HomeMy WebLinkAbout08/08/1988 Council Minutes1
COUNCIL WORK SESSION
AUGUST 8, 1988
Mayor Benson opened the Work Session August 8, 1988 at 6:30
P.M. Council Members present: Neal, Bisel, Bohjanen. Mr.
Reinert arrived at 6:40 P.M. Council Members absent: None.
City Administrator, Randy Schumacher; Engineer, Ron
Stahlberg; Attorney, Bill Hawkins and Clerk - Treasurer,
Marilyn Anderson were also present.
Mayor Benson explained that the purpose of the meeting was
to consider an alternative route for 2nd Avenue.
Mr. Stahlberg first updated the Council regarding a meeting
he attended with officers from St. Joseph Catholic Church
regarding their property on the south side of Elm Street and
just north of Sunrise Meadows. A task force has been formed
by the church to determine just exactly what they will do
with the land.
Mr. Stahlberg explained that when the Council ordered the
feasibility study it was expected that 2nd Avenue would
follow its current route. However soil tests have indicated
that will be a very expensive route if indeed it can be
constructed. Also there is the question of whether or not
the DNR would issue permits for the current site through the
wetlands. In the interim Mr. Menkveld, developer of Sunrise
Meadows has received final plat approval from the City and
is now awaiting utilities to be extended to the site. Mr.
Stahlberg explained that he has looked at rerouting 2nd
Avenue to the west and showed a map with a possible location
for the street. He explained that a centerline has been
established for the street and soil tests indicate that the
area -would be less expensive than the current route.
Mr. Stahlberg explained he had looked at shifting the state
aid road from 2nd Avenue to Sunrise Drive. He was unsure if
the state aid could be shifted.
Mr. Stahlberg explained that if the state aid road is
constructed in the proposed location the cost would be
approximately $732,000. If it is constructed on the current
2nd Avenue the cost would be $1,000,000 + and if it were to
be constructed up Sunrise Drive the cost would be $857,000.
Mr. Bisel said that looking at Sunrise Drive was looking the
wrong way. He felt the route should be up Lake Drive. Mr.
Stahlberg explained that would cause a problem because it
PAGE 1
151
COUNCIL WORK SESSION
AUGUST 8, 1988
would limit ways to radiate out the facilities. Mr. Bisel
felt there was more potential for commercial development if
the facilities were constructed up Lake Drive. He asked Mr.
Stahlberg why the lift station was constructed at its
present location and why the bad soil conditions on 2nd
Avenue were not detected prior to this time. He was
concerned because situations such as this result in added
costs to an improvement.
Mr. Neal said he had heard that some residents along Lake
Drive would be petitioning for utilities. Nothing has been
delivered to city hall.
Mayor Benson asked what are the feelings of the property
owners along the proposed road site? Mr. Stahlberg felt
that they would probably object. There was discussion
regarding what the affect of the new location would be on
the property owners.
Mr. Reinert asked what the primary focus is regarding
extension of utilities at this time. He asked if it was to
benefit residential development? He noted that there is no
firm commitment on commercial development at this time. He
asked if the Council should reconsider and not extend any
utility services until there are some firm commitments from
commercial developers. Mr. Stahlberg explained that there
has been two commitments and one is the prison.
Mr. Bisel asked that Mr. Stahlberg prepare cost estimates
for extending services on the new 2nd Avenue location and
for extending services up Lake Drive.
Mayor Benson asked how far up Lake Drive would services have
to be extended before they could go west? Mr. Stahlberg
explained and also noted that probably would affect the
state aid status of 2nd Avenue. He said the easiest route
is his proposal.
There was discussion regarding the people along the current
2nd Avenue who were already assessed for utility
availability. Mr. Hawkins explained that there would not be
a problem if they do receive services in a reasonable period
of time.
Mr. Bisel expressed his concern because of two problems that
have occurred recently and are proving to be costly. The
first problem concerned the waterline crossing at Rice Creek
PAGE 2
1
COUNCIL WORK SESSION AUGUST 8, 1988
and now the second problem is the apparent inability to
reconstruct the current 2nd Avenue.
Mr. Stahlberg said that he would analyze the proposed
alternate 2nd Avenue route and the possibility of extending
services up Lake Drive and determine how each would affect
the state aid process and also prepare cost estimates. He
also will determine how each route would affect the ability
to service the Sunrise area in the future. Mayor Benson
asked the staff to check and see if there may be a petition
coming from the Lake Drive area.
Mr. Bisel moved to adjourn at 7:07 F.M. Mr. Bohjanen
seconded the motion. Aye.
These minutes were considered and approved at a regular
council meeting on August 22, 1988.
-:✓ a
G. ANDERSON BENJAMIN G. BENSON
Clerk- Treasurer
PAGE 3
Mayor