Council Member Roeser introduced the following resolution and moved its
adoption:
CITY OF LINO LAKES
RESOLUTION NO. 12-46
RESOLUTION ACCEPTING BIDS AND AWARDING A CONSTRUCTION CONTRACT,
2012 MILL AND OVERLAY IMPROVEMENT
WHEREAS, pursuant to an advertisement for bids for the construction of the 2012 Mill and
Overlay Improvements, bids were received, opened and tabulated according to law, and the
following bids were received complying with the advertisement:
Contractor Amount of bid
North Metro Asphalt & Contracting
North Valley, Inc.
Knife River Corporation
Northwest Asphalt, Inc.
T.A. Schifsky & Sons, Inc.
$183,741.58
$184,245.17
$188,925.40
$190,386.80
$210,829.00
Engineer's Estimate $201,582.50
AND WHEREAS, it appears that North Metro Asphalt & Contracting is the lowest responsible
bidder;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. The Mayor and Clerk are hereby authorized and directed to enter into a contract with North
Metro Asphalt & Contracting, in the name of the City of Lino Lakes for the construction of
the 2012 Mill and Overlay Improvements according to the plans and specifications
approved by the City Council and on file in the office of the City Clerk.
2. The City Clerk is hereby authorized and directed to return forthwith to all bidder the Bid
Bonds made with their bids, except that the deposits of the successful bidder and the next
two lowest bidders shall be retained until a contract has been signed.
•
Julie : artell, City lerk
Adoption by the Lino Lakes City Council this 11th day of June, 2012
The motion for the adoption of the foregoing resolution was duly seconded by Council Member
Rafferty and upon vote being taken thereon, the following voted in favor thereof:
Roeser,,Rafferty., SToesz, Reinert
The following voted against same:
none (Absent - O'Donnell)
Whereupon said resolution was declared duly passed and adopted.
Jeff Re' e , Mayor
•
•
•
WSB
- Engineering • Plannin ■ Environmental • Construction 701 Xenia Avenue South
& Associates, Inc. g 9 g
Suite 300
Minneapolis, MN 55416
Tel: 763- 541 -4800
Fax: 763 -541 -1700
June 6, 2012
Honorable Mayor and City Council
City of Lino Lakes
600 Town Center Parkway
Lino Lakes, MN 55014
Re: 2012 Mill and Overlay Improvement
City of Lino Lakes Project No. 12 -02
WSB Project No. 2029 -13
Dear Mayor and Council Members:
Bids were received for the above - referenced project on Monday, June 4, 2012, and were opened
and read aloud. Five bids were received. The bids were checked for mathematical accuracy and
tabulated. Please find enclosed the bid tabulation indicating the low bid as submitted by North
Metro Asphalt Contracting LLC, Ham Lake, Minnesota, in the amount of $183,741.58. The
Engineer's Estimate for the project was $201,582.50.
We recommend that the City Council consider these bids and award a contract in the amount of
$183,741.58 to North Metro Asphalt Contracting LLC based on the results of the bids received.
Sincerely,
WSB & Associates, Inc.
ason C. Wedel, PE
City Engineer
Enclosures
cc: Donald Condon, North Metro Asphalt Contracting LLC
srb
C l Userslljeremy.koenenlAppDatall ocol aficrosoJtlWindowslTemporory Internet FikslContent outlooklPPJHIQ8L1,772 RECMMDTMluncc- 060612- signed.doc
•
•
BID TABULATION SUMMARY
PROJECT:
2012 Mill and Overlay Improvement
City Project No. 12-02
OWNER:
City of Lino Lakes, MN
WSB PROJECT NO.:
2029 -13
Bids Opened: Monday, June 4, 2012 at 1:00 p.m.
Contractor
Bid Security
(5 %)
Addendum
Received
Total Bid
1 North Metro Asphalt & Contracting X N/A
2 North Valley, Inc. X N/A
3 Knife River X N/A
4 Northwest Asphalt, Inc. X N/A
5 T. A. Schifsky & Sons, Inc. X N/A
$183,741.58
$184,245.17
$188,925.40
$210,829.00
Engineer's Opinion of Cost
$201,582.50
I hereby certify that this is a true and correct tabulation of the bids as received on June 4, 2012.
Denotes corrected figure
Jason C. Wedel, PE
K:102029- 1301AdmintConshuction Admin12029 -13 Bid Tab Summary- 060412
• R ll.
WSB
•
•
Project Name. LINO - 2012 Mill & Overlay Protect Contract No.:
Client: City of Lino Lakes
Bid Opening: 6/4/2012 1:00 PM
Project No.: 02029 -13
Owner: Minneapolis
WSB
Project Bid Abstract
Project: 02029 -13 - LINO - 2012 Mill & Overlay Project
Engineers Estimate
North Metro Asphalt &
Contracting
North Valley, Inc.
Knife River
Item No.
