RESOLUTION NO. 12 -51
AUTHORIZING UTILITY RATE STUDY
WHEREAS, the City Council has determined a need to perform a utility rate study to evaluate
the financial operations of the Water and Sewer Enterprise Funds; and
WHEREAS, the last rate analysis was completed in 2008; and
WHEREAS, in February, 2012, the City requested and received a proposal from Springsted,
Inc. to conduct a comprehensive utility rate study. The study would include reviewing current and
background utility data, including historical financial information, volumes, capital improvements,
debt service requirements, policies and practices, growth trends and reviewing engineering studies,
including the water conservation plan; and
WHEREAS, the proposed study will provide recommendations for the water and sewer user
rates, water and sewer trunk area charges, sanitary sewer unit charges, and watermain unit charges; and
WHEREAS, in order for Springsted, Inc. to accurately complete the study, we recommend
retaining WSB & Associates to prepare the following:
o Water Demand /Sewer Flow Population Projections
o Water /Sewer Capital Improvement Plan
o Replacement, Operations, and Maintenance Plan
• NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Lino Lakes,
Minnesota, that a Utility Rate Study is hereby authorized to be performed by Springsted, Inc. at a cost
of $25,800, plus expenses and WSB & Associates is authorized to perform the above mentioned
engineering services at a cost not -to- exceed $16,000. Such cost shall be split equally between the
Water and Sewer Funds.
Adopted by the Council of the City of Lino Lakes this 25th day of June, 2012.
The motion for the adoption of the foregoing resolution was introduced by Council Member
0' Donnell and was duly seconded by Council Member Roeser and upon vote being taken
thereon, the following voted in favor thereof:
O'Donnell, Roeser, Rafferty, Stoesz, Re Allt
none
The following voted against same:
ATTEST:
e Bartell, City lerk
Jeff R- = ''Mayor
CITY COUNCIL
AGENDA ITEM 5A
• STAFF ORIGINATOR: Rick DeGardner, Public Services Director
MEETING DATE: June 25, 2012
TOPIC: Consider Resolution 12 -51 Authorizing a Utility Rate Study
VOTE REQUIRED: 3/5
•
INTRODUCTION
In February, 2012, the City requested and received a proposal from Springsted, Inc. to conduct a
comprehensive utility rate study. The study would include reviewing current and background utility
data, including historical financial information, volumes, capital improvements, debt service
requirements, policies and practices, growth trends and reviewing engineering studies, including the
water conservation plan. Springsted, Inc. then would evaluate the current data and consider future
needs in developing a comprehensive report which would recommend and justify any future rate
adjustments. The last rate analysis was completed in 2008.
BACKGROUND
Utility rates are set based upon a number of factors. Among these are the cost of providing the service
(operations costs), the cost of extending the utility network (infrastructure costs), financing and
servicing of debt, and the cost of replacing worn facilities and systems (referred to as depreciation or
replacement costs). Other considerations in setting rates are regulatory guidelines, conservation
measures and rate comparisons with other area communities.
The proposed study will provide recommendations for the water and sewer user rates, water and sewer
trunk area charges, sanitary sewer unit charges, and watermain unit charges. In order for Springsted,
Inc. to accurately complete the study, we recommend retaining WSB & Associates to prepare /update
the following:
o Water Demand/Sewer Flow Population Projections
o Water /Sewer Capital Improvement Plan
o Replacement, Operations, and Maintenance Plan
WSB & Associates proposes to perform the above mentioned engineering services for a not -to- exceed
fee of $16,000 (We will be billed at the customary hourly rates). The cost for Springsted, Inc. to
conduct the utility rate study is $25,800, plus expenses, which would be financed equally from the
Water and Sewer funds. We anticipate Springsted, Inc. would present their formal report to the City
Council this fall.
RECOMMENDATION
Staff is recommending Council adopt Resolution No. 12 -51 authorizing Springsted, Inc. to complete a
utility rate study and WSB & Associates to provide supporting engineering services.
ATTACHMENTS
• Water and Wastewater Fee Study Update Proposal from Springsted, Inc., dated February, 2012.
• Estimate of Professional Engineering Services from WSB & Associates, dated June 13, 2012
PIsiI NII�III!
