CITY OF LINO LAKES
RESOLUTION NO. 05 -54
RESOLUTION ACCEPTING BIDS AND AWARDING A CONSTRUCTION CONTRACT —
WELL NO. 5.
WHEREAS, pursuant to an advertisement for bids for the construction of the Well No. 5 project,
bids were received, opened and tabulated according to law, and the following bids were
received complying with the advertisement:
Contractor Amount of Bid
EH Renner & Sons $158,825.00
Bergerson- Caswell $194,500.00
Engineer's Estimate $174,000.00
AND WHEREAS, it appears that EH Renner & Sons is the lowest responsible bidder;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. The Mayor and Clerk are hereby authorized and directed to enter into a contract with EH
Renner & Sons, in the name of the City of Lino Lakes for the construction of the Well No. 5
project according to the plans and specifications approved by the City Council and on file in
the office of the City Clerk.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposits of the successful bidder and the next
lowest bidder shall be retained until a contract has been signed.
Adopted by the Lino Lakes City Council this 11th day of April 2005.
C
John erges , Mayor
•
•
AGENDA ITEM 6Hi
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: April 11, 2005
TOPIC: Resolution No. 05 -54, Accepting Bids and Awarding Construction
Contract, Well No. 5 Drilling
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND:
Sealed bids were received and publicly opened at 10 :00 a.m. on March 29, 2005. The
results of the bid opening are presented below. City Council action is required to award
a construction contract to the lowest responsible bidder.
Contractor Amount of Bid
EH Renner & Sons $158,825.00
Bergerson - Caswell $194,500.00
Engineer's Estimate $174,000.00
The low bid is approximately 9% below the Engineer's Estimate for this project. A copy
of the complete bid tabulation is attached. This 9% overage falls within the 10%
contingency budgeted for the project.
The final completion date for this project is August 19, 2005.
OPTIONS:
1. Return to staff for further review.
2. Adopt Resolution Number 05 -54, Accepting Bids and Awarding a Construction
Contract to EH Renner & Sons for Well No. 5.
3. Not adopt Resolution No. 05 -54.
RECOMMENDATION:
Option No. 2 - Staff recommends adoption of Resolution Number 05 -54.
•
TABULATION OF BIDS
CONSTRUCTION OF WELL NO. 5
CITY OF LINO LAKES, MINNESOTA
COMMISSION NO. 13089-01
BIDS OPENED: MARCH z9,00nSAT1u:0oAm
*DENOTES ERROR IN BIDDERS CALCULATION
TEM
NO.
DESCRIPTION
QUANTITY
ENGINEER'S ESTIMATE
UNIT TOTAL
UNIT PRICE AMOUNT
EH RENNER & SONS
UNIT TOTAL
PRICE AMOUNT
•
TKDA
BERGERSON-CASWELL
UNIT TOTAL
PRICE AMOUNT
CONSTRUCTION OF NO. s_
The moving of alt drilting equipment and malerials Onto the site,
setting up the equipment, removal of equtpment. and clean-up of the
site upon completion oF Ihe Work, togother with alt items of
constuction and testing excepl for those ilernlzed separately below.
2 The furnishing, installation, and maintenance of erosion controls.
The drilling by cable tool methods of 24-inch diameter cased hole
3 through the glacia drift formation and to refusal, o"maximum 10
feet, into the bedrock, including materials.
The drilling by cable tool methods of 23-inch diameter open hole
through the Prairie du Chien-Jordan formations.
The furnishing and installing complete of 18-Inch inner casing as
specified.
Fumlshing and placing of pea into the open hole
prior to grouting, arid removal and disposab once grouting is
complete. and placing oE neat cement Eor grouting the arinular
��Uwm�hv�unudm��nnau��
7 vvuc»o�oenumvoo�on
casing.
8 Furnish, place, and shoot the rod( formation with explosives.
Remove from the well rock loosened by explosives or air surging,
and measuring this rock in an approved measuring box.
For moving 750 CFM or larger air compressor onto site, setting up
10 equipment for air surging, and removal v, air compressor from site
pon completion of work.
