HomeMy WebLinkAbout2008-122 Council Resolution• • Council Member Stoltz introduced the following resolution and moved its adoption: CITY OF LINO LAKES RESOLUTION NO. 08 -122 RESOLUTION APPROVING CHANGE ORDER NO. 16 LAKE DRIVE /I35W IMPROVEMENT PROJECT WHEREAS, pursuant to the resolution of the City Council adopted May 14, 2007, the City awarded the construction contract for the Lake Drive /I -35W Improvement Project to Lunda Construction Company, and WHEREAS, upon reviewing the construction plans it was discovered that additional grading items under Bridge No. 02817 were necessary for construction, and WHEREAS, this change order directs the contractor to perform all grading work to complete the improvements. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO LAKES, MINNESOTA: 1. Change Order No.16, in the amount of $25,370.55, is hereby approved. J nne Bartell, I ity C iB r John J er ge n, M o Adopted by the Lino Lakes City Council this 13th day of October, 2008 The motion for the adoption of the foregoing resolution was duly seconded by Council Member of and 1 and upon vote being taken thereon, the following voted in favor thereof: Stoltz, O'Donnell, Gallup, Bergeson The following voted against same: Reinert Whereupon said resolution was declared duly passed and adopted. Council Member introduced the following resolution and moved its adoption: o9"Sep, 17. 2008 8:12AM 366 LUNDA CONSTRUCTION COMPANYD1sTRIcT No. 0230 P. 2)2 Mn/DOT 2? -2460-0112-92) SHEET 1 OF 2 $TlEETS State of Minnesota - Department of Transportation CHANGE ORDER # 16 Contractor: Lunda Construction Co. Address: 15601 Clayton Avenue S. Rosextxoant,MN 55068 State Project No.: 0280 -55 Contract No. Z07502 Location: In Lino Lakes on CSAH 23 (Lake Dr) From 1000 ft. south of Town Center Paikway to Apollo Dr. 1>t accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altcred by tho following provisions. Upon reviewing the construction plans for the project it was discovered that grading items under Bridge No, 02817 were omitted from the quantity tabulations. This Change Order directs the Contractor to furnish all equipment, materials and labor necessary to perform all grading work in accordance with the additional plan sheet 81A. By signing this Change Order the Contractor acknowledges receipt of plan. sheet 81A, All work will be performed in accordance with the pertinent portions of the Special Provisions, Mn/DOT Standard SpecStcations,1V , tn/DOT Standard Plates and as directed by the Engineer. Payment to the Contractor for this work will be at the contract unit prices and negotiated prices as shown below in the Estimate of Cost. • In crease — Contract Unit Items Group No, 1 gSTI,MATE OF COST Item No, Description Unit 9uantity Unit Price Amount 2575.502 Seed Mixture 250 Pound 20 $2.50 $ 50,00 2575.511 Mulch Material Type 1 Ton 0.6 $200.00 $ 120.00 2575.532 Fertilizer Type 3 Pound 101 $0.25 $ 25.25 2575,519 Disc Anchoring Acre 0.3 $100.00 S 30.00 Subtotal Increase $225.25 • 09/ :Sep, 17. 2008' 8:12AM 366LUNDA CONSTRUCTION COMPANYDIsTRICT No. 0230 P. 3)3 Mri/DOT TP4460 -0T 12 -92) SHEET 2 OF 2 SHEETS State of Mittuesota - Department of Transportation CHANGE ORDER # 16 Contractor: Lunda Construction Co. Address: 15601 Clayton Avenue S. Rosemount, MN 55068 State Project No.: 0280 -55 Contract No. Z07502 Location: In Lino Lakes on CSA.I 23 (Lake Dr.) From 1000 ft, south of Town Center Parkway to Apollo Dr. In accordance with the terms of thls Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions. Increase Negotiated Items - Group No.1 All Items Include 10% Prune Contractor .Allowance Item No. Description 2021.501 Prattalone Mobilization 2021.501 Neaton Mobilization 2105.501 Common Excavation (CV) 2105.525 Top Soil Borrow (CV) 2221.503 Aggregate Shouldering Class 7 (CV) 2501.567 24 "CS Safety Apron & Grate Design (3148) 2501.567 24"RC Safety Apron & Grate Design (3022) 2506.502 Const Drainage Structure Design 60 -4020 2506.516 Casting Assembly A -7D 2575.513 Mulch Material Type 9 CHANGE IN CONTRACT TIME Doc to this change the Contract Time: Ys increased ( ) by Working Days Is decreased ( ) by Working Days Is increased () by Calendar Days Is decreased ( ) by Calendar Days b. Is Dot changed (X ) May be revised if the work affected the controlling operation ( ) Unit Quantit' L.S. 1 L.S. 1 CUYD 217 (P) aril) 166 (P) CUYD 98 (p) Each 1 Eao1 1 Each Each 1 1 Unit Price $1,650.00 $1,430.00 $19.I1 $22.32 $4137 $.1,238.68 $1,773.52 $2,895.20 $461.50 CUYD 54 (p) $70.08 Subtotal hicrease oust $1,650,00 $1,430.00 $4,146.87 $3,704.95 $4,054.26 $1,238 ..68 $1,773,52 $2,895.20 $ 467.50 $3 784.32 $25,14530 TOTAL ESTIMATED INCREASE $25,37055 Issued Ey. Project/Resident/ ounty Approved By: City of Lino Lakes l]gtDeer D21tc Approved By Anoka County Acoeptea o Contractctor's uthorized Representative Date Original to Project Engineer; copies to Contractor, City of Lino Lakes, Anoka County Date Date 91 -68