HomeMy WebLinkAbout2008-115 Council ResolutionCouncil Member Stoltz introduced the following resolution and
moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 08-115
APPROVING PAYMENT REQUEST NO. 2 (FINAL) AND
COMPENSATING CHANGE ORDER NO. 1, 2008 SEALCOAT PROJECT
WHEREAS, pursuant to the resolution of the Council adopted April 28, 2008, awarding
the contract for 2008 Sealcoat Project to Allied Blacktop, Inc.;
WHEREAS, a complete breakdown is detailed in Payment No. 2 (Final) and
Compensating Change Order No. 1;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
Payment Request No. 2 (Final) and Compensating Change Order No. 1 is
approved for a final contract amount of $132,447.73.
Adopted by the Lino Lakes City Council this 13th day of October, 2008.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member 0 Donnell and upon vote being taken thereon, the following voted in favor
thereof:
Stoltz, O'Donnell, Reinert, Gallup, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
•
•
AGENDA ITEM 6B
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: October 13, 2008
TOPIC: Resolution No. 08 -115, Approving Payment
Request No. 2 (Final) and Compensating Change
Order No. 1, 2008 Sealcoat Project.
VOTE REQUIRED: Simple Majority
BACKGROUND:
At the April 28, 2008 meeting, City Council awarded the 2008 Sealcoat Project contract
to Allied Blacktop, Inc.
The contractor for the 2008 Sealcoat Project, Allied Blacktop, Inc., is requesting City
approval of Payment Request No. 2 (Final) in the amount of $6,622.39. A copy of the
Final Payment is attached. The contractor has satisfactorily completed all work and has
provided all necessary documentation.
Also included with the request for Final Payment is Compensating Change Order
No. 1 in the additional amount of $5,633.73. A copy of the Compensating Change Order
is attached. With this Change Order, the final project amount is $132,447.73 which is
below the engineer's estimate of $159,345.00.
Approval of the Final Payment will begin the one -year warranty period.
RECOMMENDATION:
Staff recommends the approval of Resolution No. 08 -115, Approving Payment Request
No. 2 (Final) and Compensating Change Order No. 1, 2008 Sealcoat Project.
TKDA
ENGINEERS • ARCHITECTS • PLANNERS
444 Cedar Street, Suite 1500
Saint Paul, MN 55101 -2140
(651) 292 -4400
(651) 292 -0083 Fax
www.tkda.com
Proj. No. 14043.001 Cert. No. 2(F) St. Paul, MN, September 5 , 20 08
To City of Lino Lakes, Minnesota
This Certifies that Allied Blacktop
For 2008 Sealcoating
Owner
, Contractor
Is entitled to Six Thousand Six Hundred Twenty -Two Dollars and 39/100
FINAL
being 2nd estimate for phial payment on contract with you dated April 28th
Received payment in full of above Certificate. TKDA
($6,622.39)
Allied Blacktop L40 t- 6000, a4
, 20 Matthew J. Woodruff, P.
2008
RECAPITULATION OF ACCOUNT
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
126,814.00
All previous payments
$
125,825.34
All previous credits
Extra No.
Compensating Change Order No. 1
$
5,633.73
Credit No.
$ -
AMOUNT OF THIS CERTIFICATE
$
6,622.39
Totals
$
132,447.73
$
132,447.73
$ -
Credit Balance
$
-
There will remain unpaid on contract after
payment of this Certificate
$
-
$
132,447.73
$
132,447.73
$ -
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
•
•
•
TKDA
Engineers - Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 2(F) Period Ending July 11
Contractor Allied Blacktop
Project 2008 Sealcoating
Location City of Lino Lakes, Minnesota
, 20 08 Page 1 of 1 Proj. No. 14043.001
Original Contract Amount $126,814.00
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed
Approved Extra Orders Amount Completed
Total Amount Eamed This Estimate
$ 132,447.73
$ 0.00
0.00
$ 0.00
$ 132,447.73
Less Approved Credits $ 0.00
Less 0 % Retained $ 0.00
Less Previous Payments $ 125,825.34
Total Deductions
Amount Due This Estimate
125,825.34
$ 6,622.39
// I
Contractor 4 Date % / / / 6?
j�/� Allied Blacktop
Engineer v" f(X..A%( WOO Date Err S i S
Matthew J. Woodru , .E.
ESTIMATE NO. 2(F)
2008 SEALCOATING
OF LINO LAKES, MINNESOTA
A PROJECT NO. 14043.001
PERIOD ENDING: September 5, 2008
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
1 BITUMINOUS SEALCOATING W /FA -2 1/8" TRAP ROCK CHIPS SY 115,200.0 122,639.0 $ 1.07 $ 131,223.73
2 CRACK SEALING - (MATERIAL SUPPLIED BY CITY) LB 7,100.0 2,448.0 $ 0.50 $ 1,224.00
TOTAL ESTIMATE NO. 2(F) $ 132,447.73
•
•
•
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
Compensating
Saint Paul, MN September 5 20 08 Proj. No. 14043.001 Change Order No. 1
To Allied Blacktop
for 2008 Sealcoating
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
April 28 , 20 08 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (deer use) (not change) the contract sum by
Five Thousand Six Hundred Thirty-Three Dollars and 73/100 ($ 5,633.73 ).
COMPENSATING CHANGE ORDER
This change order shows the actual quantities installed at the unit price bid amounts (see attached itemization):
NET CHANGE =
Amount of Original Contract
Additions approved to date (Nos.
Deductions approved to date (Nos.
Contract amount to date
Amount of this Change Order (Add) (Deduct) (Ne -Chmge)
Revised Contract Amount
Approved TKDA
City of Lino Lakes
$ 5,633.73
126,814.00
126,814.00
5,633.73
132,447.73
By By
Matthew J. Woodruff, P.E.
•
Approved White - Owner
Hied B acktop Pink - Contractor
Blue - TKDA
By f M (rc91 ���1'c , �') (`�` 9/(4S d'ej') j°
COMPENSATING CHANGE ORDER NO. 1
2008 SEALCOATING
CITY OF LINO LAKES, MINNESOTA
fp
PROJECT NO. 14043.001
T
PERIOD ENDING: September 5, 2008
I CONTRACT QUANTITY UNIT AMOUNT NET CONTRACT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE CHANGE AMOUNT
1 BITUMINOUS SEALCOATING W /FA -2 1/8" TRAP ROCK CHIPS SY 115,200.0 122,639.0 $ 1.07 $ 131,223.73 $ 7,959.73 $ 123,264.00
2 CRACK SEALING - (MATERIAL SUPPLIED BY CITY) LB 7,100.0 2,448.0 $ 0.50 $ 1,224.00 $ (2,326.00) $ 3,550.00
TOTAL COMPENSATING CHANGE ORDER NO. 1 $ 132,447.73 $ 5,633.73 $ 126,814.00
•
•