CITY OF LINO LAKES
RESOLUTION NO. 04 -97
RESOLUTION APPROVING CHANGE ORDER NO.1 AND PAYMENT REQUEST NO. 2 —
TWILIGHT ACRES WATERMAIN IMPROVEMENTS.
WHEREAS, the construction of the project has been begun,
AND WHEREAS, relocation of mailboxes, subcut of additional sod areas, additional sod for the
sewer project area, and installation of additional sanitary sewer service for the Twilight Acres
Watermain Improvements,
AND WHEREAS, a complete breakdown is spelled out in the Change Order;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. Change Order No.1 resulting in a increase of $14,056.84 bringing the contract amount to
$179,249.34 and Pay Request No. 2 in the amount of $26,875.58 is approved for the
Twilight Acres Watermain Improvements.
Adopted by the Lino Lakes City Council this 12th day of July 2004.
Ann J. Ba)r, City Clerk
John Bergeson, Mayor
•
•
•
AGENDA ITEM 6G
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: July 12, 2004
TOPIC: Resolution No. 04 -97, Approving Change Order No. 1 and Payment
Request No. 2, Twilight Acres Watermain Improvements
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND:
At the July 14, 2003 meeting, City Council awarded the Twilight Acres Watermain
Improvements contract to C & L Excavating, Inc. in the amount of $165,192.50.
The Change Order addresses the relocation of mailboxes, subcut of additional sod
areas, additional sod for the sewer project area, and installation of additional sanitary
sewer service for the Twilight Acres Watermain Improvements. This increases the total
project contract to $179,249.34. A complete breakdown is spelled out in the attached
Change Order.
It is staff's recommendations to approve Change Order No. 1, which results in a total
project cost increase of $14,056.84 and authorize Payment No. 2 in the amount of
$26,875.58.
OPTIONS:
1. Return to staff for further review.
2. Adopt Resolution Number 04 -97, approving Change Order No.1 and Payment
Request No. 2 for the Twilight Acres Watermain Improvements.
3. Not adopt Resolution No. 04 -97.
RECOMMENDATION:
Option No. 2 - Staff recommends adoption of Resolution Number 04 -97.
TKDA
ENGINEERS • ARCHITECTS • PLANNERS
ER-
1500 Piper Jaffray Plaza
444 Cedar Street
Saint Paul, MN 55101 -2140
(651) 292 -4400
(651) 292 -0083 Fax
www.tkda.com
Comm. No. 12278 -05 Cert. No. 2 St. Paul, MN, May 19 , 20 04
To City of Lino Lakes, Minnesota
This Certifies that C & L Excavating, Inc.
Owner
, Contractor
For Twilight Acres Watermain Improvements
Is entitled to Twenty Six Thousand Eight Hundred Seventy -Five Dollars and 58/100 ($ 26,875.58 )
being 2nd estimate for partial payment on contract with you dated July 14 , 2003
Received payment in full of above Certificate.
,20
TKDA
Scott . Brink, P.E.
RECAPITULATION OF ACCOUNT
-48-
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
CON '1'KACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
165,192.50
All previous payments
$
143,321.64
All previous credits
Extra No.
Change Order No. 1
$
14,056.84
11 11
„ ,I
„ 11
Credit No.
$
O „
11 - ,I
11 11
11 O
AMOUNT OF THIS CERTIFICA'1h
$
26,875.58
Totals
$
179,249.34
$
170,197.22
$ -
Credit Balance
There will remain unpaid on contract after
payment of this Certificate
$
9,052.12
$
179,249.34
$
179,249.34
$ -
-48-
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
TKDA
Engineers - Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 2 Period Ending March 19 , 20 04 Page 1 of 1 Comm. No. 12278 -05
Contractor C & L Excavating, Inc. Original Contract Amount $165,192.50
Project Twilight Acres Watermain Improvements
Location City of Lino Lakes, Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed $ 0.00
Approved Extra Orders Amount Completed (CO No. 1)
Total Amount Earned This Estimate
•
Less Approved Credits
Less 5 % Retained
Less Previous Payments
Total Deductions
$ 165,098.13
$ 0.00
$ 14,056.84
$' 179,154.97
$ 0.00
$ 8,957.75
$ 143,321.64
$ 152,279.39
Amount Due This Estimate $ 26,875.58
Date nl Vic^ / •�& I
Date May 19, 2004
