HomeMy WebLinkAbout2012-116 Council Resolutiondo
•
CITY OF LINO LAKES
RESOLUTION NO. 12-116
APPROVING PAYMENT REQUEST NO. 2F (FINAL), CHANGE ORDER NO. 1 AND
COMPENSATING CHANGE ORDER NO. 2, 2012 MILL AND OVERLAY PROJECT
WHEREAS, pursuant to the resolution of the Council adopted June 11, 2012, awarding the
contract for the 2012 Mill and Overlay Project to North Metro Asphalt Contracting
LLC;
WHEREAS, a complete breakdown is detailed in Payment No. 2F (Final), Change Order No. 1
Compensating Change Order No. 2;
NOW, THEREFORE, BE IT RESOLVED by the City Council of Lino Lakes, Minnesota that
Payment Request No. 2F (Final), Change Order No. 1, and Compensating Change Order No. 2 is
approved for a final contract amount of $186,602.26.
Adopted by the City Council of Lino Lakes, Minnesota this 26th day of November, 2012.
The motion for the adoption of the foregoing resolution was introduced by Council Member
Roeser and was duly seconded by Council Member Rafferty and upon vote being taken thereon,
the following voted in favor thereof:
Roeser, Rafferty, Stoesz, O'Donnell, Reinert
The following voted against same:
none
ATTEST:
•
•
•
CITY COUNCIL
AGENDA ITEM 6C
STAFF ORIGINATOR: Jason C. Wedel, City Engineer
MEETING DATE: November 26, 2012
TOPIC: Consider Resolution No. 12 -116 Approving Pay Request 2F (Final),
Change Order No. 1 and Compensating Change Order No. 2, 2012
Mill and Overlay Project
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND
At the June 11, 2012 meeting, City Council awarded the 2012 Mill and Overlay contract to North
Metro Asphalt Contracting LLC.
The contractor is requesting City approval of Payment Request 2F (Final) in the amount of
$32,764.80. A copy of the Final Payment is attached. The contractor has satisfactorily completed
all work and has provided all necessary documentation.
Also included with the request for Final Payment are Change Orders No. 1 in the amount of
$24,668.09 and Compensating Change Order No. 2 in the amount of ($21,807.41). A copy of both
these change orders is attached. With these change order, the final project amount is $186,602.26.
Change Order No. 1 was for the addition of the paving that was done on Thomas Street. This area
was added to the project after the original contract was approved. The additional work was
approved by the City Council on August 27, 2012 and was originally estimated to cost $29,612.75.
The work is now complete and came in $4,944.66 under budget.
Compensating Change Order No. 2 is a deduction to the contract due to the construction quantities
coming in below the engineer's estimate. The original contract amount was $183,741.58 and the
revised contract, as proposed with both change orders, is $186,602.26 which equates to an increase
of $2,860.68. When the City Council approved Change Order No. 1 staff recommended using
some of the remaining funds from the 2012 surface water management project to cover the cost.
However, now that the project is complete and the increase to the contract is only $2,860.68, staff is
proposing to fund the contract increase through the pavement management fund since there are
adequate funds available. Approval of the Final Payment will begin the two year warranty period.
•
•
•
RECOMMENDATION
Approve Resolution 11 -116, Approving Payment Request No. 2F (Final), Change Order No. 1 and
Compensating Change Order No. 2, 2012 Sealcoat Project.
ATTACHMENTS
Pay Request No. 2 & Final
Change Order No. 1
Change Order No. 2
.wSB
•
& A ssocfates, Inc.
Owner: City of Lino Lakes
600 Town Center Parkway
Lino Lakes, MN 55014 -1182
For Period: 9/1/2012 to 10/17/2012
Contractor: North Metro Asphalt & Contracting
1455 165th Avenue NE
Ham Lake, MN 55304
Pay Voucher
LINO - 2012 Mill & Overlay Project
Client Contract No.:
Project No.: 02029 -13
Client Project No.:
Date: 10/25/2012
Request No.: 2 & FINAL
Proiect Summary
1
Original Contract Amount
$183,741.58
2
Contract Changes - Addition
$24,668.09
3
Contract Changes - Deduction
($21,807.41)
4
Revised Contract Amount
$186,602.26
5
Value Completed to Date
$186,602.26
6
Material on Hand
$0.00
7
Amount Eamed
$186,602.26
8
Less Retainage
$0.00
9
Subtotal
$186,602.26
10
Less Amount Paid Previously
$153,837.46
11
Liquidated Damages
$0.00
12
AMOUNT DUE THIS PAY VOUCHER NO. 2 & FINAL
$32,764.80
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT
THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL
VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE
WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER.
