HomeMy WebLinkAbout2008-114 Council Resolution•
•
•
Council Member O'Donnell
moved its adoption:
introduced the following resolution and
CITY OF LINO LAKES
RESOLUTION NO. 08-114
APPROVING PAYMENT REQUEST NO. 3 (FINAL) AND
COMPENSATING CHANGE ORDER NO. 1, 2008 OVERLAY PROJECT
WHEREAS, pursuant to the resolution of the Council adopted April 28, 2008, awarding
the contract for 2008 Overlay Project to WB Miller, Inc.;
WHEREAS, a complete breakdown is detailed in Payment No. 3 (Final) and
Compensating Change Order No. 1;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
Payment Request No. 3 (Final) and Compensating Change Order No. 1 is
approved for a final contract amount of $ 168,722.19.
Bartell, C.
Berg on, ayor
Adopted by the Lino Lakes City Council this 13th day of October, 2008.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member Reinert and upon vote being taken thereon, the following voted in favor
thereof:
O'Donnell, Reinert, Gallup, Stoltz, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
•
•
AGENDA ITEM 6C
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: October 13, 2008
TOPIC: Resolution No. 08 -114, Approving Payment
Request No. 3 (Final) and Compensating Change
Order No. 1, 2008 Overlay Project.
VOTE REQUIRED: Simple Majority
BACKGROUND:
At the April 28, 2008 meeting, City Council awarded the 2008 Overlay Project contract to
WB Miller, Inc.
The contractor for the 2008 Overlay Project, WB Miller, Inc., is requesting City approval
of Payment Request No. 3 (Final) in the amount of $8,436.11. A copy of the Final
Payment is attached. The contractor has satisfactorily completed all work and has
provided all necessary documentation.
Also included with the request for Final Payment is Compensating Change Order
No. 1 in the deduct amount of $7,425.21. A copy of the Compensating Change Order is
attached. With this Change Order, the final project amount is $168,722.19, which is
below the contract amount of $176,147.40.
Approval of the Final Payment will begin the one -year warranty period.
RECOMMENDATION:
Staff recommends the approval of Resolution No. 08 -114, Approving Payment Request
No. 3 (Final) and Compensating Change Order No. 1, 2008 Overlay Project.
TKDA
ENGINEERS • ARCHITECTS • PLANNERS
444 Cedar Street, Suite 1500
Saint Paul, MN 55101 -2140
(651) 292 -4400
(651) 292 -0083 Fax
www.tkda.com
Proj. No. 14043.002 Cert. No. 3(F) St. Paul, MN, September 9 , 20 08
To City of Lino Lakes, Minnesota Owner
This Certifies that W.B. Miller , Contractor
For 2008 Overlay Project
Is entitled to
being 3rd
Eight Thousand Four Hundred Thirty-Six Dollars and 11 /100 ($ 8,436.11)
FINAL
estimate for paPtial payment on contract with you dated April 28 , 2008
Received payment in full of above Certificate. TKDA
W.B. Miller L )1c,
, 20 Matthew J. Woodruff, P.E.
•
RECAPITULATION OF ACCOUNT
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$ 176,147.40
All previous payments
$ 160,286.08
All previous credits
Extra No.
Compensating Change Order No. 1
$ (7,425.21)
It
Credit No.
It
VI
AMOUNT OF THIS CERTIFICATE
$ 8,436.11
Totals
$ 168,722.19
168,722.19
Credit Balance
There will remain unpaid on contract after
payment of this Certificate
$ 168,722.19
$ 168,722.19
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
•
•
TKDA
Engineers - Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 3(F) Period Ending September 9 , 20 08 Page 1 of 1 Proj. No. 14043.002
Contractor W.B. Miller Original Contract Amount 176,147.40
Project 2008 Overlay Project
Location City of Lino Lakes, Minnesota
Total Contract Work Completed $ 168,722.19
Total Approved Credits $ 0.00
Total Approved Extra Work Completed $ 0.00
Approved Extra Orders Amount Completed $ 0.00
Total Amount Eamed This Estimate $ 168,722.19