Item
Units
Quantity
Unit Price Total Price
Unit Price Total Price
Unit Price Total Price
Unit Price Total Price
SCHEDULE A - MILL AND OVERLAY IMPROVEMENTS
1
2021.501
MOBILIZATION
LUMP SUM
1
$4,000.00
$4,000.00
$3,336.00
$3,336.00
$3,035.77
$3,035.77
$8,500.00
$8,500.00
2
2104.501
REMOVE BITUMINOUS CURB
LIN FT
200
$2.00
$400.00
$4.15
$830.00
$3.25
$650.00
$3.00
$600.00
3
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
2120
$4.00
$8,480.00
$1.79
$3,794.80
$1.46
$3,095.20
$2.25
$4,770.00
4
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
100
$3.00
$300.00
$2.25
$225.00
$4.88
$488.00
$4.50
$450.00
5
2112.501
SUBGRADE PREPARATION (SPECIAL)
ROAD STA
38.8
$175.00
$6,790.00
$142.60
$5,532.88
$174.83
$6,783.40
$118.00
$4,578.40
6
2331.604
BITUMINOUS PAVEMENT RECLAMATION
SQ YD
9560
$1.50
$14,340.00
$0.89
$8,508.40
$1.46
$13,957.60
$0.95
$9,082.00
7
2331.607
HAUL BITUMINOUS PAVEMENT RECLAMATION (LV)
CU YD
650
$7.00
$4,550.00
$7.50
$0.01
$6.50
$12.00
87,800.00
8
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
770
$3.25
$2,502.50
$2.85
$2,194.50
$2.87
$2,209.90
$2.30
$1,771.00
9
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)
TON
1140
$63.00
$71,820.00
$57.80
$65,892.00
$57.85
$65,949.00
$57.10
$65,094.00
10
2360.502
TYPE SP 12.5 NON WEARING COURSE MIXTURE (2,B)
TON
1460
$60.00
$87,600.00
$59.55
$86,943.00
$59.43
$86,767.80
$58.00
$84,680.00
11
2535.501
BITUMINOUS CURB
LIN FT
200
$4.00
$800.00
$8.05
$1,610.00
$6.51
$1,302.00
$8.00
$1,600.00
Total SCHEDULE A - MILL AND OVERLAY IMPROVEMENTS:
$201,582.50
$184,245.17
$188,925.40
(Total SCHEDULE A - MILL AND OVERLAY IMPROVEMENTS: $201,582.50 $184,245.17 $188,925.40
Totals for Project 02029 -13
$201,582.50
,..,
$184,245.17
$188,925.40
% of Estimate for Project 02029 -13
-8.85%
-8.60%
-6.28%
•
•
I hereby certify that this Is an exact reproduction of bids received.
Certified By:
Date: June 4, 2012
License No. 26768
Project: 02029 -13 - LINO - 2012 Mill & Overlay Project
Engineers Estimate
Northwest Asphalt, Inc.
T. A. Schifsky & Sons, Inc.
Item No.
Item
Units
Quantity
Unit Price Total Price
Unit Price Total Price
Unit Price Total Price
SCHEDULE A - MILL AND OVERLAY IMPROVEMENTS
1
2021.501
MOBILIZATION
LUMP SUM
1
$4,000.00
$4,000.00
$8,687.00
$8,687.00
$10,000.00
$10,000.00
2
2104.501
REMOVE BITUMINOUS CURB
LIN FT
200
$2.00
$400.00
$1.00
$200.00
$5.00
$1,000.00
3
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
2120
$4.00
$8,480.00
$3.33
$7,059.60
$3.00
$6,360.00
4
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
100
$3.00
$300.00
$3.50
$350.00
$1.40
$140.00
5
2112.501
SUBGRADE PREPARATION (SPECIAL)
ROAD STA
38.8
$175.00
$6,790.00
$165.00
$6,402.00
$180.00
$6,984.00
6
2331604
BITUMINOUS PAVEMENT RECLAMATION
SQ YD
9560
$1.50
$14,340.00
$0.57
$5,449.20
$1.25
$11,950.00
7
2331.607
HAUL BITUMINOUS PAVEMENT RECLAMATION (LV)
CU YD
650
$7.00
$4,550.00
$8.42
$5,473.00
$7.40
$4,810.00
8
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
770
$3.25
$2,502.50
$2.00
$1,540.00
$2.50
$1,925.00
9
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)
TON
1140
$63.00
$71,820.00
$58.70
$66,918.00
$63.00
$71,820.00
10
2360.502
TYPE SP 12.5 NON WEARING COURSE MIXTURE (2,B)
TON
1460
$60.00
$87,600.00
$59.80
$87,308.00
$64.00
$93,440.00
11
2535.501
BITUMINOUS CURB
LIN FT
200
$4.00
$800.00
$5.00
$1,000.00
$12.00
$2,400.00
Total SCHEDULE A - MILL AND OVERLAY IMPROVEMENTS:
$201,582.50
$210,829.00
(Total SCHEDULE A - MILL AND OVERLAY IMPROVEMENTS: $201,582.50 $210,829.00
Totals for Project 02029 -13
$201,582.50
i
$210,829.00
% of Estimate for Project 02029 -13
-5.55%
4.59%
I hereby certify that this Is an exact reproduction of bids received.
Certified By:
Date: June 4, 2012
License No. 26768
•
•
•
CITY COUNCIL
AGENDA ITEM 6Ai
STAFF ORIGINATOR: Jason C. Wedel, City Engineer
MEETING DATE: June 11, 2012
TOPIC: Resolution No. 12 -46, Accepting bids and Awarding a Construction
Contract, 2012 Mill and Overlay Improvement
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND
Sealed bids were received and publicly opened at 1:00 p.m. on June 4, 2012. The results of the bid
opening are presented below. City Council action is required to award a construction contract to
the lowest responsible bidder.
Contractor Amount of bid
North Metro Asphalt & Contracting
North Valley, Inc.
Knife River Corporation
Northwest Asphalt, Inc.
T.A. Schifsky & Sons, Inc.
$183,741.58
$184,245.17
$188,925.40
$190,386.80
$210,829.00
Engineer's Estimate $201,582.50
The low bids are competitive bids for this project. A copy of the complete bid tabulation is
attached. The final completion date for this project is August 31, 2012.
RECOMMENDATION
Staff recommends adoption of Resolution 12 -46 Accepting Bids and Awarding a Construction
Contract for the 2012 Mill and Overlay Improvement.
ATTACHMENTS
1. Bid Tabulation