HomeMy WebLinkAbout2013-117 Council Resolution•
•
CITY OF LINO LAKES
RESOLUTION NO. 13 -117
APPROVING PAYMENT REQUEST NO. 1F (FINAL) AND COMPENSATING CHANGE
ORDER NO. 1, 2013 SEALCOAT PROJECT
WHEREAS, pursuant to the resolution of the Council adopted July 22, 2013, awarding the
contract for the 2013 Sealcoat Project to Allied Blacktop, Inc.;
WHEREAS, a complete breakdown is detailed in Payment No. 1F (Final) and Compensating
Change Order No. 1;
NOW, THEREFORE, BE IT RESOLVED by the City Council of Lino Lakes, Minnesota that
Payment Request No. 1F (Final) and Compensating Change Order No. 1 is approved for a final
contract amount of $60,093.46.
Adopted by the City Council of Lino Lakes, Minnesota this 28th day of October, 2013.
The motion for the adoption of the foregoing resolution was introduced by Council Member
Roeser and was duly seconded by Council Member
y y Rafferty and upon
vote being taken thereon, the following voted in favor thereof:
Roeser, Rafferty, Stoesz, O'Donnell, Reinert
The following voted against same:
none
ATTEST:
•
T
Ci Cler
Juli: e Bartell, �y
1
•
•
CITY COUNCIL
AGENDA ITEM 6A
STAFF ORIGINATOR: Jason C. Wedel, City Engineer
MEETING DATE: November 26, 2012
TOPIC: Consider Resolution No. 13 -117 Approving Pay Request 1F (Final)
and Compensating Change Order No. 1, 2013 Sealcoat Project
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND
At the July 22, 2013 meeting, City Council awarded the 2013 Sealcoat Project contract to Allied
Blacktop, Inc. in the amount of $62,422.00.
The contractor for the 2013 Sealcoat Project, Allied Blacktop, Inc. is requesting City approval of
Payment Request 1F (Final) in the amount of $60,093.46. A copy of the Final Payment is attached.
The contractor has satisfactorily completed all work and has provided all necessary documentation.
Also included with the request for Final Payment is Compensating Change Order No. 1 in the
amount of ($2,328.54). A copy of the Compensating Change Order is attached. With this change
order, the final project amount is $60,422.00.
Approval of the Final Payment will begin the two year warranty period.
RECOMMENDATION
Approve Resolution 13 -117, Approving Payment Request No. 1F (Final) and Compensating
Change Order No. 1, 2013 Sealcoat Project.
ATTACHMENTS
Pay Request No. 1 & Final
Change Order No. 1
•WSB
& Associates, Inc.
Owner: City of Lino Lakes
600 Town Center Parkway
Lino Lakes, MN 55014-1182
For Period: 8/1/2013 to 9/25/2013
Contractor: Allied Blacktop
10503 89th Avenue North
Maple Grove, MN 55369
Pay Voucher
LINO - 2013 Sealcoat Project
Client Contract No.:
Project No.: 02029 -53
Client Project No.:
Date: 9/25/2013
Request No.: 1 & FINAL
Project Summary
1
Original Contract Amount
$62,422.00
2
Contract Changes - Addition
$0.00
3
Contract Changes - Deduction
$0.00
4
Revised Contract Amount
$62,422.00
5
Value Completed to Date
$60,093.46
6
Material on Hand
$0.00
7
Amount Earned
$60,093.46
8
Less Retainage
$0.00
9
Subtotal
$60,093.46
10
Less Amount Paid Previously
$0.00
11
Liquidated Damages
$0.00
12
AMOUNT DUE THIS PAY VOUCHER NO. 1 & FINAL
$60,093.46
1 HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT
THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL
VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE
WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER.
Recommended for Approval by:
WSB„, Associates, Inc.
roved by Contractor.
Allied Blacktop
Specified Contract Completion Date:
8/30/2013
Comment:
•
Construction Observer:
proved by 'Owner:
C Lino Lakes
Date:
■ 44q Tip
•
Project Material Status
Item
No.
Item
Description
Units
Unit
Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
SCHEDULE A - SEAL COAT IMPROVEMENT
1
2231.608
BITUMINOUS CRACK SEAL - OWNER SUPPLIED
POUND
$1.00
2000
1750
1750
$1,750.00
2
2356.505
BITUMINOUS MATERIAL FOR SEAL COAT (CRS -2)
SQ YD
$1.36
38200
38131
38131
$51,858.16
3
2582.501
PAVEMENT MESSAGE (LEFT -THRU ARROW) EPDXY
EACH
$185.00
2
2
2
$370.00
4
2582.501
PAVEMENT MESSAGE (RIGHT ARROW) EPDXY
EACH
$135.00
2
1
1
$135.00
5
2582.502
4" SOLID LINE WHITE -EPDXY
LIN FT
$0.34
1500
1360
1360
$462.40
6
2582.502
4" DOUBLE SOLID LINE YELLOW -EPDXY
LIN FT
$0.70
7500
7357
7357
$5,149.90
7
2582.503
CROSSWALK MARKING -EPDXY
SQ FT
$4.60
450
80
80
$368.00
Totals For SCHEDULE A - SEAL COAT IMPROVEMENT:
$60,093.46
Project Totals:
$60,093.46
•
Project Payment Status
Owner: City of Lino Lakes
Client Project No.:
Client Contract No.:
Project No.: 02029 -53
Contractor. Allied Blacktop
Contract Chances
No.