Recommended for Approval by:
WSB ssociates, Inc.
p •ved by Contrac
rth Mettrr sph • C
ting
Specified Contract Completion Date:
8/31/2012
Comment:
Construction Observer:
A roved by Owner.
City of Lino Lakes
Date:
//- Z/
Page 1
•
•
Project Material Status
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
SCHEDULE A - MILL. AND OVERLAY IMPROVEMENTS
1
2021.501
MOBILIZATION
LUMP SUM
$3,336.00
1
1
D
$3,336.00
2
2104.501
REMOVE BITUMINOUS CURB
UN FT
$4.15
200
20D
149
$830.00
3
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
51.79
2120
2120
122
$3,794.80
4
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
UN FT
52.25
100
100
100
$225.00
5
2112.501
SUBGRADE PREPARATION (SPECIAL)
ROAD STA
$142.60
38.8
38.8
0
55,532.88
6
2331.604
BITUMINOUS PAVEMENT RECLAMATION
SQ YD
$0.89
9560
9560
-1273
58,508.40
7
2331.607
HAUL BITUMINOUS PAVEMENT RECLAMATION (LV)
CU YD
$7.50
650
650
374
$4,875.00
8
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
52.85
770
770
120
$2,194.50
9
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)
TON
$57.80
1140
1140
-14
$65,892.00
10
2360.502
TYPE SP 12.5 NON WEARING COURSE MIXTURE (2,B)
TON
$59.55
1460
1460
308
586,943.00
11
2535.501
BITUMINOUS CURB
UN FT
$8.05
200
200
149
$1,610.00
Totals For Section SCHEDULE A MILL AND OVERLAY IMPROVEMENTS:
$183,741.58
Change Order 1
12
2021.501
MOBILIZATION (5% MAXIMUM)
LUMP SUM
$1,450.00
1
1
1
$1,450.00
13
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
51.79
160
160
160
5286.40
14
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
$2.25
30
30
30
$67.50
15
2105.501
COMMON EXCAVATION
CU YD
526.00
256
256
256
$6,656.00
16
2112.501
SUBGRADE PREPARATION
ROAD STA
5142.60
1.7
1.7
1.7
$242.42
17
2211.501
AGGREGATE BASE CLASS 5
TON
526.50
162.77
162.77
162.77
54,313.41
18
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
52.85
40
40
40
5114.00
19
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (2,C)
TON
557.80
62.5
62.5
62.5
$3,612.50
20
2360.502
TYPE SP 12.5 NON WEARING COURSE MIXTURE (2,C)
TON
$59.55
86.55
86.55
86.55
55,154.05
21
2511.501
RANDOM RIPRAP CLASS III
CU YD
$95.00
9
9
9
$855.00
22
2511.515
GEOTEXTILE FILTER FABRIC TYPE IV
SQ YD
55.75
25
25
25
$143.75
23
2575.502
SEED MIXTURE 260
POUND
$7.50
20
20
20
$150.00
24
2575.501
SEEDING (INCL TOPSOIL & FERTILIZER)
ACRE
$15,000.00
0.07
0.07
0.07
$1,050.00
25
2360.501
ADDL WEAR COURSE TO CORRECT DRAINAGE
TON
551.72
11.08
11.08
11.08
5573.06
Totals For Change Order 1:
$24,668.09
Change Order 2
26
2331.604
BITUMINOUS PAVEMENT RECLAMATION
SQ YD
50.89
1273
1273
1273
51,132.97
27
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)
TON
$57.80
14
14
14
$809.20
28
2104.501
REMOVE BITUMINOUS CURB
UN FT
($4.15)
149
149
149
(5618.35)
29
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
(51.79)
122
122
122
($218.38)
30
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
(52.25)
100
100
100
(5225.00)
31
2331.607
HAUL BITUMINOUS PAVEMENT RECLAMATION (LV)
CU YD
(57.50)
374
374
374
(52,805.00)
32
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
($2.85)
120
120
120
(5342.00)
33
2360.502
TYPE SP 12.5 NON WEARING COURSE MIXTURE (2,B)
TON
($59.55)
308
308
308
(518,341.40)
34
2535.501
BITUMINOUS CURB
LIN FT
(58.05)
149
149
149
(51,199.45)
Totals For Change Order 2:
(521,807.41)
Project Totals:
$186,602.26
Page 2
•
Project Payment Status
Owner: City of Lino Lakes
Client Project No.:
Client Contract No.:
Project No.: 02029 -13
Contractor. North Metro Asphalt & Contracting
Contract Changes
No.
