HomeMy WebLinkAbout2011-065 Council Resolution•
•
Council Member Roeser introduced the following resolution and moved its
adoption:
CITY OF LINO LAKES
RESOLUTION NO. 11 -65
RESOLUTION APPROVING PARTIAL PAYMENT AND CHANGE ORDER,
2011 STREET OVERLAY PROJECT
WHEREAS, pursuant to an advertisement for bids for the construction of 2011 Street Overlay
Project, bids were received, opened and tabulated according to law,
WHEREAS, changes were made to the original contract as described in Change Order #1,
AND WHEREAS, North Valley, Inc was awarded the contract;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. The Mayor and Clerk are hereby authorized and directed to approve payment #1 and change
order # 1 for the construction of the 2011 Street Overlay Project according to the plans and
specifications approved by the City Council and on file in the office of the City Clerk.
Adopted by the Lino Lakes City Council this 27th day of June, 2011.
The motion for the adoption of the foregoing resolution was duly seconded by Council Member
O' Donnell and upon vote being taken thereon, the following voted in favor
thereof: Roeser, O'Donnell, Rafferty, Reinert
The following voted against same: none ( Absent - Gallup)
Whereupon said resolution was declared duly passed and adopted.
•
AGENDA ITEM 6E
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: June 27, 2011
TOPIC: Resolution No. 11 -65, Approving Change Order #1
and Partial Payment #1, 2011 Street Overlay Project
Vote Required: Simple Majority
BACKGROUND:
Sealed bids were received and publicly opened at 11:30 a.m. on March 30, 2011. The
contractor, North Valley, Inc. was awarded the contract at $ 298,100.50. The Engineer's
• Estimate was $ 318,930.00.
After the award of the contract, culvert work was added and deleted from the original
project. The change in work has resulted in a decrease in the contract of $1,105.50 for a
total of $296,995.00. Attached is a copy of Pay Estimate 1R and Change Order 1 R.
North Valley, Inc. is in agreement with the change of work. The final completion date for
this project is July 31, 2011.
RECOMMENDATION:
Staff recommends that Resolution No. 11 —65 Approving Partial Payment and Change
Order for the 2011 Street Overlay Project be adopted.
TKDA
ENGINEERING • ARCHITECTURE • PLANNING
fill) The right time. The right people. The right company
444 Cedar Street, Suite 1500
Saint Paul, MN 55101
(651) 292-4400
(651) 292 -0083 Fax
www.tkda.com
Proj. No. 14817.002 Cert. No. 1R St. Paul, MN, June 15 , 2011
To City of Lino Lakes, Minnesota
This Certifies that North Valley, Inc.
For 2011 Overlay Project
Is entitled to One Hundred Seventy Four Thousand One Hundred Thirty Six Dollars and 02/100 ($ 174,136.02)
being 1st- Revised estimate for partial payment on contract with you dated April 11 , 2011
Owner
, Contractor
Received
of above Certificate. TKDA
North Valley, Inc..
L.fCf'�v� , /
, 2011
es E. Studenski, P.E.
RECAPITULATION OF ACCOUNT
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
298,100.50
All previous payments
$
-
All previous credits
Change Order No. 1
$
(1,105.50)
$ -
AMOUNT OF THIS CERTIFICATE
$
174,136.02
Totals
$
296,995.00
$
174,136.02
$ -
Credit Balance
$
-
There will remain unpaid on contract after
payment of this Certificate
$
122,858.98
$
296,995.00
1 $
296,995.00
$ -
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
•
Estimate No. 1R
Contractor
Project
Location
TKDA
Engineers - Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Period Ending June 15 , 20 11 Page 1 of 1 Proj. No. 14817.002
North Valley, Inc. Original Contract Amount $298,100.50
2011 Overlay Project
City of Lino Lakes, Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed
Approved Extra Orders Amount Completed
Total Amount Earned This Estimate
Less Approved Credits
Less 5 % Retained
Less Previous Payments
Total Deductions
Amount Due This Estimate
Contractor
Engineer
James E. Studenski, P.E.
