HomeMy WebLinkAbout2004-107 Council ResolutionCITY OF LINO LAKES
RESOLUTION. NO. 04-107
RESOLUTION APPROVING CHANGE ORDER NO.2 AND PAYMENT REQUEST NO. 3 - 21ST
AVENUE STREET AND STORM SEWER IMPROVEMENTS PROJECT.
WHEREAS, the construction of the project has been begun,
AND WHEREAS, aggregate base, non - wearing course bituminous pavement, and 4" draintile
was added for the 21st Avenue Street and Storm Sewer Improvements Project,
AND WHEREAS, a complete breakdown is spelled out in the Change Order;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
Change Order No.2 resulting in a increase of $13,646.98 bringing the contract amount to
$247,842.63 and Pay Request No. 3 in the amount of $28,708/3 is approved for the 21st
Avenue Street and Storm Sewer Improvements Project.
Adopted by the Lino Lakes City Council this 26th day of July 2004.
Berge on, Mdyor
AGENDA ITEM 6M
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: July 26, 2004
TOPIC: Resolution No. 04 -107, Approving Change Order No. 2 and Payment
Request No. 3, 21st Avenue Street and Storm Sewer Improvements
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND:
The 21st Avenue Street and Storm Sewer Improvements contract to Arnt Construction
Company, Inc. is in the amount of $234,195.65.
The Change Order addresses the addition of aggregate base, non - wearing course
bituminous pavement, and 4" draintile. This raises the total project contract to
$247,842.63. A complete breakdown is spelled out in the attached Change Order.
It is staff's recommendations to approve Change Order No. 2, which results in a total
project cost increase of $13,646.98 and authorize Payment No. 3 in the amount of
$28,708.73.
OPTIONS:
1 Return to staff for further review.
2. Adopt Resolution Number 04 -107, approving Change Order No.2 and Payment
Request No. 3 for the 21st Avenue Street and Storm Sewer Improvements Project.
3. Not adopt Resolution No 04 -107.
RECOMMENDATION:
Option No 2 - Staff recommends adoption of Resolution Number 04- 1.07.
TKDA
41) ENGINEERS • ARCHITECTS • PLANNERS
1500 Piper Jaffray Plaza
444 Cedar Street
Saint Paul, MN 55101 -2140
(651) 292-4400
(651) 292 -0083 Fax
www.tkda.com
Comm. No 12688 -01 Cert. No 3 St. Paul, MN, June 29 , 20 04
To City of Lino Lakes, Minnesota
This Certifies that Arnt Construction Company
For 21st Avenue Street and Storm Sewer Improvements
Is entitled to Twenty Eight Thousand Seven Hundred Eight Dollars and 73/100 - - -- ($
being ` 3rd estimate f.
Rec • / int ii ul ove C- f" cat e
. TKDA
P
Owner
, Contractor
28,708.73 )
ent on contract with you dated October 27 , 2003
t Construction Company
20 D V Scott A. Blink,
RECAPITULATION OF ACCOUNT
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
228,821.90
All previous payments
$
202,775.06
All previous credits
Extra No.
Change OrderNo. 1
$
5,373.75
Change OrderNo. 2
$
13,646.98
„ ,1
N O
Credit No.
