HomeMy WebLinkAbout2007-060 Council Resolution•
•
•
Council Member Reinert introduced the following resolution and moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 07-60
RESOLUTION APPROVING CHANGE ORDER NO. 4
LEGACY AT WOODS EDGE PHASE 1— STREET AND UTILITY IMPROVEMENTS
WHEREAS, pursuant to the resolution of the Council adopted August 22, 2005,
awarding the construction contract for the Legacy at Woods Edge Phase 1 - Street and
Utility Improvements to Glenn Rehbein Companies, and
WHEREAS, the contract requires amendment to include the installation of the sanitary
sewer lift station and electrical and mechanical equipment and adjust sanitary sewer,
water main, storm sewer and street improvement quantities to reflect actual constructed
quantities.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA that:
1. Change Order No.4 related to the installation of lift station electrical and
mechanical equipment and a reduction of in estimated quantities unit quantities
to reflect actual constructed quantities in the amount of $10,600.98 is hereby
approved.
ne Bartell, ty C -r
Jo J. Bergeson, Mayor
Adopted by the Lino Lakes City Council this 23rd day of April 2007.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member o' Donneltind upon vote being taken thereon, the following voted in favor
thereof:
Reinert, O'Donnell, Carlson, Stoltz, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
•
•
AGENDA ITEM 6C
STAFF ORIGINATOR: Michael Grochala
CITY COUNCIL
MEETING DATE: April 23, 2007
TOPIC:
Resolution No. 07 -60, Approving Change Order No.
4, Legacy at Woods Edge Phase 1 — Street and Utility
Improvements
ACTION REQUIRED: Simple Majority
BACKGROUND
On August 22, 2005 the City Council awarded the Legacy at Woods Edge Phase 1 —
Street and Utility Improvements contract to Glenn Rehbein Companies. The current
approved contract amount is $2,631,683.85.
Change Order No. 4 is for the installation of lift station control panel and mechanical
equipment and for the reduction of sanitary sewer, water main, storm sewer and street
improvement quantities to reflect actual construction quantities. The total cost of the
Change Order is $10,600.98.
The total revised contract amount, with the change order, is $2,642,284.83.
The cost of the improvements were previously included in the City's financing package
and special assessments levied against the properties.
RECOMMENDATION
Staff is recommending the adoption of Resolution No. 07 -60, Approving Change Order
No.4 in the amount of $10,600.98.
ATTACHMENTS
1. Resolution No. 07 -60
2. Change Order No. 4
• SEH CHANGE ORDER
City of Lino Lakes, Minnesota March 19, 2007
OWNER DATE
OWNERS PROJECT NO.
Legacy at Woods Edge - Phase 1
PROJECT DESCRIPTION
4
CHANGE ORDER NO.
A- LINOL0305.03
SEH FILE NO.
The following changes shall be made to the contract documents:
Description:
1. Contractor shall install lift station control panel by SyCom, pumps, piping, and fittings at a cost of
$68,877.00
2. Deduct 0.68 LF Extra Depth Sanitary Manhole, 20 LF 6" Forcemain, 35 LF 6" DIP Water Main Class
52, 62 LF 8" DIP Water Main, Class 52, 1 Each 10 "x6" Wet Tap, 2 Each 8" Gate Valve & Box, 893 LF 1"
Type "K" Copper Tubing, 27 LF Support Existing Storm Sewer Pipe 18 ", 50 LF Support Existing Storm
Sewer Pipe 24 ", 247 SF Colored Concrete and add 63.71,,L,P Bituminous Non -Wear Type LV NW 35030C
Mixture (Roadway). (- $58,276.02).
Purpose of Change Order:
1. Amend scope of contract to include installation of lift station control panel, pumps and all associated
piping. Lift station is to serve proposed townhouses on Woods Edge Boulevard.
2. Reduction in Sanitary Sewer, Water Main, Storm Sewer, and Street Improvement quantities to reflect
actual constructed quantities.
Basis of Cost: ® Actual
Attachments (list supporting documents)
Letter from Glenn Rehbein Companies dated July 17, 2006.
❑ Estimated
Contract Status
Original Contract
Net Change Prior C.O.'s 1 to 3
Change this C.O.
Revised Contract
Recommended for Approval: Sort Elliott Hendrickson Inc. by
to by race
Time
N/A
Cost
$2,231,503.85
$400,180.00
$10,600.98
$2,642,284.83
an Mas. /Pro - t Manager
App d for Owner:
Glenn Rehbein Companies BY
71:)/2<i) eci il'l4w4c
TITLE
Distribution Contractor 2 Owner 1
s: lco \1 \I ino 0030503\constructionphl \c:o #4.doc
Project Representative 1
City of Lino Lakes, Minnesota
TITLE
SEH Office 1
Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-5196
SEH is an equal opportunity employer 1 www.sehinc.com 1 651.490.2000 1 800.325.2055 1 651.490.2150 fax
1/04
11/02/2008 12:02 IFAX Fax @sehinc.com • Debbie McJames el 002/003
Nov. 2. 2006 11:01AM Glenn Rehbein Companies No. 2556 P. 2
• REHBEIN(
COMPANIES
•
•
July 17, 2006
Mr. Stefan Higgins
Short Elliott Hendrickson, Inc
3535 Vadnais Center Drive
St. Paul, MN 55110 -5196
Ph (651)490 -2000 * Fax (651)490 -2150
Re: Change Order # 1— Lift Station
Legacy at Woods Edge — Phase 1
Lino Lakes, MN
8661 NAPLES ST. N.E.
BLAINE, MN 55449
Phone (763) 784-0667
Fax (763) 7844001
www.rehbein.00m
Equal Opportunity Employer
Glenn Rehbein Excavating, Inc (GRE) is requesting a change order for the following:
Description:
Lift Station
Includes: control panel by SyCom, pumps, piping, and fittings.
Excludes: pre-cast concrete structure.
Please issue us a change order in the amount of $68,877.00 for this additional work,
If you have any questions, please give me a call.
Respectfully:
Jason Pauly
Glenn Rehbein Companies
Added Cost
$68,877.00