HomeMy WebLinkAbout2008-150 Council ResolutionCouncil Membei0 i Donnelibtroduced the following resolution and moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 08-150
APPROVING PAYMENT REQUEST NO. 3 AND CHANGE ORDER NO. 1— 2008
SURFACE WATER MANAGEMENT PROJECTS
WHEREAS, pursuant to the resolution of the Council adopted August 11, 2008, awarding the
contract for 2008 Surface Water Management Projects, Outfall Cleaning to Penn Contracting,
Inc.;
WHEREAS, a complete breakdown is detailed in Payment No. 3 and Change Order no. 1;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
Payment No. 3 in the amount of $11,012.40 and Change Order No. 1 in the amount of $9,112.00,
which results in a total project cost of $92,843.00 are approved for the 2008 Surface Water
Management Project
Julianne} Bartell, Cit CI
Adopted by the Lino Lakes City Council this 15th day of December, 2008.
The motion for the adoption of the foregoing resolution was duly seconded by Council Member
Reinert and upon vote being taken thereon, the following voted in favor
thereof: O'Donnell, Reinert, Gallup, Stoltz, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
AGENDA ITEM 1C
• STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: December 15, 2008
TOPIC: Resolution No. 08 —150, Approving Payment Request
No. 3 and Change Order No. 1, 2008 Surface Water
Management Project.
VOTE REQUIRED: Simple Majority
BACKGROUND:
At the August 11, 2008 meeting, City Council awarded the 2008 Surface Water Management,
Outfall Cleaning Contract to Penn Contracting, Inc.
Penn Contracting, Inc. is requesting City approval of Payment No. 3 in the amount of $11,012.40
and Change Order No. 1 in the amount of $9,112.00. A copy of the payment and change order is
attached. The change order covers two areas of additional work that was performed. After
working with residents on Pheasant Run South (Project 8) the scope of that project was modified
• to include the installation of draintile and rock. An additional project (Project 14) was requested
by Rice Creek Watershed District in October after a review of the overall drainage of Behm's\
Century Farms indicated that ditching work south of Palomino Trail was required to remove
sedimentation and allow for proper drainage.
Staff recommends approval of Payment No. 3 in the amount of $11,012.40 and Change Order
No. 1 in the amount of $9,112.00, which results in a total project cost of $92,843.00.
RECOMMENDATION:
Staff recommends approval of Resolution Number 08 — 150, Approving Payment Request No. 3
and Change Order No. 1, 2008 Surface Water Management Project.
•
•
•
TKDA
ENGINEERS • ARM-ITEMS • PLANNERS
444 Cedar Street, Suite 1500
Saint Paid, MN 55101 -2140
(651) 292 -4400
(651) 292 -0083 Fax
www.tkda.com
Proj. No. 14043.003 Cert. No. 3 St. Paul, MN, December 3 , 2008
To City of Lino Lakes, Minnesota
This Certifies that Penn Contracting, Inc.
For 2008 Surface Water Management Projects
Is entitled to Eleven Thousand Twelve Dollars and 40/100 -($ 11.012.40)
being 3rd estimate for partial payment on contract with you dated August 13 , 2008
Received payment in full of above Certificate. TKDA
Owner
, Contractor
, 20
Matthew J. Woodruff P.E.
RECAPITULATION OF ACCOUNT
An Employee Owned Company Promoting Affimaalire Action and Equal Opportunity
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
83,731.00
AR previous payments
$
73,084.45
All previous credits
Extra No.
Change Order No. 1
$
9,112.00
n n
n n
n It
Credit No.