'Type
Date
Description
Total
Payment
Amount
Total
Retainage
Total
Payment +
Retainage
Work
Certified Per
Payment
Total Work
Certified
1 &
FINAL
Change Order Totals:
9/25/2013
$0.00
Payment Summa
No.
From
Date
To Date
Payment
Total
Payment
Retainage
Per
Payment
Total
Retainage
Total
Payment +
Retainage
Work
Certified Per
Payment
Total Work
Certified
1 &
FINAL
8/1/2013
9/25/2013
$60,093.46
$60,093.46
$0.00
$0.00
$60,093.46
$60,093.46
$60,093.46
Payment Totals:
$60,093.46
$0.00
$60,093.46
$60,093.46
Project Summary
Material On Hand:
Total Payment to Date:
Total Retainage:
Total Amount Earned:
•
$0.00
$60,093.46
$0.00
$60,093.46
Original Contract:
Contract Changes:
Revised Contract:
$62,422.00
$0.00
$62,422.00
CHANGE ORDER NO. 1
2013 SEAL COATING IMPROVEMENT
CITY OF LINO LAKES, MN
WSB PROJECT NO. 2029-53
OCTOBER 17, 2013
OWNER:
CITY OF LINO LAKES
600 TOWN CENTER PARKWAY
LINO LAKES, MN 55014
CONTRACTOR:
ALLIED BLACKTOP COMPANY
10503 NTH AVENUE NORTH
MAPLE GROVE, MN 65369
YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION:
This compensating change order shows the actual quantities installed at the unit price bid amounts (see attached itemization).
ADDITIONAL CONTRACT QUANTITIES ARE SHOWN ON THE ATTACHED DETAIL SHEET.
R IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR
FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE.
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
ORIGINAL CONTRACT PRICE:
EVIOUS CHANGE ORDERS: N/A
ONTRACT PRICE PRIOR TO THIS CHANGE ORDER:
NET DECREASE OF THIS CHANGE ORDER:
CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS:
562,422.00
50.00
562,422.00
(52,328.54)
560,093.46
ORIGINAL CONTRACT TIME:
NET CHANGE FROM PREVIOUS CHANGE ORDERS:
CONTRACT TIME PRIOR TO THIS CHANGE ORDER:
NET INCREASE OF CHANGE ORDER:
CONTRACT TIME WITH APPROVED CHANGE ORDERS
9/30/2013
NONE
9/30/2013
NONE
9/30/2013
RECOMMENDED BY:
SON C. WEDEL, PE, PROJECT MANAGER
WSB & ASSOCIATES, INC.
ENGINEER
CONTRACTOR SIGNATURE
AWED BLACKTOP COMPANY
CONTRACTOR
APPROVED BY:
CITY ENGINEER
�0 h (I 3
DATE
GFPf-A16,6841&? 'Weft
10 /?i11
DATE
Pagel
K.102029-5301AdrniniConstrucdon Model
2029 -63 Change Order 1401713001
CHANGE ORDER NO. 1 DETAIL
2013 SEAL COATING IMPROVEMENT
CITY OF UNO LAKES, MN
WSB PROJECT NO. 2029-53
OCTOBER 17, 2013
ADDED ITEMS
Item No. Mat. No. Description
Qty Unit Price Extended Amount
TOTAL ADDED ITEMS CHANGE ORDER NO. 1
DELETED ITEMS
$0.00
Item No. Mat. No. Description
Qty Unit Price Extended Amount
8 2231.608 BITUMINOUS CRACK SEAL - OWNER SUPPLIED -250 POUND $1.00 ($250.00)
9 2356.505 BITUMINOUS MATERIAL FOR SEAL COAT (CRS -2) -69 SQ YD $1.36 ($93.84)
10 2582.501 PAVEMENT MESSAGE (RIGHT ARROW) EPDXY -1 EACH $135.00 ($135.00)
11 2582.502 4" SOLID LINE WHITE -EPDXY -140 LIN FT $0.34 ($47.60)
12 2582.502 4" DOUBLE SOLID LINE YELLOW -EPDXY -143 UN FT $0.70 ($100.10)
13 2582.503 CROSSWALK MARKING -EPDXY -370 SQ FT $4.60 ($1,702.00)
TOTAL DELETED ITEMS CHANGE ORDER NO. 1
TOTAL ADJUSTMENT TO ORIGINAL CONTRACT AMOUNT
($2,328.54)
($2,328.54)
K: 102029- S301AdmintCanshudton Admint
Page 2 2029 -53 Change Order 1- 101713001 Detail