HomeMy WebLinkAbout2005-196 Council ResolutionCity Council
MOU Anoka County
December 12, 2005
CITY OF LINO LAKES
RESOLUTION NO. 05 -196
RESOLUTION APPROVING MEMORANDUM OF UNDERSTANDING
WITH COUNTY OF ANOKA
COUNTY STATE AID HIGHWAY 14 RECONSTRUCTION PROJECT
WHEREAS, Anoka County is proposing to reconstruct County State Aid Highway No.
14 (Main Street) from I -35W to I -35E; and
WHEREAS, the City of Lino Lakes and the County of Anoka agree that it is in the best
interest of the traveling public to reconstruct the roadway in accordance with the
preliminary layout dated July 29, 2005; and
WHEREAS, the purpose of the Memorandum of Understaning is to reach general
agreement between the parties regarding the project parameters.
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
• 1. that the City Council hereby approves the Memorandum of Understanding with
the County of Anoka for the reconstruction of County State Aid Highway No. 14
(Main Street) from I -35W to I -35E and authorizes execution of said agreement.
Adopted by the Lino Lakes City Council this 12th day of December, 2005.
ATTE_T
e Bartell, Ci erk
•
•hn J : er• eson, Mayor
•
•
DATED November 29, 2005
MEMORANDUM OF UNDERSTANDING
FOR THE RECONSTRUCTION OF COUNTY STATE AID HIGHWAY 14 (MAIN
STREET) BETWEEN I -35 W AND I -35 E IN THE CITIES OF CENTERVILLE AND
LINO LAKES, MINNESOTA
(S.P. 02- 614 -24)
This Memorandum of Understanding (MOU) is between the County of Anoka, State of Minnesota, a political
subdivision of the State of Minnesota, 2100 Third Avenue North, Anoka, Minnesota, 55303, hereinafter
referred to as "County ", and the City of Lino Lakes, a municipal corporation under the laws of the State
of Minnesota, 600 Town Center Parkway, Lino Lakes, Minnesota 55014 hereinafter referred to as the
"City"
The parties to this MOU agree in principle that construction of County State Project No. 02- 614 -24 referred
to as the "Project" is in the best interest of the traveling public and that the Preliminary Layout as shown in
Exhibit "A" defines the design of the Project.
It is agreed that the Exhibit "A" Layout dated July 29, 2005 has been reviewed and accepted by the parties
except as identified in this MOU and is suitable for preparation of final construction documents. Any
significant changes made hereafter to the design as presented in the Exhibit "A" Layout will require approval
by the parties as an amendment to this MOU or addressed in a separate Joint Powers Agreement (JPA) that
will formalize this MOU. These same changes will require a change in the cost share to include any
additional design engineering cost that may occur.
INTERSECTIONS:
As agreed by the parties, improvements to following City Street intersection have been incorporated in the
Exhibit "A" Layout design:
1. Woodlland Drive
2. 21st Avenue N
It is understood that future improvements may be required at the CSAH 14 and 21St Avenue N intersection to
accommodate improvements for the future interchange at I -35 E. It is understood that future improvements
will need to be made to CSAH 21 and County Road 54 in the future as development occurs Improvements
may include but are not limited to: turn lanes, through lanes, extension of concrete medians. The parties will
meet jointly to consider any future improvements. The costs of these improvements will be determined at the
time of construction and may be shared by the County, City and Developer.
The intersection at 21St Avenue N will be limited to a 3/4 access condition (for 21' Ave., intersection will
allow right in, right out, left in, but no left out) until the interchange at I -35E is reconstructed or development
in the area desires to connect to Main Street at 21St Avenue N. and is expected to produce an unacceptable
level of service (LOS F) on Main Street. Flap - "A" attached to the layout presents how access to Main Street
is anticipated to be achieved in the future upon completion of the I -35E interchange.
J: IProjects\CSAH 141Lino Lakes02- 614- 24MOU.doc
Page 1 of 4
•
•
•
RIGHT OF WAY:
The parties agree that the County will acquire all necessary right -of -way and easements for the Project.
Acquisition of any additional right -of -way and /or easements needed for the improvements to the City street
intersections beyond what is defined in the Exhibit "A" Layout will be the responsibility of the City. The
parties agree that parcels required for the project that are owned by the City will be conveyed to the County
at no cost to the County. It is agreed by the parties that the City shall perform all special assessment searches
required for the Project at no cost to the County. It is agreed by the parties that all necessary right of way and
easements will be in legal possession of the County prior to acceptance of bids for the project.
