HomeMy WebLinkAbout2006-193 Council Resolution• Council Memberstoltz introduced the following resolution and moved its adoption: CITY OF LINO LAKES RESOLUTION NO. 06 -193 RESOLUTION APPROVING CHANGE ORDER NO. 1 LEGACY AT WOODS EDGE PHASE 2 — STREETLIGHTING IMPROVEMENTS WHEREAS, pursuant to the resolution of the Council adopted April 24, 2006, awarding the construction contract for the Legacy at Woods Edge Phase 1 — Streetlighting Improvements to W.H. Response, and WHEREAS, temporary street lighting was required to insure safety to the travel public on an interim basis until permanent fixtures are available for installation. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO LAKES, MINNESOTA that: 1. Change Order No.1 related to temporary street lighting in the amount of $3,065.00 is hereby approved. u ranne Bartell, ity Jerk JoIKn J. Beg es Mayor Adopted by the Lino Lakes City Council this 27th day of November, 2006. The motion for the adoption of the foregoing resolution was duly seconded by Council Member ca,-i and and upon vote being taken thereon, the following voted in favor thereof: Stoltz, Carlson, O'Donnell, Reinert, Bergeson The following voted against same: Whereupon said resolution was declared duly passed and adopted. • • STAFF ORIGINATOR: CITY COUNCIL MEETING DATE: TOPIC: ACTION REQUIRED: BACKGROUND AGENDA ITEM 1Gi Michael Grochala November 27, 2006 Resolution No. 06 -193, Approving Change Order No. 1, Legacy at Woods Edge Phase 2 — Streetlighting Improvements Simple Majority On April 24, 2006 the City Council awarded the Legacy at Woods Edge Phase 2 — Street lighting Improvements contract to W.H. Response. The current approved contract amount is $483,135.84. Change Order No. 1 is for the addition of five temporary lights installed along Town Center Parkway. Installation of the permanent light fixtures was delayed due to modifications of the final shop drawings for the "Blue Heron" emblem included with the lights. Due to the opening of the roadway and the Country Inn and Suites temporary lighting was required. The total for the change order is $3,065.00. The total revised contract amount, with the change order, is $486,200.84. The cost of the improvements were previously included in the City's financing package and special assessments levied against the properties. RECOMMENDATION Staff is recommending the adoption of Resolution No. 06 -193, Approving Change Order No.1 in the amount of $3,065.00. ATTACHMENTS 1. Resolution No. 06 -193 2. Change Order No. 1 • � SEH • • November 10, 2006 Honorable Mayor and City Council City of Lino Lakes 600 Town Center Parkway Lino Lakes, MN 55014 -1182 Attn: Michael Grochala Community Development Director Dear Mr. Grochala: RE: Lino Lakes, Minnesota Legacy at Woods Edge — Phase 2 Lino Lakes, Minnesota SEH No. A- LINOL0305.03 Please find enclosed Change Order No. 1 for the referenced project. The change order is for the installation of 5 temporary light poles installed along Town Center Parkway. The light poles were supplied by the contractor and pole supplier without a charge. The wiring was paid as part of the original contract and will be used for power to the permanent poles when they are available. The light poles were installed to provide lighting to the County Inn and Suites hotel until the permanent light fixtures are installed. The total for the change order is $3,065.00. Please don't hesitate to contact me with any questions or comments. Sincerely, Anthony J. Kutzke, EIT Project Engineer ajk Enclosure x:Vco\ linol U130503U.egacyPh2\ConstPhase'co 1 cty.doc Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-5196 SEH is an equal opportunity employer 1 www.sehinc.com I 651.490.2000 1 800.325.2055 1 651.490.2150 fax • SEH CHANGE ORDER City of Lino Lakes, Minnesota October 31, 2006 OWNER DATE OWNERS PROJECT NO. Legacy at Woods Edge - Phase 2 PROJECT DESCRIPTION 1 CHANGE ORDER NO. A- LINOL0305.03 SEH FILE NO. The following changes shall be made to the contract documents: Description: 1. Contractor shall install 5 temporary light poles and fixtures on existing light pole bases along Town Center Parkway. Existing 1 1/2" conduits will be used to pull wire and wire will be paid at the original contract price. Work to include termination at streetlights and at existing service cabinet. Purpose of Change Order: Amend scope of contract to include temporary lighting along Town Center Parkway for access to the County Inn and Suites hotel. Basis of Cost: ® Actual Attachments (list supporting documents) Letter from Signature Lighting dated September 28, 2006 ❑ Estimated Contract Status Original Contract Net Change Prior C.O.'s to Change this C.O. Revised Contract Recommended for Approval: Short Elliott Hendrickson Inc. by d to Contrac BY ignature Lighting Inc. TITLE Distribution Contractor 2 s:11co\I\lino l\ 030503 \legacyph2\constphase\co# 1.doc Owner 1 Time N/A Cost $483,135.84 $0.00 $3,065.00 $486,200.84 Mason / roject Manager Approve • for Owner: BY City of Lino Lakes, Minnesota TITLE Project Representative 1 SEH Office 1 Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110 -5196 SEH is an equal opportunity employer 1 www.sehinc.com 1 651.490.2000 1 800.325.2055 1 651.490.2150 fax 1/04 • • City of Lino Lakes /S E H Attention: Ms. Sue Mason 600 Town Centex Pkwy Lino Lakes, MIDI 55014 September 28, 18430 Krypton St NW Anoka, MN 55303 Office- 763 - 753 -8157 Fax — 763 - 753 -7581 Re: Temporary, Street Lighting — Town Center Project Dear Sue, Submitted here, based on the conversation from the weekly construction meeting on September 13, 2006, Signature Lighting Inc. is pleased to have an opportunity to submit this proposal for the installation of five temporary decorative streetlights located within the Town Center Project in the City of Lino Lakes. The following is the list of material and labor to install these lights: • Use existing 1 ' /z" conduit • Pull the copper wire through conduit and through each base location to the five requested locations of the temporary lights. We would bill the wire and labor to do this to the original contract so we are not duplicating any costs. • Install five decorative 15 foot aluminum poles on existing concrete bases. These poles have been loaned to us by Lumec at no charge and will be returned to Lumec when the new poles are installed. •! Install five Lumec 100 Watt HPS "Lantern" style post top fixtures. These fixtures have been loaned to us by Lumec at no charge and will be returned to Lumec when the new fixtures are installed. •! Termination at streetlights and at existing service cabinet Total Price: $3,065.00 Note: The wire needed for these temporary lights will be run through each concrete base to the light locations; we will cone the bases however if the wire is stolen new wire replacement costs will be the burden of the City. Please feel free to contact me at (612) 910 4382 for any questions or additional information you may need. Sincerely, John Olson Principal Representative