• Sp � �� n s ed
ra
•
•
Water and Wastewater Fee Study Update
Work Plan February 2012
Objective(s)
The purpose of this study is to assist the City of Lino Lakes in evaluating the financial operations of
its Water and Wastewater Utilities to update the necessary level of user fees, area charges, and
trunk fees that will provide adequate cash flow to pay for current plant expenditures, anticipated
future operating and maintenance expenses, debt service including principal and interest, utility
improvements asset replacement, and adequate cash reserves. Rate recommendations will reflect
the each Utility's recent cost experience as well as anticipated future costs during the nominal
period for which rates are projected.
Springsted completed a rate analysis for the City in 2007. This analysis would update that study
and make adjustments to rates and fees based on activity since 2007.
Task 1 - Review Background Information
➢ Internal review of background information:
— Review historical financial information, volumetric rates, basic facility charges,
contractual charges and other fees and charges that provide sources of revenue for
each utility
— Review the current allocation of costs to functional cost components and to rates
and charges for each utility
— Review any current allocations of capital costs to connection and other charges and
fees for each utility
— Review current and historical billing data for each utility
— Review current funding practices, funding sources and policies related to financing
capital improvements for each utility
— Review and update the City's existing capital improvement plan for each utility
identifying the sources of funding for each improvement
— Review any existing debt service coverage requirements for both senior and
subordinate debt and the impact of adding additional debt to finance new capital
improvements for each utility
— Review ordinances, policies and practices related to user fees, connection fees and
other charges for utility services
City of Lino Lakes, Minnesota
Water and Wastewater Fee Study Update
• February 2012
Page 2
•
•
— Review the historical growth of the customer base and projections for anticipated
growth for each utility
— Review any engineering studies, cost of services studies and other relevant studies
related to each utility
— Review the planning period to be used in the study
➢ Analyze information and develop preliminary availability fees for each utility and cost of
service analysis for each utility
— Analyze the information to identify any omissions and/or inconsistencies and collect
additional information, as needed
— Develop projected customer growth and future service demands based upon the
existing systems and anticipated growth
— Project the cost of providing services for each utility
Task 11 - Conduct Study
➢ Develop a financial projection of each Utility that integrates all anticipated revenue
sources, including interest on the cash balance, anticipated operating expenditures
including existing and projected new depreciation, anticipated capital expenditures,
existing debt service, projected debt service for identified projects and changes in the
customer base over the planning period:
— Develop a five -year forecast of revenues and expenditures for each Utility to
determine the adequacy of revenues provided by existing rates
— Evaluate the impact of anticipated capital improvement financing options on rates,
fees and charges
— Develop recommendations for the financing of the anticipated capital improvements
based on the above impact analysis
— Identify the overall change in revenue required to provide for adequate funding for
major capital improvement programs, to meet all recurring annual operating and
capital expenditures, to cover all debt service requirements, to comply with any
existing revenue bond covenants, and to maintain sufficient cash balances and
capital reserves (as defined by the City) for each Utility The projections will be
made using an income statement approach and will include a yearly cash flow
analysis
— Develop preliminary rate schedules for each Utility that provides revenue recovery
at levels necessary to support the Utility's operation as defined above. Rates
developed will include user fees, area charges, connection charges and other fees
and charges that provide sources of revenue to the Utility
— Perform a sensitivity analysis to illustrate the impacts of adverse assumption
changes (e.g. future growth, operating costs)
➢ Evaluate each Utility's current service fees and charges to determine whether there are
additional service fees and charges that are currently not assessed and that may be
applicable to the Utility's provision of services and, conversely, whether there are fees
and charges that can be reduced or eliminated
City of Lino Lakes, Minnesota
Water and Wastewater Fee Study Update
• February 2012
Page 3
➢ Project the fiscal impact of proposed changes to fees and charges on each Utility's
current rates, fees and charges
— Develop recommendations for any changes to fees and charges, together with the
impact on current rates and charges
— Make recommendations for changes in existing ordinances, resolutions and policies
necessary to implement any new fees and charges recommended
➢ If we make a recommendation to increase rates or charges, Springsted will:
— Evaluate and compare the proposed fee structure with the Utility's current fee
structure and with the fee structure of at least three other similarly -sized local
government utility operations in the area
— Prepare sample bills for a minimum of 6 customers from representative customer
classes, comparing existing rates and charges to proposed rates and charges
— Review and make recommendations for changes needed in existing ordinances,
resolutions and policies
➢ Develop a five -year financial projection of capital expenditure needs related to growth
that integrates all anticipated revenue sources, anticipated capital expenditures, and
existing and projected debt service over the planning period:
— Develop preliminary availability fee that provides revenue recovery at levels
necessary to support the capital needs
— Perform a sensitivity analysis to illustrate the impacts of adverse assumption
changes (e.g. future growth)
Task III - Present and Review Draft Report
➢ Springsted will prepare a Draft Report of Findings that will contain our findings and
recommendations. This review document will form the core of our final report. We will
submit fifteen bound copies plus one reproducible copy to the City for their review and
comment
> We will meet with City to review and discuss the Draft Report in a workshop session
➢ Based on our discussion and review of the Draft Report, Springsted will make
modifications or changes, incorporating the City's comments into the final report, as
appropriate.