BITUMINOUS TRAIL AND CONCRETE SIDEWALK:
The parties agree that the construction of the bituminous trail and concrete sidewalk are eligible for federal
funds and that all matching fiends will be contributed by the City. The parties understand that the cost for the
trail and walk includes: bituminous and concrete surfacing, aggregate base, sub - drains if required, soil
correction, excavation, borrow material (granular and topsoil), and turf establishment. The parties agree that
the County will pay for the design of the trail and walk, wetland mitigation required by impacts caused by the
trail and walk, the additional right of way and easements required to construct the trail and walk at the proper
location, and any removal items, with the exception of soils, required to construct the trail and walk. Anoka
County will apply for funds through the Metro Parks Trail Program for possible reimbursement to the City
after construction.
TRAFFIC SIGNALS:
A traffic signal is anticipated at the CSAH 14 /CSAH 21 (20th Avenue N) intersection. The parties agree that
the signal will be installed with this project if the warrants are met.
TRAFFIC CONTROL:
The parties understand and agree that CSAH 14 will be closed with traffic detoured for a period of time to
perform soil correction, and construct the new bridge over Rice Creek. The closure will be limited to the
period of time required to complete the soil correction and construct two paved lanes in the area requiring
soil correction and construct the bridge.
DRIVEWAYS:
The parties agree that all driveways affected by the Project will be reconstructed in kind with the cost of any
upgrades requested by the City including concrete aprons to be the responsibility of the City. Turn - arounds
on driveways will be paid for by the County.
LANDSCAPING /STREETSCAPING:
The parties agree that if the City wishes to include landscaping/streetscape features in the Project, they shall
be designed in accordance with Anoka County Highway Department Landscape /Streetscape Guidelines. The
cost of the design and construction of these features will be the responsibility of the City. The City shall
provide all construction documents including plans, specifications, and estimated quantities and cost to the
County for inclusion in the project bid documents. All construction documents must be submitted to the
County by April 30, 2006.
J: IProjects\CSAH 141Lino Lakes02- 614- 24MOU.doc
Page 2 of 4
•
•
UTILITIES:
The parties agree that the Exhibit "A" Layout does include specific proposed utility locations. The City will
be responsible for the design of any sanitary sewer and water main improvements, which will be incorporated
in the project bid documents. The cost of the design and construction of these features will be the
responsibility of the City. The City's design of the sanitary sewer and water main utilities are to include
plans, specifications, and estimated quantities and cost. All construction documents must be submitted to the
County by April 30, 2006.
PERMITS:
The parties agree that the County will secure all necessary permits for this Project. The City agrees to
coordinate with the County in securing the permits required by the Rice Creek Watershed District. The City
also agrees to secure any permits required for improvements proposed by the City including utilities, and
streetscape items.
SUMMARY:
Upon acceptance and signatures by the parties of this MOU, a separate joint powers agreement for cost share
and maintenance will be prepared by the County for execution by the City and the County prior to acceptance
of bids for this project. The joint powers agreement to follow will formalize all estimated and actual cost
shares. The parties recognize the difficult nature of this project and every effort will be made to reduce the
impacts to adjoining properties. Construction work will be staged to continue daily access to the properties
that do not have alternate access.
In the interim, the attached Exhibit "C" provides an estimate of the construction cost share of the Project and
Exhibit "D" outlines County policy for cost splits on construction projects.
J: IProjectslCSAH 14ILino Lakes02- 614- 24MOU.doc
Page 3 of 4
•
COUNTY OF ANOKA CITY OF LINO LAKES
By: By:
Margaret Langfeld, Chair John Bergeson
Anoka County Board Mayor
of Commissioners
Dated: Dated:
ATTEST:
By: By:
John "Jay" McLinden Gordon Heitke
Anoka County Administrator City Administrator
Dated: Dated:
RECOMMENDED FOR APPROVAL:
By: By:
Douglas W. Fischer, P.E. Michael Grochala
Anoka County Engineer City Community Development Director
APPROVED AS TO FORM AND EXECUTION:
By: By:
Dan Klint Name
Assistant Anoka County Attorney
J: IProjectslCSAH 14ILino Lakes02- 614- 24MOU.doc
Page 4 of 4
•
•
•
STAFF ORIGINATOR:
CITY COUNCIL
MEETING DATE:
TOPIC:
AGENDA ITEM 6B
Michael Grochala
December 12, 2005
Consideration of Resolution No. 05 -196
Approving Memorandum of Understanding with
Anoka County for the Reconstruction of CSAH
14 — I35W to 135E.
ACTION REQUIRED: Simple Majority
BACKGROUND
Anoka County has completed the preliminary plans for the improvement of County State
Aid Highway 14 (Main Street) from I -35W to I -35E and is beginning the final design
process.
Anoka County is requesting City approval of a Memorandum of Understanding (MOU).
The purpose of the MOU is to reach general agreement between the parties regarding
the project parameters. A copy of the MOU is attached for your review.
General.
