HomeMy WebLinkAbout2007-168 Council Resolution•
•
Council MemberReinert introduced the following resolution and moved its
adoption:
CITY OF LINO LAKES
RESOLUTION NO. 07-168
APPROVING PAYMENT REQUEST NO. 2 CHANGE ORDER NO. 1,
LINO PARK GRADING AND TRAIL IMPROVEMENTS
WHEREAS, pursuant to the resolution of the Council adopted July 23, 2007, awarding
the contract for Lino Park Grading and Trail Improvements to Jay Brothers, Inc.;
WHEREAS, a complete breakdown is detailed in Payment No. 2 and Change Order no. 1;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
Payment No. 2 and Change Order No. 1 in the amount of $20,578.22, which results in a
total project cost of $67,668.25 are approved for the Lino Park Grading and Trail
Improvements.
e Bartell, City 1
Adopted by the Lino Lakes City Council this 8th day of October, 2007.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member Carlson and upon vote being taken thereon, the following voted in favor
thereof:
Reinert, Carlson, O'Donnell, Stoltz, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
AGENDA ITEM 6D
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: October 8, 2007
TOPIC: Resolution No. 07 -168, Approving Payment Request No. 2 and Change
Order No. 1, Lino Park Grading and Trail Improvements.
VOTE REQUIRED: Simple Majority
BACKGROUND:
At the July 23, 2007 meeting, City Council awarded the Lino Park Grading and Trail
• Improvements to Jay Brothers, Inc.
The contractor for the Surface Lino Park Grading and Trail Improvements, Jay Brothers,
Inc. is requesting City approval of Payment No. 2 in the amount of $20,578.22. A copy
of the payment and change order is attached. The change order covers additional grading
work required by the Rice Creek Watershed District and extra topsoil placement on site.
Staff recommends approval of Payment No. 2 in the amount of $20,578.22 and Change
Order No. 1 in the amount of $3,671.00, which results in a total project cost of
$67,668.25. The total project cost is under the engineers estimate of $91,460.
RECOMMENDATION:
Staff recommends the approval of Resolution No. 07 -168, Approving Payment Request
No. 2 and Change Order No. 1, Lino Park Grading and Trail Improvements.
•
TKDA
ENGINEERS • ARCHITECTS • PLANNERS
444 Cedar Street, Suite 1500
Saint Paul, MN 55101 -2140
(651) 292-4400
(651) 292-0083 Fax
www.tkda.com
Proj. No. 13849.003 Cert. No. 2 St. Paul, MN, October 1 , 20 07
To City of Lino Lakes, Minnesota
This Certifies that Jay Brothers, Inc.
Owner
, Contractor
For Lino Park Grading and Trail Work
Is entitled to Twenty Thousand Five Hundred Seventy -Eight Dollars and 22/100 ($ 20,578.22)
being 2nd
estimate for partial payment on contract with you dated July 23 , 07
Received payment in full of above Certificate. TKDA
Jay Brothers, Inc.
, 20
Thomas D. Prew, P.E.
RECAPITULATION OF ACCOUNT
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
63,997.25
All previous payments
$
41,059.48
All previous credits
Extra No.
Change Order No. 1
$
3,671.00
„ „
Credit No.
$ -
„ „
AMOUNT OF THIS CERTIFICATE
$
20,578.22
Totals
$
67,668.25
$
61,637.70
$ -
Credit Balance
$
-
There will remain unpaid on contract after
payment of this Certificate
$
6,030.55
$
67,668.25
$
67,668.25
$ -
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
•
TKDA
Engineers- Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 2 Period Ending September 28 , 20 07 Page 1 of 1 Proj. No. 13849.003
Contractor Jay Brothers, Inc. Original Contract Amount $63,997.25
Project Lino Park Grading and Trail Work
Location City of Lino Lakes, Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed $ 0.00
Approved Extra Orders Amount Completed
Total Amount Earned This Estimate
$ 64,881.79
$ 0.00
$ 0.00
$ 64,881.79
Less Approved Credits $ 0.00
Less 5 % Retained $ 3,244.09
Less Previous Payments $ 41,059.48
Total Deductions $
Amount Due This Estimate $
44,303.57
20,578.22
Contractor Date
Jay Brothers, Inc.
• Engineer Date
Thomas D. Prew
ESTIMATE NO. 2
LINO LAKES GRADING AND TRAIL WORK
Y OF LINO LAKES, MINNESOTA
A PROJECT NO. 13849.003
PERIOD ENDING: September 28, 2007
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
1 MOBILIZATION LS 1 1.0 $ 2,300.00 $ 2,300.00
2 COMMON EXCAVATION CY 2,972 2,972.0 $ 4.50 $ 13,374.00
3 CLASS 5 AGGREGATE BASE TN 1,300 1,049.0 $ 12.50 $ 13,112.50
4 2" 2360 BITUMINOUS WEAR COURSE TN 275 283.2 $ 52.63 $ 14,904.29
5 TOPSOIL BORROW (LV) CY 1,800 1,800.0 $ 8.00 $ 14,400.00
6 SILT FENCE (INSTALL AND REMOVE) LF 1,600 1,560.0 $ 2.00 $ 3,120.00
TOTAL $ 61,210.79
CHANGE ORDER NO. 1
1 ADDITIONAL COMMON EXCAVATION CY 430.0 430.0 $ 4.50 $ 1,935.00
2 ADDITIONAL TOPSOIL BORROW CY 217.0 217.0 $ 8.00 $ 1,736.00
TOTAL CHANGE ORDER NO. 1 $ 3,671.00
TOTAL ESTIMATE NO. 2 $ 64,881.79
•
•
•
CHANGE ORDER
TKDA
Engineers- Architects - Planners
Saint Paul, MN October 1 20 07 Proj. No. 13849.003 Change Order No. 1
To Jay Brothers, Inc.
for Lino Lakes Grading and Trail Work
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
June 11 , 20 07 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decr aso) (not change) the contract sum by
Three Thousand Six Hundred Seventy -One Dollars and 00 /100 ($ 3,671.00 ).
This change order provides for changes in the work of this contract according to the attached itemization.
Item No. Description Unit Contract Quantity Unit Price Amount to Date
1 ADDITIONAL COMMON EXCAVATION CY 430 $4.50 $ 1,935.00
2 ADDITIONAL TOPSOIL BORROW CY 217 $8.00 $ 1,736.00
TOTAL $ 3,671.00
ft') NET CHANGE =
$ 3,671.00
Amount of Original Contract $ 63,997.25
Additions approved to date (Nos. )
Deductions approved to date (Nos. )
Contract amount to date $ 63,997.25
Amount of this Change Order (Add) (Decuet) (age) $ 3,671.00
Revised Contract Amount
Approved City of Lino Lakes TKDA
Owner
$ 67,668.25
By By
Thomas D. Prew, P.E.
Approved Jav Brothers, Inc.
Contractor
By
White - Owner
Pink - Contractor
Blue - TKDA