$ -
n n
n n
n n
n n
AMOUNT OF THIS CERTIFICATE
$
11,012.40
Totals
$
92843.00
$
84,096.85
$ -
Credit Balance
$
-
There will remain unpaid on contract after
payment of this Certificate
$
8,746.15
$
92,843.00 t $
927843.001 $
An Employee Owned Company Promoting Affimaalire Action and Equal Opportunity
TKDA
Engineers - Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 3 Period Ending December 3 , 20 08 Page 1 of 1 Proj. No.14043.003
Contractor Penn Contracting. Inc.. Original Contract Amount $83.731.00
Project 2008 Surface Water Management Projects
Location City of Lino Lakes. Minnesota
Total Contract Work Completed $ 88,523.00
Total Approved Credits $ 0.00
Total Approved Extra Work Completed $ 0.00
Approved Extra Orders Amount Completed $ 0.00
Total Amount Earned This Estimate $ 88,523.00
Less Approved Credits $ 0.00
Less 5 %Retained $ 4,426.15
Less Previous Payments $ 73,084.45
Total Deductions $ 77,510.60
Amount Due This Estimate $ 11,012.40
Contractor Date
Penn Contracting, Inc.
41) Engineer Date
Matthew J. Woodruff P.E.
ESTIMATE NO. 3
PERIOD ENDING: December 3, 2008
2008 SURFACE WATER MANAGEMENT PROJECT
CITY OF LINO LAKES, MINNESOTA
ATKDA PROJECT NO. 14043.003
M CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
PROJECT 1 - 496 LONESOME PINE
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2
BUILD CATCH BASIN OVER EXISTING 21" ST. SEWER TYPE 409 EA 1.0 1.0 $ 4,131.00 $ 4,131.00
3 4" PERFORATED DRAINTILE WITH ROCK & FABRIC WRAP LF 120.0 125.0 $ 20.00 $ 2,500.00
4 INSTALL YARD DRAIN BOX EA 1.0 1.0 $ 3,450.00 $ 3,450.00
5 TOPSOIL CY 20.0 - $ 50.00 $
6 SILT FENCE LF 30.0 20.0 $ 5.00 $ 100.00
7 SPRINKLER REPAIR LS 1.0 - $ 650.00 $
8 SOD SY 1,000.0 150.0 $ 4.00 $ 600.00
• 9 DRAINTILE TEES WITH CAPS EA - 3.0 $ 150.00 $ 450.00
• 10 REMOVE BUSH AT HOMEOWNER'S REQUEST LS 1.0 $ 250.00 $ 250.00
SUBTOTAL PROJECT 1 $ 11,881.00
PROJECT 2 - OLD BIRCH STREET
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN STORM SEWER PIPE LF 90.0 90.0 $ 10.00 $ 900.00
3 CLEAN/OPEN STORM SEWER OUTFALL EA 6.0 6.0 $ 1,200.00 $ 7,200.00
4 SEED / RESTORATION LS 1.0 1.0 $ 700.00 $ 700.00
SUBTOTAL PROJECT 2 $ 9,200.00
PROJECT 3 - BIRCH STREET
1 MOBILIZATION EA 1.0 - $ 400.00 $
2 COMMON EXCAVATION CY 40.0 - $ 75.00 $
3 SOD SY 200.0 - $ 4.00 $
•4 SILT FENCE LF 50.0 - $ 5.00 $
SUBTOTAL PROJECT 3 $
PROJECT 4 - RUFFED GROUSE COURT
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN /OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,500.00 $ 2,500.00
3 SEED / RESTORATION LS 1.0 1.0 $ 1,000.00 $ 1,000.00
• 4 DITCH TO DRAIN LF - 50.0 $ 10.00 $ 500.00
• 5 REMOVE CLUMP OF TREES LS 1.0 $ 500.00 $ 500.00
SUBTOTAL PROJECT 4 $ 4,900.00
PROJECT 5 - OSPREY COURT
