standard Plates and as directed by the Engineer.
Payment to the Contractor for this work will be at the Mn/DOT 1904 Force Account, as shown below in the Estimate of
•ost:
ESTIMATE OF COST
Force Account
Description
Approach Panel Removals
Distribution: S.P. 0280 -55 Group 01 — 100%
CHANGE IN CONTRACT TIME
Due to this change the Contract Time:
a. Is increased ( ) by Working Days
Is decreased ( ) by Working Days
Is increased ( ) by Calendar Days
Is decreased ( ) by Calendar Days
b. Is not changed (X )
c. May be revised if the work affected
the controlling operation ( )
Issued By:
Amount
$1,600.00
�,��r� 'Resident/ 1Tr Engineer Date
Approved By:
City of Lino Lakes
Date
Approved By:
Anoka County
Accepted By:,.:__ L
Contractor's Authorized Representative
11110riginal to Project Engineer; copies to Contractor, City of Lino Lakes, Anoka County
Date
1Z -ZB - °"
Date