The intent of the agreement is to establish a baseline of parameters prior to completing
the project final design. The MOU establishes the project scope, anticipated
improvements and responsibilities of the local jurisdictions (Anoka County, City of
Centerville, and Lino Lakes). Upon approval of the MOU, any substantial departures
from the accepted preliminary plan may necessitate changes in funding participation.
Intersection.
Improvements to the intersections of Woodland Drive and 21st Avenue are proposed
with the project. Woodland Avenue will retain full access. Both right and left turn lanes
are proposed at this intersection.
The 21st Avenue intersection straddles the corporate limits of Lino Lakes and
Centerville. The intersection is located approximately 750 feet from the existing I -35E
ramps. The design of the intersection is impacted by the future improvement of the
CSAH 14/1 -35E interchange as well as future traffic projections. The conceptual
interchange layout, prepared by the Minnesota Department of Transportation (Mn /DOT),
includes a loop in the northwest quadrant of the interchange which places the existing
southbound I -35E off ramp approximately 500 feet from the 21st Avenue intersection.
Because of the limited intersection spacing and projected traffic volumes it is unlikely
City Council
MOU Anoka County
December 12, 2005
• that a full access at 21st Avenue can be maintained without greatly impacting future
traffic operations.
•
Anoka County originally proposed a median across the 21st Avenue intersection which
would limit access on both sides of CSAH 14 to right -in, right out movements. Due to
concern from adjacent businesses the County is now proposing a 3/4 intersection that
would allow right -in, right -out and left-in turning movements.
Additionally, Anoka County has refined the conceptual interchange layout to include
direct access to parcels south of main street from a new local street opposite the I -35E
off - ramps. This will be achieved with the future reconstruction of the I -35E Interchange.
From staff's perspective, the issue over the intersection spacing is valid. Given the
potential for development north and south of CSAH 14, a full access at 21st Avenue,
could lead to operational problems along CSAH 14 in the future. The proposed 3/4
intersection provides for the majority of turning movements and coupled with a "backage
road" between 20t" Avenue and 21st Avenue would resolve many of the impacts to
existing businesses. The revised interchange plan addresses these issues.
Right -of -Way.
Anoka County will be responsible for acquiring all right -of -way and easements for the
project. The City is only responsible for acquisition relating to improvements outside of
the existing project limits. The City may need to acquire utility easements along 21st
Avenue, north of Main Street for water and sanitary sewer trunk mains. Any special
assessment searches required for the project will be performed at no cost to the county.
Bituminous Trail.
A bituminous trail is included as part of the project from I -35W to I -35E. The trail is
eligible for federal funds and all matching funds will be contributed by the City for those
portions within Lino Lakes. Funding for the City's portion of the trail will come from our
Municipal State Aid Street account. Anoka County has agreed to apply for funds
throught the Metro Parks Trail Program for possible partial reimbursement to the City
after construction.
Traffic Control.
CSAH 14 will be closed within the regional park and traffic detoured during construction
of the Rice Creek Bridge and areas requiring soil corrections. The closure will be
limited to the time necessary to make these improvements.
Driveways.
• All existing driveways throughout the project area will be replaced in kind. Any
upgrades will be the responsibility of the City. (No upgrades are anticipated).
2
•
City Council
MOU Anoka County
December 12, 2005
Landscapinq /Streetscapinq.
Any landscaping or streetscaping features must be designed in accordance with the
Anoka County Landscape /Streetscape guidelines. All design and construction costs will
be the responsibility of the City. Staff is not proposing any landscaping or streetscaping
design with this project.
Utilities.
The City is responsible for the cost and design of any proposed utility improvements.
Trunk sanitary sewer and water main currently exist under CSAH 14 at 21st Avenue.
The City will need to extend these northerly to a point outside the proposed
improvements.
Permits.
The County is responsible for all permits necessary for the project. The city will be
responsible for permits outside the project scope i.e., utility extensions.
RECOMMENDATION
• Overall the MOU is consistent with anticipated impacts of the project. The only
significant issue is the design of the 21st Avenue intersection. CSAH 14 is a major east -
west corridor through Anoka County. Insuring an adequate transportation system
through the I -35E corridor is critical to promoting new economic development
opportunities as well as maintaining existing ones.
The City has previously taken the lead in planning a transportation system that will
provide long term benefits. In 1998 the City worked with Anoka County to realign Otter
Lake Road and limit access to Main Street to avoid the problems now being
experienced at the 21st Avenue intersection.
•
The proposed I -35E Interchange layout adequately addresses future access to the
properties Tying south of Main Street. The City's estimated share of the $14.7 million
project is $418,389.
Staff is recommending approval of the Memorandum of Understanding with Anoka
County.
ATTACHMENTS
1. Resolution No. 05 -196
2. Memorandum of Understanding