$
,
AMOUNT OF THIS CERTIFICATE
$
28,708.73
Totals
$
247,842.63
$
231,483.79
$ -
Credit Balance
There will remain unpaid on contract after
payment of this Certificate
$
16,358.84
$
247,842.63
$
247,842.63
$ -
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
TKDA
Engineers- Architects - Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 3 Period Ending June 29 , 20 04 Page 1 of 1 Comm. No. 12688 -01
Contractor Arnt Construction Company Original Contract Amount $228,821.90
Project 21st Avenue Street and Storm Sewer Improvements
Location City of Lino Lakes. Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed
Approved Extra Orders Amount Completed
Total Amount Earned This Estimate
0.00
$ 243,667.15
$ 0.00
$ 0.00
$ 243,667.15
Less Approved Credits $ 0.00
Less 5 % Retained $ 12,18336
Less Previous Payments $ 202,775.06
Total Deductions
214,958.42
Amount Due This Estimate $ 28,708.73
Contractor
• ; Engineer
Date �,/�
Date June 29, 2004
ESTIMATE NO. 3 PERIOD ENDING: June 29, 2004
21ST AVENUE STREET AND STORM SEWER IMPROVEMENTS
CITY OF LINO LAKES, MINNESOTA
TKDA COMMISSION NO. 12688 -01
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
DIVISION I - STORM SEWER CONSTRUCTION
1 15" RC PIPE SEWER, CLASS 5, DESIGN 3006 LF 92.0 97.0 $ 26.00 $ 2,522.00
2 18" RC PIPE SEWER, CLASS 5, DESIGN 3006 LF 171.0 171.0 $ 28.00 $ 4,788.00
3 24" RC PIPE SEWER, CLASS 3, DESIGN 3006 LF 284.0 284.0 $ 34.00 $ 9,658.00
4 15" RC PIPE APRON WITH TRASH GUARD EA 1.0 1.0 $ 716.00 $ 716.00
5 24" RC PIPE APRON WITH TRASH GUARD EA 1.0 1.0 $ 1,370.00 $ 1,370.00
6 CONSTRUCT CATCH BASIN - TYPE 402 EA 2.0 2.0 $ 1,150.00 $ 2,300.00
7 CONSTRUCT 48" DIAMETER CATCH BASIN MANHOLE - TYPE 406 EA 2.0 2.0 $ 1,648.00 $ 3,296.00
8 CONSTRUCT 60" DIAMETER CATCH BASIN MANHOLE - TYPE 406 EA 1.0 1.0 $ 2,884.00 $ 2,884.00
9 CONSTRUCT 48" DIAMETER STORM SEWER MANHOLE -
TYPE 409 EA 1.0 1.0 $ 1,648.00 $ 1,648.00
10 RIPRAP CLASS II CY 10.0 - $ 85.00 $
11 RIPRAP CLASS III CY 20.0 10.0 $ 85.00 $ 850.00
12 EXPLORATORY DIGGING HRS 4.0 2.0 $ 256.00 $ 512.00
13 POND /DITCH EXCAVATION CY 1,010.0 1,040.0 $ 4.56 $ 4,742.40
14 ` CRUSHED ROCK 6" DEPTH (TRENCH STABILIZATION) LF 300.0 $ 5.00 $ -
15 INSULATION (4" THICK) SY 150.0 150.0 $ 23.00 $ 3,450.00
16 STORM POND NATIVE SEEDING (MN/DOT MIX 25A MODIFIED
[256]) ACRE 0.3 $ 2,200.00 $
SUBTOTAL - DIVISION I $ 38,734.40
DIVISION II - STREET CONSTRUCTION AND RESTORATION
1 MOBILIZATION
2 TRAFFIC CONTROL
3 CLEARING
LS 1.0 1.0 $ 7,500.00 $ 7,500.00
LS 1.0 0.75 $ 1,200.00 $ 900.00
TR 10.0 21.0 $ 110.00 $ 2,310.00
4 GRUBBING TR 10.0 16.0 $ 110.00 $ 1,760.00
5 REMOVE CONCRETE CURB AND GUTTER (ALL TYPES) LF 131.0 141.0 $ 2.00 $ 282.00
6 REMOVE BITUMINOUS PAVEMENT (ALL DEPTHS) SY 3,068.0 3,068.0 $ 1.25 $ 3,835.00
7 SAWCUT BITUMINOUS PAVEMENT (FULL DEPTH) LF 324.0 637.0 $ 3.00 $ 1,911.00
8 COMMON EXCAVATION (P) CY 6,510.0 6,510.0 $ 3.78 $ 24,607.80
9 SELECT GRANULAR BORROW (CV) (P) CY 3,450.0 3,450.0 $ 11.30 $ 38,985.00
10 TOPSOIL BORROW (LV) CY 350.0 336.0 $ 0.01 $ 3.36
11 AGGREGATE BASE, CLASS 5 (100% CRUSHED) TON 2,800.0 1800.0 $ 10.34 $ 21952.00
12 TYPE LV AGG. 3 WEARING COURSE (B) (LVWE35030B) TON 610.0 568.22 $ 38.00 $ 21,592.36
13 TYPE LV AGG. 3 NON - WEARING COURSE (B) (LVNW35030B) TON 605.0 605.00 $ 37.60 $ 22,748.00