Task IV - Present and Review Final Report
➢ Springsted will present the Final Report of Findings and Recommendations in a City
Council regular or workshop session
> We will provide fifteen bound copies of the final study plus one reproducible copy of the
final report
•
City of Lino Lakes, Minnesota
Water and Wastewater Fee Study Update
411 February 2012
Page 4
Expectations
In order to conduct this study, the City will need to designate a staff member to serve as a project
manager. This person will be responsible for assisting Springsted with gathering accurate and timely
data needed to complete the project and to assist in arranging for required meetings. At a minimum the
following information will be needed to complete the study:
•
•
Utility Rate Study Update Required Information
➢ Copy of your most recent and previous two years Comprehensive Annual Financial
Reports (already have)
➢ 2008 -2011 actuals (by line item)
➢ 2011 and 2012 budget including revenues and expenditures for each utility (by line item)
➢ 2012 beginning cash balance in each fund
➢ A listing of all anticipated capital expenditures for the planning period 2012 through the
2022 (or lesser timer period if 2012 to 2022 is not available) indicating item to be
purchased, amount, and anticipated funding source for each utility
➢ Information related to the current customer base for the utility by customer class
including number of customers, sales volume by type of service /charge /revenue source,
and total revenue
➢ Copy of your current depreciation schedule and depreciable life use for various assets
➢ Copies of any current policies related to capital expenditures and/or funding for them
including special assessments
➢ Copies of any current policies related to fund balances and /or cash balances
➢ Copies of existing debt schedules for any outstanding debt, i.e. bonds, equipment
certificates, lease- purchase agreements where Springsted was not the Financial Advisor
➢ Information related to the anticipated growth in both residential and
commercial /industrial utility sales during the planning period
➢ Current schedule of user fees and charges
➢ Copies of any engineering studies, cost of services studies and other relevant studies
related to each Utility and this study
City of Lino Lakes, Minnesota
Water and Wastewater Fee Study Update
• February 2012
Page 5
Compensation
We propose to complete this study as described in this proposal for the lump sum fee of $25,800
exclusive of any out -of- pocket expenses such as travel and copying. This amount would include up to
three on -site meetings. We will complete the study within 10 -12 weeks of receiving the notice to proceed
provided that all necessary information is made available to Springsted in a timely manner and that City
staff is available for required meetings. This draft schedule does not anticipate any unforeseen delays or
other circumstances that would result in a later completion date. Should any unforeseen delays or
circumstances arise, Springsted can draw on its staff of 60 professionals to keep the project on schedule
to the greatest extent possible.
Springsted would invoice the City for work completed based on the following schedule:
Npfrel
Completion of Task II
Completion of Task III
Completion of Task IV
10% 100%
Should the City request and authorize additional work outside the scope of services described in this
proposal or additional revisions beyond those agreed upon at the discussion and review of the draft
report and preliminary model, we would invoice the City at our standard hourly fees.
Title
Rate
Principal & Senior Officer
Officer & Project Manager
Senior Associate
Associate
Support Staff
$220
$190
$155
$145
$ 65
•
•
A,
WSB
& Associates, Inc.
June 13, 2012
Infrastructure • Engineering • Planning • Construction
Rick DeGardner
600 Town Center Parkway
City of Lino Lakes
Lino Lakes, MN 55014
Re: Estimate of Professional Engineering Services
Water and Wastewater Fee Study Update
City of Lino Lakes, Minnesota
Dear Mr. DeGardner:
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763 -541 -4800
Fax: 763 - 541 -1700
On behalf of WSB & Associates, Inc. (WSB), we are pleased to submit this proposal to the City
of Lino Lakes to provide professional engineering services as they relate to the a Rate Study for
the City's water and sewer trunk area charges, sanitary sewer unit charge, watermain unit charge,
and user rates. It is our understanding that the study will be conducted by Springsted Inc. and
that WSB will be providing information to them for use in the rate study.
