HomeMy WebLinkAbout2008-037 Council Resolution•
Council Member Stoltz introduced the following resolution and moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 08 -37
RESOLUTION APPROVING CHANGE ORDER NO. 12
LAKE DRIVE /I35W IMPROVEMENT PROJECT
WHEREAS, pursuant to the resolution of the City Council adopted May 14, 2007, the City
awarded the construction contract for the Lake Drive /I -35W Improvement Project to Lunda
Construction Company, and
WHEREAS, the aggregate test reports and material disposition forms compiled by Mn /DOT
indicate that on August 20, 2007 the coarse aggregate for ready -mix concrete failed to meet the
gradation requirements for Mn /DOT Specification 3137 CA -50, and
WHEREAS, on February 25, 2008 the City Council approved Change Order No. 10 deducting
$360.00 from the contract price in accordance with the contract provisions, and
WHEREAS, upon further review, Mn /DOT's concrete office has determined that the specified
ready -mix concrete should be accepted as in substantial compliance.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. Change Order No.12, superseding Change Order No. 10 making it null and void, is
hereby approved.
Ju ian e Bartell, City C
Joh r. Berg on, ayor
Adopted by the to Lakes City Council this 28th day of April, 2008.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member Gallup and upon vote being taken thereon, the following voted in favor
thereof:
Stoltz, Gallup, O'Donnell, Bergeson
The following voted against same:
None (Absent - Reinert)
Whereupon said resolution was declared duly passed and adopted.
• Council Member introduced the following resolution and moved its adoption:
•
STAFF ORIGINATOR:
CITY COUNCIL
MEETING DATE:
TOPIC:
AGENDA ITEM 1G
Michael Grochala
April 28, 2008
Resolution No. 08 -24, Approving Change Order
No.12, Lake Drive /35W Improvement Project
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND:
On May 14, 2007 the City Council awarded the Lake Drive /I -35W Improvement Project
to Lunda Construction Company in the amount of $7,531,701.71.
On February 25, 2008 the City Council approved Change Order No. 10 deducting
$360.00 for concrete materials that failed to meet gradation requirements. Upon further
review Mn /DOT's concrete office has determined that the specified concrete is in
substantial compliance with the contract provisions. Change Order No. 12 supersedes
Change Order No. 10 making it null and void.
RECOMMENDATION:
Staff is recommending approval of Resolution No. 08 -37.
ATTACHMENTS
1. Resolution No. 08 -37
2. Change Order No. 12
r
Mn /DOT TP -2460- 0112 -92) SHEET 1 OF 1 SHEETS
State of Minnesota - Department of Transportation
CHANGE ORDER # 12
•
Contractor: Lunda Construction Co. State Project No.: 0280 -55
Address: 15601 Clayton Avenue S.
Rosemount, MN 55068 Contract No. Z07502
Location: In Lino Lakes on CSAH 23 (Lake Dr.) From 1000 ft. south of Town Center Parkway to Apollo Dr.
In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions.
This Change Order No. 12 will supersede Change Order No. 10 making it null and void.
The aggregate test reports and material disposition forms compiled by Mn 'DO T indicate that on 8 -20 -07 the
coarse aggregate for ready -mix concrete supplied by Cemstone Plant #7 & #17 Blaine failed to meet the
gradation requirements for Mn/DOT Specification 3137 CA -50.
This concrete was used for Bridge No. 02817 Abutment.
After further review upon recommendation of the Concrete Office, the concrete containing the deficient
material above is waived per Mn/DOT Concrete Engineer Douglas J. Schwartz's memo dated January 16, 2008
states shall be accepted as substantial compliance.
•
CHANGE IN CONTRACT TIME
Due to this change the Contract Time:
a. Is increased ( ) by Working Days
Is decreased ( ) by Working Days
Is increased ( ) by Calendar Days
Is decreased ( ) by Calendar Days
b. Is not changed (X )
c. May be revised if the work affected
the controlling operation ( )
Issued By: �3a
Project/Residen ounty Engineer Date
Approved By:
City of Lino Lakes
Approved By:
Anoka County
Date
Liifki4S
Dte
Accepted By: v-- 2,--/ -D 3
Contractor's Authorized Representative Date
Original to Project Engineer; copies to Contractor, City of Lino Lakes, Anoka County