ES 7 (MATE NO. 2
ILIGHT ACRES WATERMAIN IMPROVEMENTS
TY OF LINO LAKES, MINNESOTA
TKDA COMMISSION NO. 12278 -05
PERIOD ENDING: March 19, 2004
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
DIVISION I - WATERMAIN CONSTRUCTION
1 CONNECT TO EXISTING WATERMAIN EA 2.0 2.0 $ 450.00 $ 900.00
2 8" DIP WATERMAIN (CL 52) LF 1,610.0 1,568.0 $ 20.50 $ 32,144.00
3 6" DIP WATERMAIN (CL 52) LF 40.0 31.0 $ 35.00 $ 1,085.00
4 8" GATE VALVE AND BOX EA 4.0 4.0 $ 850.00 $ 3,400.00
5 6" GATE VALVE AND BOX EA 3.0 3.0 $ 650.00 $ 1,950.00
6 FIRE HYDRANT EA 3.0 3.0 $ 1,900.00 $ 5,700.00
7 1" COPPER SERVICE PIPE (TYPE K) LF 780.0 899.0 $ 19.20 $ 17,260.80
8 1" CORPORATION STOP EA 25.0 26.0 $ 50.00 $ 1,300.00
9 1" CURB STOP AND BOX EA 25.0 26.0 $ 75.00 $ 1,950.00
10 DIP FITTINGS LBS 800.0 640.0 $ 3.50 $ 2,240.00
11 INSULATION (4" THICKNESS) SF 224.0 $ 5.00 $
12 TRENCH STABILIZATION ROCK LF 1,600.0 $ 3.00 $
SUBTOTAL - DIVISION I $ 67,929.80
DIVISION II - STREET CONSTRUCTION AND RESTORATION
1 MOBILIZATION LS 1.0 1.0 $ 7,200.00 $ 7,200.00
2 TRAFFIC CONTROL LS 1.0 1.0 $ 2,000.00 $ 2,000.00
3 CLEAR AND GRUB TREE 5.0 $ 300.00 $
4 REMOVE BITUMINOUS PAVEMENT (ALL DEPTHS) SY 810.0 1,023.0 $ 2.75 $ 2,813.25
5 SAWCUT BITUMINOUS PAVEMENT (ALL DEPTHS) LF 413.0 487.0 $ 3.00 $ 1,461.00
6 COMMON EXCAVATION (STREET AND DRIVEWAY) CY 250.0 1,077.0 $ 18.00 $ 19,386.00
4•8 7 AGGREGATE BASE (CL 5) 100% CRUSHED TON 2,100.0 1378.32 $ 15.00 $ 20,674.80
2350 TYPE LV 3 WEAR COURSE B TON 700.0 734.32 $ 41.50 $ 30,474.28
9 TOPSOIL BORROW (LV) CY 300.0 276.0 $ 14.00 $ 3,864.00
10 SOD - LAWN TYPE SY 2,000.0 2,438.0 $ 2.50 $ 6,095.00
11 EROSION CONTROL FENCE LF 100.0 - $ 4.00 $
12 ADJUST SANITARY MANHOLE EA 8.0 8.0 $ 400.00 $ 3,200.00
SUBTOTAL - DIVISION II $ 97,168.33
TOTAL DIVISION I AND II $ 165,098.13
CHANGE ORDER NO. 1
MOVE MAIL BOXES AS REQUIRED BY USPS EA 9.0 $ 60.00 $ 540.00
$ -
2
•
EQUIPMENT AND LABOR TO SUBCUT ADDITIONAL SOD AREAS
AND HAUL OUT EXCESS (GRADING AND PREP WORK FOR
ADDITIONAL SOD IN THE SAN SEWER PROJECT AREA) $ -
TANDEM DUMP TRUCK HR 16.5 $ 58.00 $ 957.00
SKID STEER HR 16.5 $ 82.00 $ 1,353.00
$
ADDITIONAL SOD QUANTITY FOR SEWER PROJECT AREA SY 3,000.0 $ 2.50 $ 7,500.00
$ -
LABOR AND EQUIPMENT TO INSTALL ADDITIONAL SANITARY
SEWER SERVICE LS 1.0 $ 3,706.84 $ 3,706.84
SUBTOTAL CHANGE ORDER NO. 1 $ 14,056.84
TOTAL ESTIMATE NO. 2 $ 179,154.97
•
O j) 5&
CHANGE ORDER
TKDA
Engineers- Architects - Planners
Saint Paul, MN May 19 20 04 Comm. No. 12278 -05 Change Order No. 1
To C &L Excavating, Inc.
for Twilight Acres Watermain Improvements
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
July 14 , 20 03 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) the contract sum by $14,056.84
Fourteen Thousand , Fifty Six Dollars and 84/100.
This change order provides for changes in the work of this contract according to the attached itemization.
NET CHANGE =
Amount of Original Contract
Additions approved to date (Nos.
Deductions approved to date (Nos.
Contract amount to date
Amount of this Change Order () (Deduct
Revised Contract Amount
Approved City of Lino Lakes, Minnesota TKDA
Owner
By By
14,056.84
$ 165,192.50
$ 165,192.50
$ 14,056.84
$ 179,249.34
.//
Scott A. Brink, P.E.
Approved C & L Excavating, Inc. White - Owner
Contractor Pink - Contractor
Blue - TKDA
ry
By
CHANGE ORDER NO. 1 DATE: May 19, 2004
fight Acres Watermain Improvements
OF LINO LAKES, MINNESOTA
COMMISSION NO. 12278 -053
ITEM UNIT
NO. DESCRIPTION UNIT QUANTITY PRICE AMOUNT
CHANGE ORDER NO. 1
1 MOVE MAIL BOXES AS REQUIRED BY USPS EA 9.0 $ 60.00 $ 540.00
2 EQUIPMENT AND LABOR TO SUBCUT ADDITIONAL SOD AREAS AND
HAUL OUT EXCESS (GRADING AND PREP WORK FOR ADDITIONAL SOD
IN THE SAN SEWER PROJECT AREA)
TANDEM DUMP TRUCK HR 16.5 $ 58.00 $ 957.00
SKID STEER HR 16.5 $ 82.00 $ 1,353.00
3 ADDITIONAL SOD QUANTITY FOR SEWER PROJECT AREA SY 3,000.0 $ 2.50 $ 7,500.00
4 LABOR AND EQUIPMENT TO INSTALL ADDITIONAL SANITARY SEWER
SERVICE LS 1.0 $ 3,706.84 $ 3,706.84
SUBTOTAL CHANGE ORDER NO. 1 $ 14,056.84
•