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN/OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,500.00 $ 2,500.00
3 SEED / RESTORATION LS 1.0 1.0 $ 550.00 $ 550.00
SUBTOTAL PROJECT 5 $ 3,450.00
PROJECT 6 - HODGSON ROAD
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN/OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,000.00 $ 2,000.00
3 DITCHING LF 150.0 100.0 $ 14.00 $ 1,400.00
4 SEED / RESTORATION LS 1.0 1.0 $ 1,000.00 $ 1,000.00
SUBTOTAL PROJECT 6 $ 4,800.00
PROJECT 7 - LAMOTTE CIRCLE
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN STORM SEWER PIPE LF 500.0 500.0 $ 10.00 $ 5,000.00
3 SEED / RESTORATION LS 1.0 1.0 $ 1,500.00 $ 1,500.00
• 4 ADDITIONAL MOBILIZATION LS - 1.0 $ 1,500.00 $ 1,500.00
•. 5 CLEAN/OPEN STORM SEWER OUTFALL LS 1.0 $ 2,500.00 $ 2,500.00
• 6 CLEAR AND GRUB BRUSH/SMALL TREES LS 1.0 $ 500.00 $ 500.00
• 7 EXTEND OUTFALL PIPE LS 1.0 $ 800.00 $ 800.00
• 8 PLACE RIP RAP, ABOUT 8 CY LS 1.0 $ 1,600.00 $ 1,600.00
SUBTOTAL PROJECT 7 $ 13,800.00
ESTIMATE NO. 3
2008 SURFACE WATER MANAGEMENT PROJECT
CITY OF UNO LAKES, MINNESOTA
TKDA PROJECT NO. 14043.003
OrEM
NO. DESCRIPTION
PERIOD ENDING: December 3, 2008
CONTRACT QUANTITY UNIT AMOUNT
UNIT QUANTITY TO DATE PRICE TO DATE
PROJECT 8 - PHEASANT RUN SOUTI{
1 MOBIUZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAR AND GRUB TREES EA 2.0 - $ 400.00 $
3 SALVAGE & REINSTALL CHAIN UNK FENCE LF 200.0 - $ 6.00 $ -
4 TOPSOIL BORROW CY 40.0 16.0 $ 50.00 $ 800.00
5 SPRINKLER REPAIR LS 1.0 - $ 500.00 $ -
6 SOD SY 1,000.0 320.0 $ 4.00 $ 1,280.00
7 DRAINTILE (Change Order No. 1) LF 100.0 100.0 $ 25.00 $ 2,500.00
8 YARD DRAINT BOX (Change Order No. 1) EA 2.0 2.0 $ 1,500.00 $ 3,000.00
9 LANDSCAPE ROCK (Change Order No. 1) LS 1.0 1.0 $ 1,500.00 $ 1,500.00
SUBTOTAL PROJECT 8 $ 9,480.00
PROJECT 9 - MARVY STREET
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN STORM SEWER PIPE LF 90.0 90.0 $ 10.00 $ 900.00
3 CLEAN /OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,000.00 $ 2,000.00
4 COMMON EXCAVATION CY 40.0 40.0 $ 40.00 $ 1,600.00
5 SEED / RESTORATION LS 1.0 1.0 $ 1,500.00 $ 1,500.00
SUBTOTAL PROJECT 9 $ 6,400.00
PROJECT 10 - APOLLO MEADOWS
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 PLACE RIP RAP AT FLARED ENDS CY 25.0 25.0 $ 200.00 $ 5,000.00
3 SEED / RESTORATION LS 1.0 1.0 $ 2,000.00 $ 2,000.00
• •
4 CEAN/OPEN STORM SEWER OUTFALL EA - 2.0 $ 1,500.00 $ 3,000.00
SUBTOTAL PROJECT 10 $ 10,400.00
PROJECT 11 - 4Th AVENUE
1 MOBIUZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN /OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,200.00 $ 2,200.00
3 SEED / RESTORATION LS 1.0 1.0 $ 1,000.00 $ 1,000.00
• 4 REMOVE AND DISPOSE TREE STUMPS LS - 1.0 $ 400.00 $ 400.00