11 For air surging to develop the Formation.
For installing and removing air compressor, piping, and appurtenant
/u
equipment for eunx.eumnono| air surging required.
Furnish and install in Ihe welt a tesi pump capabte of delivering
c.mmnpmm water from the well, and remove from the well once
/» lest pumping is complete, including rurnisliing sufficient dlscharge
piping and power for operating the test punip.
14 For well testing for yield, u,ommvwn.andlecoverY.____
For installiiig and removing from the well the test pump. piping, alt
15 appurtenant equipment and power for operating Ihe test pump for
each additional yield, drawdown, and recovery lest as required.
.o
6
7
LS
$ 19,202.50
$ 19,202.50
$ 21,000.00
21,000.00
$ 20,000.00
400 LF $ 5.78 $ 2,310.00
70 LF * 247.50 $ 17,325.00
5.00
215.00
$ 2,000.00
$ 15,050.00
5.00
225.00
$
20,000.00
215 LF * 126.50 $ 27,197o0
150 LF 88.00 $ 13,200.00
60 TN y 77.00 $ 4.620.00
115.00
$ 24,725.00
80.00
$ 12,000.00
200.00 $ 43,000.00
85.00 $ 12,750.00
50.00
$ 3,000.00
320.00
$ 6,400.00
200 LB 20.63 $ 4,125.00
500 CY 77.00 $ 38,500.00
LS $ 5,500.00 $ 5,500.00
25.00
60.00
$ 8,000.00
For sand content Tests, as required, includlng tIie taking of the
sample, delivery and testing of the sample and reporting the results.
The collection and analysis of the well water by a qualified approved
taborabory for testing as specified. and preparation of a report.
80. HR $ 192.50 $ 15,400.00
1 LS $ 1.100o0 $ 1.100.00
LS 4,950.00 4,950.00
$ 5,000.00
$ 30,000.00
$ 8,000.00
200.00 $ 16,000.00
500.00
500.00
120.00
360.00
$ 7,200.00
25.06- 5/00.00 _
85.00
5,500.00
$ 42,500.00
$ 5,500.00
165.00 $ 13,200o0
1,000.00 $ 1,000.00
$ 5,000.00
60 HR $ 137.50 8,250o0
�
LS $ 1.375.00 m 1.375.00
a
LS m 55.00 $ 275.00
LS $ 1,100.00 $ 1,100.00
110.00
500.00
$ 5,000.00
$ 6,600.00
10.00
$ 1,100.00
�
500.00
50.00
$ 1,100.00
6,500o0 $ 6,500.00
1400n$
1,000.00 $ 1,000o0
50.00
1,250.00
� 250.00
$ 1,250.00
Page 1
•
TABULATION OF 13I135
CONSTRUCTION OF WELL NO. 5
CITY OF LINO LAKES, MINNESOTA
COMMISSION NO. 13089 -01
BIDS OPENED: MARCH 29, 2005, AT 10:00 AM
*DENOTES ERROR IN BIDDERS CALCULATION
TEM
NO.
DESCRIPTION
Provide a Gam-
amma Log of tip to 285 Linear Feet of cased and open
18 rock hole, if directed by the Engineer.
Provide a color video record of the finished well, if directed by the
19 Engineer.
TOTAL BID AMOUNT
QUANTITY UNIT
1
LS
LS
ENGINEER'S ESTIMATE
UNIT TOTAL
PRICE AMOUNT
$ 1,100.00
$ 1,320.00
$ 1,100.00
$ 1,320.00
$ 174,000_00
EI-I RENNER & SONS
UNIT TOTAL
PRICE AMOUNT
$ 600.00
$ 1,300.00
$ 600.00
$ 1,300.00
$ 158,825.00
.-
TKD4
ENGINEERS - ARCHITECTS - PLANNERS
BERGERSON- CASWELL
UNIT TOTAL
PRICE AMOUNT
$ 1,000.00
$ 700.00
$ 1,000.00
$ 700.00
$ 194,500.00
Page 2