Type
Date
Description
Amount
CO1
Change Order
10/17/2012
Change Order No. 1 (see change order document for description).
$24,668.09
CO2
Change Order
10/17/2012
Change Order No. 2 (see change order document for description).
($21,807.41)
Change Order Totals:
$2,860.68
Payment Summary
No.
From
Date
To Date
Payment
Total
Payment
Retainage
Per
Payment
Total
Retainage
Total
Payment +
Retainage
Work
Certified Per
Payment
Total Work
Certified
1
8/1/2012
8/31/2012
$153,837.46
$153,837.46
$8,096.71
$8,096.71
$161,934.17
$161,934.17
$161,934.17
F &
FINAL
9/1/2012
10/17/2012
$32,764.80
$186,602.26
($8,096.71)
$0.00
$186,602.26
$24,668.09
$186,602.26
Payment Totals:
$186,602.26
$0.00
$186,602.26
$186,602.26
Project Summary
Material On Hand:
Total Payment to Date:
Total Retainage:
Total Amount Earned:
$0.00
$186,602.26
$0.00
$186,602.26
Original Contract:
Contract Changes:
Revised Contract:
$183,741.58
$2,860.68
$186,602.26
Page 3
012 MILL AND OVERLAY IMPROVEMENT
CITY OF LINO LAKES PROJECT NO. 12 -02
WSB PROJECT NO. 2029-13
CHANGE ORDER 'NO.1
OCTOBER 17, 2012
OWNER:
CITY OF LINO LAKES
600 TOWN CENTER PARKWAY
LINO LAKES, MN 55014
CONTRACTOR:
NORTH METRO ASPHALT CONTRACTING LLC
1455 165TH AVENUE NE
HAM LAKE, MN 55304
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
This change order represents the addition of Thomas Street to the project.
ADDITIONAL CONTRACT QUANTITIES ARE SHOWN ON THE ATTACHED DETAIL SHEET.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS: NA
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF THIS CHANGE ORDER:
0 CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
RECOMMENDE. BY:
$183,741.58
$0.00
$183,741.58
$24,668.09
$208,409.67
ORIGINAL CONTRACT TIME:
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF CHANGE ORDER:
CONTRACT TIME WITH APPROVED CHANGE ORDERE
C. WEDEL, PE, PROJECT MANAGER
WSB & ASSOCIATES, INC.
ENGINEER
APPROVED BY:
8/31/2012
NONE
8/31/2012
NONE
8/31/2012
RACTOR SIGNATURE
NORTH METRO ASPHALT CONTRACTING LLC
CONTRACTOR
APPROVED BY:
CITY ENGINEER
DATE
C#Y�hB
f►m79va/.e.e. �.r GNIT if' Ewe-
/Z-2 /-2 / - /2-
DATE
fib
K:102029- 1301AdmIn %Conshucfon Admtnl
Page 1 2029 -13 Change Order 1-101712C0 1
ill 2012 MILL AND OVERLAY IMPROVEMENT
CITY OF LINO LAKES PROJECT NO. 12 -02
WSB PROJECT NO. 2029-13
•
ORDER NO. 1 DETAIL
OCTOBER 17, 2012
ADDED ITEMS
Item No. Mat. No. Description
Qty Unit Price Extended Amount
12 2021.501 MOBILIZATION (5% MAXIMUM) 1 LUMP SUM $1,450.00 $1,450.00
13 2104.505 REMOVE BITUMINOUS PAVEMENT 160 SQ YD $1.79 $286.40
14 2104.513 SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 30 LIN FT $2.25 $67.50
15 2105.501 COMMON EXCAVATION 256 CU YD $26.00 $6,656.00
16 2112.501 SUBGRADE PREPARATION 1.7 ROAD STA $142.60 $242.42
17 2211.501 AGGREGATE BASE CLASS 5 162.77 TON $26.50 $4,313.41
18 2357.502 BITUMINOUS MATERIALFOR TACK COAT 40 GALLON $2.85 $114.00
19 2360.501 TYPE SP 12.5 WEARING COURSE MIXTURE (2,0) 62.5 TON $57.80 $3,612.50
20 2360.502 TYPE SP 12.5 NON WEARING COURSE MIXTURE 86.55 TON $59.55 $5,154.05
(2,C)
21 2511.501 RANDOM RIPRAP CLASS III 9 CU YD $95.00 $855.00
