HomeMy WebLinkAbout2008-127 Council ResolutionCouncil Member Reinert introduced the following resolution and
moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 08-127
APPROVING PAYMENT REQUEST NO. 4 (FINAL), CHANGE ORDER
NO 2. AND COMPENSATING CHANGE ORDER NO. 3, LINO PARK GRADING
AND TRAIL WORK
WHEREAS, pursuant to the resolution of the Council adopted July 23, 2007, awarding
the contract for the Lino Park Grading and Trail Work to Jay Brothers, Inc.;
WHEREAS, a complete breakdown is detailed in Payment No. 4 (Final), Change Order
No. 2 and Compensating Change Order No. 3;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
Payment Request No. 4 (Final), Change Order No. 2 and Compensating Change
Order No. 3 is approved for a final contract amount of $67,791.19.
A-cam
�ulinne Bartell, C Clerk
Bergeson, Mayor
Adopted by the Lino Lakes City Council this 27th day of October, 2008.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member o' non/le-11 and upon vote being taken thereon, the following voted in favor
thereof:
Reinert, O'Donnell, Gallup, Stoltz, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
•
•
AGENDA ITEM 6C
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: October 27, 2008
TOPIC: Resolution No. 08 -127, Approving Payment
Request No. 4 (Final), Change Order No. 2 and
Compensating Change Order No. 3, Lino Park
Grading and Trail Work
VOTE REQUIRED: Simple Majority
BACKGROUND:
At the July 23, 2007 meeting, City Council awarded the Lino Park Grading and Trail
Work project contract to Jay Brothers, Inc.
The contractor for the Lino Park Grading and Trail Work, Jay Brothers, Inc., is requesting
City approval of Payment Request No. 4 (Final) in the amount of $4,207.04. A copy of
the Final Payment is attached. The contractor has satisfactorily completed all work and
has provided all necessary documentation.
Included with the request for Final Payment is Change Order No. 2 in the amount of
$2,733.40. The work under Change Order No. 2 covers additional stabilization and
vegetation as required by the Rice Creek Watershed District. Compensating Change
Order No. 3 in the deduct amount of $2,610.46 is also included with the request. A copy
of Change Order No. 2 and Compensating Change Order No. 3 is attached. With this
Change Order, the final project amount is $67,791.19, which is below the engineers'
estimate of $91,460.00.
Approval of the Final Payment will begin the one -year warranty period.
RECOMMENDATION:
Staff recommends the approval of Resolution No. 08 -127, Approving Payment Request
No. 4 (Final), Change Order No. 2 and Compensating Change Order No. 3, Lino Park
Grading and Trail Work.
TKDA
iiNGINEERS • ARCHITECTS • PLANNERS
444 Cedar Street, Suite 1500
Saint Paul, MN 55101 -2140
(651) 292 -4400
(651) 292 -0083 fax
www.tkda.com
Proj. No. 13849.003 Cert. No. 4(F) St. Paul, MN, September 16 , 20 08
To City of Lino Lakes, Minnesota
This Certifies that Jay Brothers, Inc.
For Lino Park Grading and Trail Work
Is entitled to Four Thousand Two Hundred Seven Dollars and 04/100
Owner
, Contractor
FINAL
being 4th estimate for payment on contract with you dated July 23
Received payment in full of above Certificate. TKDA
Jay Brothers, Inc.
($ 4.207.04)
07
azr Woo
, 20 Matthew J. Woodruff, P.E.
RECAPITULATION OF ACCOUNT
•
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
63,997.25
All previous payments
$ 63,584.15
All previous credits
Extra No.
Change Order No. 1
$
3,671.00
Change Order No. 2
$
2,733.40
Compensating Change Order No. 3
$
(2,610.46)
Credit No.
$
-
„ „
AMOUNT OF THIS CERTIFICATE
$ 4,207.04
Totals
$
67,791.19
$ 67,791.19
$
-
Credit Balance
$ -
There will remain unpaid on contract after
payment of this Certificate
$ -
1 $
67,791.19
II $ 67,791.19
n $
- I
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
•
•
•
TKDA
Engineers - Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 4(F) Period Ending September 16 , 20 08 Page 1 of 1 Proj. No. 13849.003
Contractor Jay Brothers, Inc. Original Contract Amount $63,997.25
Project Lino Park Grading and Trail Work
Location City of Lino Lakes, Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed $ 0.00
Approved Extra Orders Amount Completed
Total Amount Earned This Estimate
$ 67,791.19
$ 0.00
$ 0.00
$ 67,791.19
Less Approved Credits $ 0.00
Less 0 % Retained $ 0.00
Less Previous Payments $ 63,584.15
Total Deductions $ 63,584.15
Amount Due This Estimate $ 4,207.04
Contractor
Engineer
Jay Brothers, Inc.