SUBTOTAL PROJECT 11 $ 4,000.00
PROJECT 12 - 79TH STREET AND NANCY DRIVE
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 CLEAN STORM SEWER PIPE LF 200.0 200.0 $ 10.00 $ 2,000.00
3 CLEAN/OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,200.00 $ 2,200.00
4 SEED / RESTORATION LS 1.0 1.0 $ 1,000.00 $ 1,000.00
SUBTOTAL PROJECT 12 $ 5,600.00
•
PROJECT 13 - HIGHLAND MEADOWS
1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00
2 PLACE RIP RAP AT FLARED END SECTIONS CY 5.0 6.0 $ 250.00 $ 1,500.00
3 SEED / RESTORATION LS 1.0 1.0 $ 600.00 $ 600.00
SUBTOTAL PROJECT 13 $ 2,500.00
PROJECT 14 - PALOMINO TRAIL DITCH WORK
(Chanae Order No. 11
1 MOBILIZATION LS 1.0 1.0 $ 500.00 $ 500.00
2 EXCAVATOR WITH OPERATOR HR 4.5 4.5 $ 150.00 $ 675.00
3 LABOR HR 13.5 13.5 $ 62.00 $ 837.00
4 MISCELLANEOUS MATERIALS LS 1.0 1.0 $ 100.00 $ 100.00
SUBTOTAL PROJECT 14 $ 2,112.00
TOTAL ESTIMATE NO. 3
$ 88,523.00
•
•
•
CHANGE ORDER
TKDA
Engineers- Architects - Planners
Saint Paul, MN December 3 20 08 Proj. No. 14043.003 Change Order No. 1
To Penn Contracting. Inc.
for 2008 Surface Water Management Projects
for City of Lino Lakes. Minnesota
You are hereby directed to make the following change to your contract dated
August 13 , 20 08 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decFease) (not change) the contact sum by
Nine Thousand One Hundred Twelve Dollars and 00 /100 (($ 9.112.00)
This change order provides for changes in the work of this contract according to the attached itemization.
NET CHANGE =
Amount of Original Contract
Additions approved to date (Nos.
Deductions approved to date (Nos.
$ 9,112.00
$ 83,731.00
Contract amount to date $ 83,731.00
Amount of this Change Order (Add) (Deduet) (Ne-G ge) $ 9,112.00
Revised Contract Amount $ 92843.00
Approved City of Lino Lakes TKDA
By By
Matthew J. Woodruff P.E.
Approved Penn Contracting. Inc. White - Owner
Contractor Pink - Contractor
Blue - TKDA
By
CHANGE ORDER NO. 1
2008 SURFACE WATER MANAGEMENT PROJECT
CITY OF LINO LAKES, MINNESOTA
TKDA PROJECT NO. INTEM
NO. DESCRIPTION
PERIOD ENDING: December 3, 2008
CONTRACT QUANTITY UNIT AMOUNT
UNIT QUANTITY TO DATE PRICE TO DATE
CHANGE ORDER NO. 1
PROJECT 8 - PHEASANT RUN SOUTH
7 DRAINTILE LF 100.0 100.0 $ 25.00 $ 2,500.00
8 YARD DRAIN BOX EA 2.0 2.0 $ 1,500.00 $ 3,000.00
9 LANDSCAPE ROCK LS 1.0 1.0 $ 1,500.00 $ 1,500.00
SUBTOTAL PROJECT 8 $ 7,000.00
PROJECT 14 - PALOMINO TRAIL DITCH WORK
1 MOBILIZATION LS 1.0 1.0 $ 500.00 $ 500.00
2 EXCAVATION WITH OPERATOR HR 4.5 4.5 $ 150.00 $ 675.00
3 LABOR HR 13.5 13.5 $ 62.00 $ 837.00
4 MISCELLANEOUS MATERIALS LS 1.0 1.0 $ 100.00 $ 100.00
SUBTOTAL PROJECT 14 $ 2,112.00
TOTAL FOR CHANGE ORDER NO. 1 $ 9,112.00