0.00
0.00
9,165.05
0.00
183,301.07
0.00
0.00
183,301.07
9,165.05
174,136.02
Dated /72a //
Date G — �5 — 2.0 11 l
•
•
•
PAYMENT ESTIMATE NO. 1R PERIOD ENDIN( June 15, 2011
2011 OVERLAY PROJECT
CITY OF LINO LAKES, MINNESOTA
TKDA PROJECT NO. 14817.002
ITEM
NO.
GENERAL
DESCRIPTION
QUANTITY UNIT AMOUNT
QUANTITY UNIT TO DATE PRICE TO DATE
1 MOBILIZATION 1 LS 1.0 $ 6,600.00 $ 6,600.00
2 TRAFFIC CONTROL 1 LS 1.0 $ 1,000.00 $ 1,000.00
3 TOPSOIL BORROW WITH SEED 180 CY 14.0 $ 5.00 $ 70.00
4 SODDING 100 SY 0.0 $ 4.10 $ -
5 EROSION CONTROL BLANKET CATEGORY 3 WITH SEED 600 SY 255.0 $ 1.30 $ 331.50
6 SILT FENCE 200 LF 260.0 $ 2.58 $ 670.80
7 BIODEGRADEABLE FIBER EROSION CONTROL ROLLS 60 LF 98 $ 3.75 $ 367.50
SUBTOTAL GENERAL $ 9,039.80
STORM SEWER AND WATER QUALITY
8 REMOVE 15" CMP CULVERT
9 REMOVE 30" RCP CULVERT
10 REMOVE AND DISPOSE OF CATCH BASIN
11 INSTALL 15" RCP STORM SEWER
12 INSTALL 15" RCP FES
13 INSTALL 30" RCP STORM SEWER
14 INSTALL 30" RCP FES
15 CONSTRUCT 4' CURB CUT
16 CONSTRUCT INFILTRATION DITCH WITH NATIVE
SEEDING
17 REHABILITATE CATCH BASINS
SUBTOTAL STORM SEWER AND WATER QUALITY
STREET
100 LF 170.0 $ 7.25 $ 1,232.50
60 LF 0.0 $ 10.30 $
2 EA 0.0 $ 206.00 $
100 LF 160.0 $ 30.00 $ 4,800.00
4 EA 5.0 $ 570.00 $ 2,850.00
60 LF 0.0 $ 59.00 $ -
2 EA 0.0 $ 775.00 $
4 EA 0.0 $ 250.00 $
250 LF 0.0 $ 11.00 $
13 EA 13.0 $ 335.00 $ 4,355.00
$ 13,237.50
18 ADJUST GATE VALVE 1 EA 0.0 $ 206.00 $ -
19 ADJUST MANHOLE 1 EA 1.0 $ 375.00 $ 375.00
20 RECLAIM BITUMINOUS 19,700 SY 17996.0 $ 0.69 $ 12,417.24
21 HAUL OUT EXCESS MILLINGS (LV) 1,000 CY 1236.0 $ 6.95 $ 8,590.20
22 RESHAPE MILLINGS (3% CROWN) 58 RS 58 $ 160.00 $ 9,280.00
23 SAW CUT BITUMINOUS 300 LF 240.0 $ 2.50 $ 600.00
24 SAWCUT CONCRETE 75 LF 0.0 $ 4.50 $ -
25 REMOVE BITUMINOUS DRVEWAY PAVEMENT 180 SY 0.0 $ 4.85 $
26 REMOVE CONCRETE DRIVEWAY PAVEMENT 120 SY 0.0 $ 8.00 $ -
27 SUBGRADE EXCAVATION 122 CY 108.0 $ 11.00 $ 1,188.00
28 SELECT GRANDULAR BORROW 122 CY 108.0 $ 15.00 $ 1,620.00
29 GEOTEXTILE STABILIZATION FABRIC 500 SY 0.0 $ 2.00 $
30 AGGREGATE BASE FOR DRIVEWAYS 90 TN 0.0 $ 16.50 $
31 BITUMINOUS BASE CORSE 2360 (LVNW 35030) 2,330 TN 2304.5 $ 48.85 $ 112,574.33
32 BITUMINOUS MATERIAL FOR TACK COAT 990 GAL 0.0 $ 3.50 $ -
33 BITUMINOUS WEARING COURSE 2360 (LVWE 45030) 1,760 TN 0.0 $ 55.85 $
34 BITUMINOUS CURBING 450 LF 0.0 $ 3.50 $
35 BITUMINOUS DRIVEWAY PAVEMENT 180 SY 0 $ 16.50 $
36 6" CONCRETE DRIVEWAY PAVEMENT 50 SY 0.0 $ 48.85 $ -
SUBTOTAL STREET $ 146,644.77
