CITY OF LINO LAKES
RESOLUTION NO. 05 -112
RESOLUTION APPROVING CHANGE ORDER NO. 1 AND FINAL PAYMENT FOR
THE 2005 SEALCOAT PROJECT
WHEREAS, the construction of the 2005 Sealcoat Project, including Compensating
Change Order No. 1 has been completed by Pearson Brothers, Inc. and
WHEREAS, the one -year warranty period for this project will begin with the Final
Payment.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
Compensating Change Order No. 1 and Payment Certificate No. 1 (Final) is
approved for a total contract amount of $48,666.65.
Adopted by the City Council this 8t" day of August, 2005.
Ann J.
lair, City Clerk
erg son, Mayor
•
TKDA
ENGINEERS • ARCHITECTS • PLANNERS
1500 PiperJaffray Plaza
444 Cedar Street
Saint Paul, MN 55101 -2140
(651) 292 -4400
(651) 292 -0083 Fax
www.tkda.cam
Proj. No. 13328 -01 Cert. No. 1 FINAL St. Paul, MN, July 14 , 20 05
To City of Lino Lakes, Minnesota
This Certifies that Pearson Bros. Inc.
For 2005 Sealcoating
Owner
, Contractor
Is entitled to Forty -Eieht Thousand Six Hundred Sixty -Six Dollars and 65/100 ($ 48,666.65)
FINAL
being 1st estimate for partial payment on contract with you dated April 25 , 2005
Received payment in full of above Certificate. TKDA
(ACtCi
Pearso Bros. Inc.
.fit , 20 n Thomas D. Prew, P.E.
RECAPITULATION OF ACCOUNT
-44-
An Employee Owned Company Promoung Affirmative Action and Equal Opportunity
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
48 , 235.00
All previous payments
$
-
All previous credits
Extra No.
Compensating Change Order No. 1
$
431.65
$
-
Credit No.
$ -
O 11
11 tl
AMOUNT OF THIS CERTIFICAII,
$
48,666.65
Totals
$
48,666.65
$
48,666.65
$ -
There will remain unpaid on contract after
payment of this Certificate
$
-
$
48,666.65
$
48,666.65
$ -
-44-
An Employee Owned Company Promoung Affirmative Action and Equal Opportunity
TKDA
• Engineers - Architects - Planners Saint Paul, Minnesota 55101
•
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
FINAL
Estimate No. 1 Period Ending July 14 , 20 05 Page 1 of 1 Proj. No. 13328.000
Contractor Pearson Bros. Inc. Original Contract Amount $48, 235.00
Project 2005 Sealcoating
Location City of Lino Lakes, Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed
Approved Extra Orders Amount Comple:ied
Total Amount Earned This Estimate
$ 48,666.65
$ 0.00
0.00
$ 0.00
$ 48,666.65
Date
Less Approved Credits $ 0.00
Less 0 % Retained $ 0.00
Less Previous Payments $ 0.00
Total Deductions $
Amount Due This Estimate
Contractor
Engineer
Pearson Bros. Inc.
Thomas D. Prew, P.E.
- 4 5 -
0.00
48,666.65
/1-151- C'5'
Date July 14. 2005
ESTIMATE NO. 1 FINAL
2005 SEALCOATING
CITY OF LINO LAKES, MINNESOTA
TKDA PROJECT NO. 13328 -01
PERIOD ENDING: July 14, 2005
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
2005 SEALCOATING
1 MODIFIED FA -21/8" TRAP ROCK CHIPS TN 350.0 339.0 $ 30.00 $ 10,170.00
2 CRS -2 ASPHALT GA 8,900.0 6,790.0 $ 0.85 $ 5,771.50
3 CRACK SEALING LB 2,100.0 2,899.0 $ 0.80 $ 2,319.20
SUBTOTAL - 2005 SEALCOATING $ 18,260.70
2005 SEALCOAT (NEW DEVELOPMENT)
1 MODIFIED FA -2 1/8' TRAP ROCK CHIPS TN 595.0 576.0 $ 30.00 $ 17,280.00
2 CRS -2 ASPHALT GA 11,600.0 11,415.0 $ 0.85 $ 9,702.75
3 CRACK SEALING LB 3,100.0 4,279.0 $ 0.80 $ 3,423.20
SUBTOTAL - 2005 SEALCOAT (NEW DEVELOPMENT) $ 30,405.95
TOTAL ESTIMATE NO. 1 FINAL
•
-46-
$ 48,666.65
•
•
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
Compensating
Saint Paul, MN July 14 20 05 Proj. No. 13328 -01 Change Order No. 1
To Pearson Bros. Inc.
for 2005 Sealcoating
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
April 25 , 20 05 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decreaco) (not chango) the contract sum by
Four Hundred Thirty -One and 65//100 Dollars ($ 431.65 ).