22 2511.515 GEOTEXTILE FILTER FABRIC TYPE IV 25 SQ YD $5.75 $143.75
23 2575.502 SEED MIXTURE 260 20 POUND $7.50 $150.00
24 2575.501 SEEDING (INCL. TOPSOIL & FERTILIZER) 0.07 ACRE $15,000.00 $1,050.00
25 2360.501 ADDL WEAR COURSE TO CORRECT DRAINAGE 11.08 TON $51.72 $573.06
TOTAL ADDED ITEMS CHANGE ORDER NO. 1 $24,668.09
DELETED ITEMS
Item No. Mat. No. Description
Qty Unit Price Extended Amount
TOTAL DELETED ITEMS CHANGE ORDER NO. 1
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT
$0.00
$24,668.09
K:102029- 1301AdminlConstruction Adminl
Page 2 2029 -13 Change Order 1-101712C0 1 Detail
00 12 MILL AND OVERLAY IMPROVEMENT
CITY OF LINO LAKES PROJECT NO. 12 -02
WSB PROJECT NO. 2029-13
CHANGE ORDER NO. 2
OCTOBER 17, 2012
OWNER:
CITY OF LINO LAKES
600 TOWN CENTER PARKWAY
LINO LAKES, MN 55014
CONTRACTOR:
NORTH METRO ASPHALT CONTRACTING LLC
1455 165TH AVENUE NE
HAM LAKE, MN 55304
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
This compensating change order shows the actual quantities installed at the unit price bid amounts (see attached itemization).
ADDITIONAL CONTRACT QUANTITIES ARE SHOWN ON THE ATTACHED DETAIL SHEET.
IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
PREVIOUS CHANGE ORDERS: NO. 1
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET DECREASE OF THIS CHANGE ORDER:
fkONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
RECOMMENDED B
WEDEL, PE, PROJECT MANAGER
WSB & ASSOCIATES, INC.
ENGINEER
$183,741.58
$24,668.09
$208,409.67
($21,807.41)
$186,602.26
ORIGINAL CONTRACT TIME:
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF CHANGE ORDER:
CONTRACT TIME WITH APPROVED CHANGE ORDERS
APPROVED BY:
8/31/2012
NONE
8/31/2012
NONE
8/31/2012
NTRACTOR SIGNATURE
NORTH METRO ASPHALT CONTRACTING LLC
CONTRACTOR
APPROVED BY:
CITY ENGINEER
111- .?D —i.1
DATE
Cor►/twool (Qpp.sw,r- 0.11Cs4
/./ Z/Z
DATE
Page 1
K:102029.1301AdminlConslruct /on Adminl
2029 -13 Change Order 240171200 2
•
2012 MILL AND OVERLAY IMPROVEMENT
CITY OF LINO LAKES PROJECT NO. 12-02
WSB PROJECT NO. 2029-13
CHANGE ORDER .NO. '2 DETAIL
OCTOBER 17, 2012
ADDED ITEMS
Item No. Mat. No. Description
Qty Unit Price Extended Amount
26 2331.604 BITUMINOUS PAVEMENT RECLAMATION 1273 SQ YD $0.89 $1,132.97
27 2360.501 TYPE SP 12.5 WEARING COURSE MIXTURE (2,B) 14 TON $57.80 $809.20
TOTAL ADDED ITEMS CHANGE ORDER NO. 2
DELETED ITEMS
$1,942.17
Item No. Mat. No. Description
Qty Unit Price Extended Amount
28 2104.501 REMOVE BITUMINOUS CURB 149 LIN FT $4.15 $618.35
29 2104.505 REMOVE BITUMINOUS PAVEMENT 122 SQ YD $1.79 $218.38
30 2104.513 SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 100 LIN FT $2.25 $225.00
31 2331.607 HAUL BITUMINOUS PAVEMENT RECLAMATION (LV) 374 CU YD $7.50 $2,805.00
32 2357.502 BITUMINOUS MATERIAL FOR TACK COAT 120 GALLON $2.85 $342.00
33 2360.502 TYPE SP 12.5 NON WEARING COURSE MIXTURE 308 TON $59.55 $18,341.40
(2,B)
34 2535.501 BITUMINOUS CURB
149 LIN FT $8.05 $1,199.45
TOTAL DELETED ITEMS CHANGE ORDER NO. 2 $23,749.58
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT ($21,807.41)
Page 2
KA02029- 1301AdmJn1Construction Admini
202943 Change Order 2- 101712C0 2 Detail