Council Membero' Donne -Introduced the following resolution and moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 07-207
RESOLUTION APPROVING PAYMENT REQUEST NO. 1 (FINAL) FOR THE
SANDHILL DRIVE STORM SEWER REMOVAL, CLEANING, AND
REINSTALLATION .
WHEREAS, pursuant to the resolution of the Council adopted October 8, 2007, awarding the
contract for Sandhill Drive Storm sewer Removal, Cleaning, and Reinstallation to Glenn
Rehbein Excavating, Inc.;
WHEREAS, a complete breakdown is detailed in attached Payment No. 1 (Final);
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
Payment No. 1 (Final) in the amount of $38,720.20 is approved for the Sandhill Drive Storm
sewer Removal, Cleaning, and Reinstallation.
•
Sul' 1 e Bartell, City) Cleric
Adopted by the Lino Lakes City Council this 17th day of December, 2007.
The motion for the adoption of the foregoing resolution was duly seconded by Council Member
Stoltz and upon vote being taken thereon, the following voted in favor thereof: O'Donnell , Stoltz,
The following voted against same: Reinert, Carlson,
Bergeson
none
Whereupon said resolution was declared duly passed and adopted.
•
•
•
AGENDA ITEM 6A
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: December 17, 2007
TOPIC: Resolution No. 07 -207, Approving Payment Request No. 1
(Final), Sandhill Drive Storm Sewer Removal, Cleaning,
and Reinstallation.
VOTE REQUIRED: Simple Majority
BACKGROUND:
Through routine street patching maintenance on Sandhill Drive during the week of September
28, 2007, Public Works discovered a sinkhole caused by joint separation in the storm sewer pipe.
After further investigation of the Sandhill Drive area on October 1 it was determined that the
storm sewer pipe would need to be removed, cleaned and reinstalled to prevent further roadway
damage and to maintain safe driving conditions on Sandhill Drive. The City Council accepted
quotes and authorized a contract with Glenn Rehbein Excavating, Inc on October 8, 2007 for the
Sandhill Drive Storm Sewer Removal, Cleaning and Reinstallation.
Glenn Rehbein Excavating, Inc. is requesting City approval of Payment No. 1(Final) in the
amount of $38,720.20. Included in this pay estimate is Change Order No. 1 in the amount of
$4,780.00 which covers the replacement of damaged pipe. Also included in this pay estimate is
Compensating Change Order No. 2 in the deduct amount of $3,808.80, a copy of the pay estimate
and change orders are attached.
Staff recommends approval of Payment No. 1 (Final) in the amount of $38,720.20, which results.
The total project cost is approximately 2.5% above the accepted quote of $37,749.00 due to the
replacement of damaged pipe.
RECOMMENDATION:
Staff recommends approval of Resolution No. 07 -207, Approving Payment Request No. 1 (Final)
for the Sandhill Drive Storm Sewer Removal, Cleaning, and Reinstallation.
TKDA
ENGINEERS • ARCHITECTS • PLANNERS
444 Cedar Street, Suite 1500
Saint Paul, MN 55101 -2140
(651) 292-4400
(651) 292 -0083 Fax
www.tkda.com
Proj. No. 13849.002 Cert. No. 1(F) St. Paul, MN, November 6 , 20 07
To City of Lino Lakes, Minnesota
This Certifies that Glenn Rehbein Companies
For Sandhill Drive Storm Sewer Removal, Cleaning, and Reinstallation
Is entitled to
being 1st
Owner
, Contractor
Thirty-Eight Thousand Seven Hundred Twenty Dollars and 20/100
FINAL
estimate for paftial payment on contract with you dated October 10
($ 38 720.20)
Received payment in full of above Certificate. TKDA
Glenn Rehbein Companies
, 20
it7f (A)no
Matthew J. Woodruff, P.E.
2007
RECAPITULATION OF ACCOUNT
t
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
37,749.00
All previous payments
$
-
All previous credits
Extra No.
Change Order No. 1
$
4,780.00
Compensating Change Order No. 2
$
(3,808.80)
Credit No.
$ -
„ „
VI VI
„ It
AMOUNT OF THIS CERTIFICATE
$
38,720.20
Totals
$
38,720.20
$
38,720.20
$ -
Credit Balance
$
-
There will remain unpaid on contract after
1payment of this Certificate
$
-
$
38,720.20
$
38,720.20
$ -
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
•
•
TKDA
Engineers - Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 1(F) Period Ending November 6 , 20 07 Page 1 of 1 Proj. No. 13849.002
Contractor Glenn Rehbein Companies Original Contract Amount $ 37,749.00
Project Sandhill Drive Storm Sewer Removal, Cleaning, and Reinstallation
Location City of Lino Lakes, Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed
Approved Extra Orders Amount Completed
Total Amount Earned This Estimate
$ 33,940.20
$ 0.00
4,780.00
$ 4,780.00
$ 38,720.20
Less Approved Credits $ 0.00
Less 0 % Retained $ 0.00
Less Previous Payments $ 0.00
Total Deductions $ 0.00
Amount Due This Estimate
Contractor
Glenn Rehbein Companies
Engineer iVl LA O
Matthew J. Woodruff, P.E.