COMPENSATING CHANGE ORDER
This change order shows the actual quantities installed at the unit price bid amounts (see attached itemization):
NET CEHANGE =
$ 431.65
Amount of Original Contract $ 48,235.00
Additions approved to date (Nos. ) $ -
Deductiors approved to date (Nos. ) $
Contract amount to date $ 48,235.00
Amount of this Change Order (Add) (Deduct) (No Change) $ 431.65
Revised Contract Amount $ 48,666.65
Approved City of Lino Lakes, Minnesota
Owner
TKDA
By By
Thomas D. Prei, P.E.
Approved Pearson Bros. Inc. White - Owner
Contractor Pink - Contractor
Blue - TKDA
- 4 7 -
CHANGE ORDER NO. 1 (COMPENSATING)
2005 SEALCOATING
CITY OF LINO LAKES, MINNESOTA
TKDA PROJECT NO. 13328 -01
PERIOD ENDING: July 14, 2005
0 T E M CONTRACT QUANTITY UNIT AMOUNT NET CONTRACT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE CHANGE AMOUNT
2005 SEALCOATING
1 MODIFIED FA -2 1/8" TRAP ROCK CHIPS TN 350.0 339.0 $ 30.00 $ 10,170.00 $ (330.00) $ 10,500.00
2 CRS -2 ASPHALT GA 6,900.0 6,790.0 $ 0.85 $ 5,771.50 $ (93.50) $ 5,865.00
3 CRACK SEALING LB 2,100.0 2,899.0 $ 0.80 $ 2,319.20 $ 639.20 $ 1,680.00
SUBTOTAL - 2005 SEALCOATING $ 18,260.70 $ 215.70 $ 18,045.00
2005 SEALCOAT (NEW DEVELOPMENT)
1 MODIFIED FA -2 1/8" TRAP ROCK CHIPS TN 595.0 578.0 $ 30.00 $ 17,280.00 $ (570.00) $ 17,850.00
2 CRS -2 ASPHALT GA 11,600.0 11,415.0 $ 0.85 $ 9,702.75 $ (157.25) $ 9,860.00
3 CRACK SEALING LB 3,100.0 4,279.0 $ 0.80 $ 3,423.20 $ 943.20 $ 2,480.00
SUBTOTAL - 2005 SEALCOAT (NEW DEVELOPMENT) $ 30,405.95 $ 215.95 $ 30,190.00
TOTAL COMPENSATING CHANGE ORDER NO. 1
•
$ 48,666.65 $ 431.65 $ 48,235.00
•
AGENDA ITEM 6C
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: August 8, 2005
TOPIC: Resolution No. 05 -112, Approving Change Order No. 1 and Final
Payment, 2005 Sealcoat Project
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND:
The contractor for the 2005 Sealcoat Project, Pearson Brothers, Inc. is requesting City
approval of Payment Certificate No. 1 (Final) in the amount of $48,666.65. A copy of
the Final Payment is attached. The contractor has satisfactorily completed all work and
has provided all necessary documentation.
The original contract amount was $48,235.00 and the final contract amount is
$48,666.65. Also included within the request for Final Payment is Change Order No. 1,
which is a compensating change order in the amount of $431.65. With this Change
Order, the final contract amount is still $19,760.85 below the Engineer's Estimate of
• $68,427.50.
Approval of the Final Payment will begin the one -year warranty period.
•
OPTIONS:
1. Return to staff for further review.
2. Approve Resolution 05 -112 Approving Change Order No. 1 and Final Payment for
the 2005 Sealcoat Project.
RECOMMENDATION:
Option No. 2 - Staff recommends that Resolution 05 -112 be approved.