maxx (,„6„,
Matthew J. Woodruff, P
Date 10— Qle)
Date Cer , ZoOS
ESTIMATE NO. 4(F)
LI 0 LAKES GRADING AND TRAIL WORK
OF LINO LAKES, MINNESOTA
A PROJECT NO. 13849.003
PERIOD ENDING: September 16, 2008
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
1 MOBILIZATION LS 1 1.0 $ 2,300.00 $ 2,300.00
2 COMMON EXCAVATION CY 2,972 2,972.0 $ 4.50 $ 13,374.00
3 CLASS 5 AGGREGATE BASE TN 1,300 1,049.0 $ 12.50 $ 13,112.50
4 2" 2360 BITUMINOUS WEAR COURSE TN 275 283.2 $ 52.63 $ 14,904.29
5 TOPSOIL BORROW (LV) CY 1,800 1,822.0 $ 8.00 $ 14,576.00
6 SILT FENCE (INSTALL AND REMOVE) LF 1,600 1,560.0 $ 2.00 $ 3,120.00
TOTAL $ 61,386.79
CHANGE ORDER NO. 1
1 ADDITIONAL COMMON EXCAVATION CY 430.0 430.0 $ 4.50 $ 1,935.00
2 ADDITIONAL TOPSOIL BORROW CY 217.0 217.0 $ 8.00 $ 1,736.00
TOTAL CHANGE ORDER NO. 1 $ 3,671.00
CHANGE ORDER NO. 2
1 BIOMIX MULCH - DELIVERED CY 60.0 60.0 30.89 $ 1,853.40
2 BIOMIX MULCH - PLACED LS 1.0 1.0 880 $ 880.00
TOTAL CHANGE ORDER NO. 2 $ 2,733.40
TOTAL ESTIMATE NO. 4(F) $ 67,791.19
•
•
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
Saint Paul, MN September 16 20 07 Proj. No. 13849.003 Change Order No. 2
To Jay Brothers, Inc.
for Lino Lakes Grading and Trail Work
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
June 11 , 20 07 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decrease) (ange) the contract sum by
Two Thousand Seven Hundred Thirty -Three Dollars and 40/100 ($ 2,733.40 ).
This change order provides for changes in the work of this contract according to the attached itemization.
Item No. Description Unit Contract Quantity Unit Price Amount to Date
1 Biomix Mulch - Delivered CY 60 $ 30.89 $ 1,853.40
2 Biomix Mulch - Placed LS 1 $880.00 $ 880.00
TOTAL $ 2,733.40
• NET CHANGE =
Amount of Original Contract
Additions approved to date (Change Order No. 1
Deductions approved to date (Nos. )
Contract amount to date
Amount of this Change Order (Add) (Deduct) (Ne-Ch ge)
Revised Contract Amount
Approved City of Lino Lakes
• Approved Jay Brothers, Inc.
By k(titNVCosL3.
Owner
Contractor
$ 2,733.40
$ 63,99725
$ 3,671.00
$
67,668.25
$ 2,733.40
$ 70,401.65
TKDA
By l� U (�(.� (/lm
M
LIA
atthew J. Woodruff, P.E.
White - Owner
Pink - Contractor
Blue - TKDA
•
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
COMPENSATING
Saint Paul, MN September 16 20 08 Proj. No. 13849.003 Change Order No. 3
To Jay Brothers, Inc.
for Lino Lakes Grading and Trail Work
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
June 11 , 20 07 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decrease) (net- slange) the contract sum by
Two Thousand Six Hundred Ten Dollars and 46/100 ($ 2,610.46 ).
This change order shows the actual quantities installed at the unit price bid amounts (see attached itemization):
NET CHANGE =
$ (2,610.46)
Amount of Original Contract $ 63,997.25
Additions approved to date (Change Order No. 1 and Change Order No. 2 ) $ 6,404.40
Deductions approved to date (Nos. )
Contract amount to date
Amount of this Change Order (tom) (Deduct) (Ne -Ghaage)
Revised Contract Amount
Approved City of Lino Lakes
By
Owner
Approved Jay Brothers, Inc.
Contractor
• By KILtN\J■fa- q/C'Qq■
$ 70,401.65
$ (2610.46)
$ 67,791.19
TKDA
White - Owner
Pink - Contractor
Blue - TKDA
COMPENSATING CHANGE ORDER NO. 3
LINO LAKES GRADING AND TRAIL WORK
C 4100
OF LINO LAKES, MINNESOTA
ROJECT NO. 13849.003
PERIOD ENDING: September 16, 2008
ITEM CONTRACT QUANTITY UNIT AMOUNT NET CONTRACT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE CHANGE AMOUNT
1 MOBILIZATION LS 1 1.0 $ 2,300.00 $ 2,300.00 $ $ 2,300.00
2 COMMON EXCAVATION CY 2,972 2,972.0 $ 4.50 $ 13,374.00 $ - $ 13,374.00
3 CLASS 5AGGREGATE BASE TN 1,300 1,049.0 $ 12.50 $ 13,112.50 $ (3,137.50) $ 16,250.00
4 2" 2360 BITUMINOUS WEAR COURSE TN 275 283.2 $ 52.63 $ 14,904.29 $ 431.04 $ 14,473.25
5 TOPSOIL BORROW (LV) CY 1,800 1,822.0 $ 8.00 $ 14,576.00 $ 176.00 $ 14,400.00
6 SILT FENCE (INSTALL AND REMOVE) LF 1,600 1,560.0 $ 2.00 $ 3,120.00 $ (80.00) $ 3,200.00
TOTAL $ 61,386.79 $ (2,610.46) $ 63,997.25
CHANGE ORDER NO. 1
1 ADDITIONAL COMMON EXCAVATION CY 430.0 430.0 $ 4.50 $ 1,935.00 $ - $ 1,935.00
2 ADDITIONAL TOPSOIL BORROW CY 217.0 217.0 $ 8.00 $ 1,736.00 $ - $ 1,736.00
TOTAL CHANGE ORDER NO. 1 $ 3,671.00 $ - $ 3,671.00
CHANGE ORDER NO. 2
1 BIOMIX MULCH - DELIVERED CY 60.0 60.0 30.89 $ 1,853.40 $ - $ 1,853.40
2 BIOMIX MULCH - PLACED LS 1.0 1.0 880 $ 880.00 $ - $ 880.00
TOTAL CHANGE ORDER NO. 2 $ 2,733.40 $ - $ 2,733.40
TOTAL COMPENSATING CHANGE ORDER NO. 3
•
$ 67,791.19 $ (2,610.46) $ 70,401.65