$ 38,720.20
Date
Date >J 6 -7
PAY ESTIMATE NO. 1(F)
PERIOD ENDING: November 6, 2007
SANDHILL DRIVE STORM SEWER REMOVAL, CLEANING, AND REINSTALLATION
IIIKOF LINO LAKES, MINNESOTA
A PROJECT NO. 13849.002
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
SANITARY SEWER
1 MOBILIZATION LS 1 1.0 $ 525.00 $ 525.00
2 REMOVE CONCRETE CURB AND GUTTER LF 120 82.0 $ 2.10 $ 172.20
3 REMOVE BITUMINOUS SY 193 130.0 $ 3.00 $ 390.00
4 GRUB STUMPS EA 9 9.0 $ 30.00 $ 270.00
5 SALVAGE /RESPREAD TOPSOIL LS 1 1.0 $ 425.00 $ 425.00
6 REMOVE/CLEAN /RELAY 300 LF 30" RCP LF 300 300.0 $ 57.50 $ 17,250.00
7 ROCK TRENCH STABILIZATION (1' DEPTH) CY 290 186.0 $ 40.00 $ 7,440.00
8 ROD ALL PIPE JOINTS (LAST 3 AT FES MAY ALREADY BE DONE) LS 1 $ 3,050.00
1.0 $ 3,050.00
9 WRAP ALL PIPE JOINTS WITH FABRIC LS 1 1.0 $ 210.00 $ 210.00
10 CLEAN OUT POND AREA AT FES (WASTE MATERIAL ON SITE) EA 6 6.0 $ 80.00 $ 480.00
11 PLACE 1 -1/2" ROCK AT OUTFALLS (SEE DETAIL) CY 14 14.0 $ 42.00 $ 588.00
12 CLASS 5 TN 70 120.0 $ 22.00 $ 2,640.00
13 EROSION CONTROL BLANKET AT FES (EROSION LOGS) EA 6 - $ 80.00 $ -
14 WORK ZONE SIGNAGE - NOTIFY HOMES 24 HRS. BEFORE
START LS 1 10 $ 500.00 $ 500.00
SUBTOTAL BASE BID $ 33,940.20
CHANGE ORDER NO. 1
8 -FOOT SECTION OF 30" RCP EA 5.0 5.0 $ 365.40 $ 1,827.00
30" FLARED END SECTION EA 1.0 1.0 $ 590.00 $ 590.00
ADDITIONAL TIE RODS - MATERIAL LS 1.0 1.0 $ 1,163.00 $ 1,163.00
4 ADDITIONAL TIE RODS - LABOR LS 1.0 1.0 $ 1,200.00 $ 1,200.00
SUBTOTAL CHANGE ORDER NO. 1 $ 4,780.00
TOTAL PAY ESTIMATE NO. 1(F) $ 38,720.20
•
•
•
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
Saint Paul, MN November 6 20 07 Proj. No. 13849.002 Change Order No. 1
To Glen Rehbein Companies
for Sandhill Drive Storm Sewer Removal, Cleaning, and Reinstallation
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
October 10 , 20 07 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decrease) (not change) the contract sum by
Four Thousand Seven Hundred Eighty Dollars and 00 /100 ($ 4,780.00 ).
This change order provides for changes in the work of this contract according to the attached itemization.
Item Unit Total
No. Description Unit Qty Price Amount
1. 8 -foot Section of 30" RCP EA 5 $ 365.40 $1,827.00
2. 30" Flared End Section EA 1 $ 590.00 $ 590.00
3. Additional Tie Rods - Material LS 1 $1,163.00 $1,163.00
4. Additional Tie Rods - Labor LS 1 $1,200.00 $1,200.00
TOTAL $4,780.00
NET CHANGE =
Amount of Original Contract
Additions approved to date (Nos.
Deductions approved to date (Nos.
Contract amount to date
Amount of this Change Order (Add) (Deduet) (Ne- Mange)
Revised Contract Amount
Approved City of Lino Lakes, Minnesota
Owner
TKDA
By By
Approved Glenn Rehbein Companies
By
Contractor
$ 4,780.00
$ 37,749.00
$ 37,749.00
$ 4,780.00
$ 42,529.00
Matthew J. Woodruff, P.E.