CHANGE ORDER NO. 1R
1 BITUMINOUS CURB REMOVAL LF 874 $ 3.50 $ 3,059.00
2 INLET PROTECTION EA 16 $ 150.00 $ 2,400.00
3 CLEARING AND GRUBBING EA 5 $ 250.00 $ 1,250.00
4 INSTALL CATCH BASIN STRUCTURES EA 2 $ 2,950.00 $ 5,900.00
5 INSTALL CASTINGS EA 2 $ 885.00 $ 1,770.00
6 RIP RAP (CLASS 3) CY 0 $ 300.00 $
TOTAL CHANGE ORDER NO. 1R $ 14,379.00
TOTAL PAYMENT ESTIMATE NO. 1 REVISED $ 183,301.07
•
•
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
Saint Paul, MN June 15 20 11 Proj. No. 14817.002 Change Order No. 1R
To North Valley, Inc., 20015 Iguana St NW, Suite 100, Nowthen, Minnesota 55330
for 2011 Overlay Project
for City of Lino Lakes Minnesota
You are hereby directed to make the following change to your contract dated
April 11 , 20 11 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decrease) (n� t� age) the contract suin by: One Thousand One Hundred
Five Dollars and 50 /100 ($1,105.50).
This change order provides for changes in the work of this contract according to the attached itemization.
NET CHANGE =
$ (1,105.50)
Amount of Original Contract $ 298,100.50
Additions approved to date (Nos )
Deductions approved to date (Nos. )
Contract amount to date
Amount of this Change Order (Add) (Deduct) (No Change)
Revised Contract Amount
Approved TKDA
City of Lino Lakes, Minnesota
By By
North Valley, Inc.
By t f7 <.7
$ 298,100.50
$ (1,105.50)
$ 296, 995.00
ones E. Studenski, P.E.
White - Owner
Pink - Contractor
Blue - TKDA
CHANGE ORDER NO. 1R June 14, 2011
2011 OVERLAY PROJECT
ATY OF LINO LAKES, MINNESOTA
DA PROJECT NO. 14817.002
ITEM
NO.
DESCRIPTION
UNIT CONTRACT
UNIT QUANTITY PRICE AMOUNT
1 Bituminous Curb Removal LF 874 $ 3.50 $ 3,059.00
2 Inlet Protection EA 16 $ 150.00 $ 2,400.00
3 Clearing and Grubbing EA 5 $ 250.00 $ 1,250.00
4 Install Catch Basin Structures EA 2 $ 2,950.00 $ 5,900.00
5 Install Castings EA 2 $ 885.00 $ 1,770.00
6 Rip Rap (Class 3) CY 0 $ 300.00 $
7 Remove 30" RCP Culvert LF -60 $ 10.30 $ (618.00)
8 Remove and Dispose of Catch Basin EA -2 $ 206.00 $ (412.00)
9 Install 30" RCP Storm Sewer LF -60 $ 59.00 $ (3,540.00)
10 Install 30" RCP FB EA -2 $ 775.00 $ (1,550.00)
11 Remove Subgrade Excavation CY -122 $ 11.00 $ (1,342.00)
12 Select Granular Borrow CY -122 $ 15.00 $ (1,830.00)
13 Construct 4' Curb Cut EA -4 $ 250.00 $ (1,000.00)
14 Construct Infiltration Ditch with Native Seed LF -250 $ 11.00 $ (2,750.00)
15 6" Concrete Driveway Pavement SY -50 $ 48.85 $ (2,442.50)
$
TOTAL CHANGE ORDER NO. 1R $ (1,105.50)
•
•