COUNCIL WORK SESSION APRIL 13, 1987
A Work Session of the Lino Lakes City Council with Engineer Ron
Stahlberg convened at 6:15 P.M. Mayor Benson and Council Members
Bisel, Bohjanen, Reinert were present. Council Member Marier was
absent. Public Works Director, Don Volk and Clerk - Treasurer, Marilyn
Anderson were also present. Mr. Schumacher was ill and did not
attend.
Mr. Stahlberg reviewed the maps he had prepared with respect to the
proposed sanitary sewer system. Mr. Stahlberg was asked if White Bear
Township could extend their sewer main without giving Lino Lakes
consideration. Mr. Stahlberg said that Metro Waste Control would be
aware of the extension and they are aware of Lino Lakes need in this
area.
Mr. Stahlberg was asked if the Forest Lake Interceptor was large
enough for others to use. Mr. Stahlberg thought it was, but will
check on this.
Mr. Stahlberg reviewed the map with respect to the proposed water main
system. He outlined how this facility could be built in stages
through the County Park as the need arises.
Mr. Bisel asked if Lino Lakes built a water tower large enough, would
Centerville be interested in using it as well. Mr. Stahlberg said the
mains could be extended east on Birch Street and then north on
Centerville Road. Centerville could use this system until Lino Lakes
grows large enough to use the complete facility.
Mr. Stahlbergs map showed the water main installation in three stages.
The cost of the first stage going from the west to the east is
estimated at $381,200, the next stage would be $366,400 and the third
stage that would terminate new 12th Avenue is $95,000. These figures
do not include the cost of a water tower.
There was discussion of placing the water tower at 12th Avenue and
Birch Street. Mr. Stahlberg explained the cost of maintenance would
be high because it is at the end of the water main and would require
winter care. He recommended that the mains be built in stages as
outlined on his map and delay construction of the water tower for now.
As the area develops the City could take another look at where a tower
should be built.
Mr. Stahlberg's initial recommendation is that in 1987 the City build
the mains from Rice Lake Estates to tie into the Uhde development,
Erickson development and Lakes Additions developments. This cost would
be approximately $747,600. This would be basically building the
entire water main system. The advantages would be; lower initial
PAGE 1
064
COUNCIL WORK SESSION APRIL 13, 1987
cost, no cold weather protection costs and would allow faster
development of the area. This would mean that both well no. 1 and
well no. 2 would be hooked into these mains. The disadvantage would
be a restricted fire flow from Circle Pines and limited capacity fro
Circle Pines. This plan also allows the City to buy time before the
investment in a water tower.
Mr. Stahlberg outlined the costs of elevated water tanks. A 500,000
gallon tank would cost approximately $450,000, a 750,000 gallon tank
would cost $650,000 and a 1,000,000 gallon tank would cost
approximately $850,000. These figures do not include the cost of the
well or the mains going to the tank.
Mr. Stahlberg provided a population estimate for the period through
the year 2000. He projected a population of 8,600 by that year. He
also felt his figures were conservative. He also noted that most of
this additional population would be situated where services are
available.
Mr. Stahlberg was asked to determine at what point Circle Pines will
be forces to discontinue water service to Lino Lakes (how many
connections would there be in Lino Lakes at that point). At that
point Lino Lakes would be forced to build a water tank. He noted that
there are some advantages for Circle Pines to continue the linkup
between the two cities such as our well no. 2 can be used as a backup
well for Circle Pines. Mr. Volk noted that Circle Pines currently has
a problem with not enough wells.
The Council felt this recommendation was worth looking into and aske
the Mr. Schumacher contact Springsted, Inc. and determine the cost per
year of a system with just the installation of water mains and the
second cost estimate would be with the water mains and a one million
gallon tank.
Mr. Stahlberg was asked to pursue the recommendation with Circle Pines
do determine if it is feasible to continue researching this idea.
Mr. Stahlberg then restated the two options that he will consider: 1)
installation of water mains from Rice Lake Estates to Black Duck Drive
without a storage tank; 2) water mains from Rice lake Estates to 12th
Avenue with a one million gallon water storage tank.
Mayor Benson asked if it was feasible to put up a storage tank and
then not use it? Mr. Stahlberg said it is feasible, however the
problem would be, how are you going to finance it? Mr. Volk said that
Shoreview currently shuts down the large tank on Lexington Avenue for
the winter months only using in the summer when the demand is higher.
PAGE 2
1
1
065
COUNCIL WORK SESSION APRIL 13, 1987
There was discussion of charging a water availability charge. Mr.
Stahlberg said this would help build up a fund for future extension of
water mains. At this point Lino Lakes has a problem with not enough
customers.
The Council took a break at 7:03 P.M.
PAGE 3