White - Owner
Pink - Contractor
Blue - TKDA
•
CHANGE ORDER
TKDA
Engineers - Architects - Planners
COMPENSATING
Saint Paul, MN November 6 20 Proj. No. 13849.002 Change Order No. 2
To Glenn Rehbein Companies
for Sandhill Drive Storm Sewer Removal, Cleaning, and Reinstallation
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
October 10 , 20 07 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (ise) (decrease) (not change) the contract sum by
Three Thousand Eight Hundred Eight Dollars and 80/100 .($ 3,808.80 ).
This change order provides for changes in the work of this contract according to the attached itemization.
NET CHANGE =
$ (3,808.80)
Amount of Original Contract $ 37,749.00
Additions approved to date (Change Order No. 1 ) $ 4,780.00
Deductions approved to date (Nos. )
Contract amount to date $ 42,529.00
Amount of this Change Order (Add) (Deduct) (No Change) $ (3,808.80)
Revised Contract Amount $ 38,720.20
Approved City of Lino Lakes TKDA
Owner
By By V
Matthew J. Woodruff, P.E.
Approved
By
Glenn Rehbein Companies
Contractor
.0(77
White - Owner
Pink - Contractor
Blue - TKDA
COMPENSATING CHANGE ORDER NO. 2
SANDHILL DRIVE STORM SEWER REMOVAL, CLEANING, AND REINSTALLATION
CITY OF LINO LAKES, MINNESOTA
PROJECT NO. 13849.002
PERIOD ENDING: November 6, 2007
ITEM CONTRACT QUANTITY UNIT AMOUNT NET CONTRACT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE CHANGE AMOUNT
SANITARY SEWER
1 MOBILIZATION LS 1 1.0 $ 525.00 $ 525.00 $ - $ 525.00
2 REMOVE CONCRETE CURB AND GUTTER LF 120 82.0 $ 2.10 $ 172.20 $ (79.80) $ 252.00
3 REMOVE BITUMINOUS SY 193 130.0 $ 3.00 $ 390.00 $ (189.00) $ 579.00
4 GRUB STUMPS EA 9 9.0 $ 30.00 $ 270.00 $ $ 270.00
5 SALVAGE/RESPREAD TOPSOIL LS 1 1.0 $ 425.00 $ 425.00 $ $ 425.00
6 REMOVE/CLEAN /RELAY 300 LF 30" RCP LF 300 300.0 $ 57.50 $ 17,250.00 $ $ 17,250.00
7 ROCK TRENCH STABILIZATION (1' DEPTH) CY 290 186.0 $ 40.00 $ 7,440.00 $ (4,160.00) $ 11,600.00
8 ROD ALL PIPE JOINTS (LAST 3 AT FES MAY ALREADY BE DONE) LS 1 $ 3,050.00
1.0 $ 3,050.00 $ $ 3,050.00
9 WRAP ALL PIPE JOINTS WITH FABRIC LS 1 1.0 $ 210.00 $ 210.00 $ $ 210.00
10 CLEAN OUT POND AREA AT FES (WASTE MATERIAL ON SITE) EA 6 $ 80.00
6.0 $ 480.00 $ $ 480.00
11 PLACE 1 -1/2" ROCK AT OUTFALLS (SEE DETAIL) CY 14 14.0 $ 42.00 $ 588.00 $ - $ 588.00
12 CLASS 5 TN 70 120.0 $ 22.00 $ 2,640.00 $ 1,100.00 $ 1,540.00
13 EROSION CONTROL BLANKET AT FES (EROSION LOGS) EA 6 - $ 80.00 $ - $ (480.00) $ 480.00
14 WORK ZONE SIGNAGE - NOTIFY HOMES 24 HRS. BEFORE
START LS 1 1.0 $ 500.00 $ 500.00 $ - $ 500.00
SUBTOTAL BASE BID $ 33,940.20 $ (3,808.80) $ 37,749.00
CHANGE ORDER NO. 1
1 8 -FOOT SECTION OF 30" RCP EA 5.0 5.0 $ 365.40 $ 1,827.00 $ - $ 1,827.00
2 30" FLARED END SECTION EA 1.0 1.0 $ 590.00 $ 590.00 $ - $ 590.00
3 ADDITIONAL TIE RODS - MATERIAL LS 1.0 1.0 $ 1,163.00 $ 1,163.00 $ - $ 1,163.00
4 ADDITIONAL TIE RODS - LABOR LS 1.0 1.0 $ 1,200.00 $ 1,200.00 $ - $ 1,200.00
SUBTOTAL CHANGE ORDER NO. 1 $ 4,780.00 $ - $ 4,780.00
COMPENSATING CHANGE ORDER NO. $ 38,720.20 $ (3,808.80) $ 42,529.00
•
•