A delineation of tasks to be performed by WSB & Associates, Inc. and by the City follows
directly. Assumptions related to these same items are also delineated in a subsequent section.
WSB Tasks
WSB will be responsible for the following tasks:
Task 1— Water /Sewer Rate Philosophy
Task 1.1: Determine the Water and Sewer Rate Philosophy
This task will include the review of the existing philosophy and incorporate any changes required
following discussions with the City.
Task 2 — Water Demand/ Sewer Flow and Population Projections
Task 2.1: Determine Developable Areas and Associated Water Demand and SewerFlow Per
Type of Area
From the land use map and the population projections a water demand and sewer flow associated
with each land use type will be determined. Average day demands, peaking factors, and water
losses will be estimated. Population projections are necessary for water and sewer trunk area
charges, sanitary sewer unit charge, and watermain unit charge projections.
QlUserslrick.degard erlAppDatalLocallMicrosoJllWindowslTemporary Internet Files1Content .Outlook■LIXIVIRSQILTR PROP- 061311 -rate smdy.doc
•
June 13, 2012
Page 2
Task 2.2: Estimate Consumption /Sewage Generation Trends
Estimate consumption/generation trends for residential and commercial /industrial uses and other
uses.
Task 2.3: Estimate Future Water Demands /Sewage Flows
Based on City provided land use and population projections, determine future water
demands /sewer flows per year. Future demands /flows are necessary for user rate projections.
Task 3 — Water /Sewer Capital Improvement Plan, Funding Options
Task 3.1: Prepare Capital Improvement Plans
Prepare an annual CIP and 10 -year CIP for the water and sewer systems based on present day
values. The CIP will document needed improvements and the timeframe in which they should
be completed, along with associated costs.
Task 3.2: Recommend Funding Alternatives
Using the list of recommended capital improvements and the revised philosophy in Task 1, make
general recommendations regarding funding the improvements through various fees (e.g. utility
user, trunk, and water /sewer access fees).
Task 3.3: Prepare CIP
Prepare a draft and final memo summarizing recommended capital improvement plans and
funding options
Task 4 — Replacement, Operations, and Maintenance Plan
Task 4.1: Prepare Estimated Infrastructure Replacement Schedule
Prepare an estimated annual replacement budget based on the age and condition of the existing
infrastructure.
Task 4.2: Prepare Estimated Operations and Maintenance
Prepare an estimated annual replacement budget based on the age and condition of the existing
infrastructure. For this task, we will need assistance from the City staff to project the annual
expenses based on historical expenses.
Task 4.3: Recommend Funding Alternatives
Using the list of recommended replacements, operations, and maintenance costs and the revised
philosophy in Task 1, make general recommendations regarding funding the replacements
through various fees (e.g. utility user, trunk, and access fees).
City of Lino Lakes Tasks
In order to complete our tasks, we will need the City to provide the following:
• Provide a designated project contact person.
• Provide answers to specific project questions, provide requested information, and make
decisions regarding project direction during the course of the project.
C: I Usersbl ckdegardn erlAppDotalLocal∎Micros fiIWindowslTempormy Internet F les \Contem.OutlookNMXIVIRSQILTR PROP - 0613/2 -rare study.doc
•
June 13, 2012
Page 3
Fee
We propose to perform the tasks as defined above for a not -to- exceed fee of $16,000. We will
bill at our customary hourly rates.
Agreement
If you are in agreement with the scope of services, please have the City block of this letter signed
and return a copy to WSB. Our receipt of an executed copy will be WSB's authorization to
proceed. Monthly project invoices for services and reimbursables are due within 30 days after
receipt of WSB's invoice. Should the City request additional services outside of the above scope
of services, we will work with you to establish a revised scope and fees.
Thank you for the opportunity to be of service to you. If you have any questions or comments,
please call us at (763) 541 -4800.
Sincerely,
WSB & Associates, Inc.
Nancy Zeigler, PE
Senior Project Manager
ACCEPTED:
City of Lino Lakes
By:
Title:
Date:
61 Userslrick. degardnerlAppOatalLoca lLNicrosoftlWindowslTemporary Internet Fi les1ContentOutlookWIXIVIRSQ'yTR PROP- 061312 -rate study.doc