Less Approved Credits $
Less 0 % Retained $
Less Previous Payments
Total Deductions
Amount Due This Estimate
Contractor
alEngineer
W. Miller
(A./100
Matthew J. Woodruff, P
0.00
0.00
160,286.08
Date
160,286.08
$ 8,436.11
Date Cerr l 5 zeio8
ESTIMATE NO. 3(F)
2008 OVERLAY PROJECT
OAOF LINO LAKES, MINNESOTA
PROJECT NO. 14043.002
PERIOD ENDING: September 9, 2008
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
2008 OVERLAY PROJECT
1 MOBILIZATION LS 1 1.00 $ 5,700.00 $ 5,700.00
2 RECLAIM BITUMINOUS SY 13146 13,146.00 $ 0.40 $ 5,258.40
3 HAUL OUT EXCESS MILLINGS (LV) CY 587 638.00 $ 5.00 $ 3,190.00
4 RESHAPE MILLINGS (3% CROWN) RS 43.8 43.80 $ 130.00 $ 5,694.00
5 BITUMINOUS BASE COURSE 2360 (LVNW 35030) TN 1675 1,549.72 $ 45.40 $ 70,357.29
6 BITUMINOUS WEARING COURSE 2360 (LVWE 45030) TN 1350 1,431.84 $ 51.90 $ 74,312.50
7 BITUMINOUS MATERIAL FOR TACK COAT GAL 730 730.00 $ 2.00 $ 1,460.00
8 BITUMINOUS CURBING LF 500 $ 2.00 $
9 SAWCUT BITUMINOUS DRIVEWAYS LF 220 $ 2.00 $
10 REMOVE BITIMINOUS DRIVEWAY MATERIAL SY 250 $ 3.00 $
11 BIT. WEARING COURSE 2360 (LVWE 45030) (FOR DRIVES) SY 250 - $ 14.00 $ -
12 REMOVE AND REPLACE CATCH BASIN (TYPE 402) EA 3 3.00 $ 550.00 $ 1,650.00
13 REMOVE AND REPLACE CATCH BASIN (TYPE 406) EA 3 2.00 $ 550.00 $ 1,100.00
TOTAL ESTIMATE NO. 3(F) $ 168,722.19
•
•
•
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
Saint Paul, MN September 9 20 08 Proj. No. 14043.002
To W.B. Miller
Compensating
Change Order No. 1
for 2008 Overlay Project
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
April 28 , 20 08 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decrease) (not change) the contract sum by
Seven Thousand Four Hundred Twenty -Five Dollars and 21/100 ($ 7,425.21 ).
COMPENSATING CHANGE ORDER
This change order shows the actual quantities installed at the unit price bid amounts (see attached itemization):
NET CHANGE =
Amount of Original Contract
Additions approved to date (Nos.
Deductions approved to date (Nos.
Contract amount to date
Amount of this Change Order (tom) (Deduct) (Pie -Chaage)
Revised Contract Amount
Approved City of Lino Lakes TKDA
Owner
$ (7,425.21)
$ 176,147.40
$ 176,147.40
$ (7,425.21)
$ 168,722.19
By By F 1
Matthew J. Woodruff, P.E.
Approved W.B. Miller White - Owner
Contractor Pink - Contractor
Blue - TKDA
COMPENSATING CHANGE ORDER NO. 1
2008 OVERLAY PROJECT
CITY OF LINO LAKES, MINNESOTA
PROJECT NO. 14043.002
PERIOD ENDING: September 9, 2008
ITEM CONTRACT QUANTITY UNIT AMOUNT NET CONTRACT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE CHANGE AMOUNT
2008 OVERLAY PROJECT
1 MOBILIZATION LS 1 1.00 $ 5,700.00 $ 5,700.00 $ - $ 5,700.00
2 RECLAIM BITUMINOUS SY 13146 13,146.00 $ 0.40 $ 5,258.40 $ - $ 5,258.40
3 HAUL OUT EXCESS MILLINGS (LV) CY 587 638.00 $ 5.00 $ 3,190.00 $ 255.00 $ 2,935.00
4 RESHAPE MILLINGS (3% CROWN) RS 43.8 43.80 $ 130.00 $ 5,694.00 $ - $ 5,694.00
5 BITUMINOUS BASE COURSE 2360 (LVNW 35030) TN 1675 1,549.72 $ 45.40 $ 70,357.29 $ (5,687.71) $ 76,045.00
6 BITUMINOUS WEARING COURSE 2360 (LVWE 45030) TN 1350 1,431.84 $ 51.90 $ 74,312.50 $ 4,247.50 $ 70,065.00
7 BITUMINOUS MATERIAL FOR TACK COAT GAL 730 730.00 $ 2.00 $ 1,460.00 $ - $ 1,460.00
8 BITUMINOUS CURBING LF 500 $ 2.00 $ - $ (1,000.00) $ 1,000.00
9 SAWCUT BITUMINOUS DRIVEWAYS LF 220 $ 2.00 $ - $ (440.00) $ 440.00
10 REMOVE BITIMINOUS DRIVEWAY MATERIAL SY 250 - $ 3.00 $ $ (750.00) $ 750.00
11 BIT. WEARING COURSE 2360 (LVWE 45030) (FOR DRIVES) SY 250 $ 14.00 $ $ (3,500.00) $ 3,500.00
12 REMOVE AND REPLACE CATCH BASIN (TYPE 402) EA 3 3.00 $ 550.00 $ 1,650.00 $ $ 1,650.00
13 REMOVE AND REPLACE CATCH BASIN (TYPE 406) EA 3 2.00 $ 550.00 $ 1,100.00 $ (550.00) $ 1,650.00
TOTAL COMPENSATING CHANGE ORDER NO. 1
•
•
$ 168,722.19 $ (7,425.21) $ 176,147.40