14 BITUMINOUS MATERIAL FOR TACK COAT GAL 250.0 450.0 $ 1.50 $ 675.00
15 B618 CONCRETE CURB AND GUTTER LF 1,615.0 1,675.0 $ 1120 $ 11760.00
16 INSTALL SIGN TYPE C (INCLUDING POST AND ASSEMBLY) EA 1.0 $ 180.00 $ -
17 PAVEMENT MARKINGS - 4" SOLID LINE - WHITE PAINT LF 810.0 $ 0.40 $
18 TYPE III BARRICADE EA 1.0 $ 250.00 $
19 ADJUST EXISTING VALVE BOX EA 5.0 5.0 $ 225.00 $ 1,125.00
20 ADJUST EXISTING FRAME AND RING CASTING EA 2.0. 2.0 $ 500.00 $ 1,000.00
21 SILT FENCE, TYPE PRE - ASSEMBLED LF 300.0 350.0 $ 0.01 $ 3.50
22 SODDING - TYPE SALT RESISTANT SY Z500.0 2,474.0 $ 100 $ 7,422.00
23 SEEDING (INCLUDING SEED MIX 50B OR 60B, FERTILIZER,
MULCH, AND DISK ANCHORING ACRE 0.8 - $ 1,440.00 - $
24 RELOCATE MAILBOXES EA 3.0 3.0 $ 200.00 $ 600.00
25 4 " STREET DRAINTILE WITH GEOTEXTILE SOCK LF 235.0 235.0 $ 4.00 $ 940.00
SUBTOTAL - DIVISION II $ 185,912.02
SUBTOTAL ESTIMATE NO. 3
CHANGE ORDER NO. 1
REMOVE EXISTING STORM SEWER PIPE (15" CMP)
INSTALL 18" CPP PIPE
15" CPP PIPE BEND (22 DEGREES)
HIGH EARLY CONCRETE FOR CURB & GUTTER
5 SINGLE POLY SHEET FOR CONCRETE CURB & GUTTER
6 RECONSTRUCT SANITARY MANHOLE
CHANGE ORDER NO. 1
$ 224,646.42
LF 185.0 185.0 $ 12.00 $ 2,220.00
LF 27.0 27.0 $ 24.00 $ 648.00
EA 1.0 1.0 $ 150.00 $ 150.00
LF 1,675.0 1,675.0 $ 0.39 $ 653.25
LF 1,675.0 1,675.0 $ 0.30 $ 502.50
EA 1.0 1.0 $ 1,200.00 $ 1,200.00
$ 5,373.75
CHANGE ORDER NO. 2
FURNISH AND INSTALL ADDITIONAL CLASS 5 AGGREGATE ' BASE
FURNISH AND INSTALL ADDITIONAL TYPE LV AGG. 3 NON -
WEARING COURSE
FURNISH AND INSTALL ADDITIONAL 4" DRAINTILE
CHANGE ORDER NO. 2
TON 935.0 935.0 $ 10.34 $ 9,667.90
TON
LF
74.55
294.0
74.55 $
294.0 $
37.60 $ 2,803.08
4.00 $ 1,176.00
$ ' 13,646.98
TOTAL ESTIMATE NO. 3
$ 243,667.15
CHANGE ORDER
TKDA
Engineers- Architects - Planners
Saint Paul, MN June 29 20 04 Comm. No. 12688 -01 Change Order No. 2
To Arnt Construction Company
for 21st Avenue Street and Storm Sewer Improvements
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
October 27 , 20 03 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (deer-ease) (net-ehaage) the contract sum by
Thirteen Thousand Six Hundred Forty Six Dollars and 98/100 ($ 13,646.98 ).
This change order provides for changes in the work of this contract according to the attached itemization.
NET CHANGE _ $ 13,64698
Amount of Original Contract $ 228,821.90
Additions approved to date (Change Order No 1) $ 5,37335
Deductions approved to date (Nos. )
Contract amount to date $ 234,195.65
Amount of this Change Order (Add) (Deduct) (No Change) $ 13,64698
Revised Contract Amount $ 247,842.63
Approved City of Lino Lakes, Minnesota TKDA
Owner
By By
Approved Arnt Construction Company
By �a
Contractor
Scott A. Brink, P.E.
White Owner
Pink - Contractor
Blue - TKDA
CHANGE ORDER NO. 2 PERIOD ENDING: June 29, 2004
21ST AVENUE
• STREET AND STORM SEWER IMPROVEMENTS
CITY OF LINO LAKES, MINNESOTA
TKDA COMMISSION NO. 12688 -01
ITEM
NO. DESCRIPTION
UNIT AMOUNT
UNIT QUANTITY PRICE TO DATE
FURNISH AND INSTALL ADDITIONAL CLASS 5 AGGREGATE
BASE
FURNISH AND INSTALL ADDITIONAL TYPE LV AGG. 3 NON -
WEARING COURSE
FURNISH AND INSTALL ADDITIONAL 4" DRAINTILE
TON
TON
LF
935 $ 10.34 $ 9,667.90
74.55 $
294 $
37.60 $ 2,803.08
4.00 $ 1,176.00
CHANGE ORDER NO. 2 $ 13,646.98