HomeMy WebLinkAbout01/09/1989 Council Minutes (2)COUNCIL WORK SESSION JANUARY 9, 1989
Mayor Benson called a work sesion of the Lino Lakes City
Council to order, Monday, January 9, 1989 at 6:00 P.M.
Council. Members present: Bohjanen, Neal, Bisel, Reinert.
Council Members absent: None. City Administrator, Randy
Schumacher; City Engineer, Ron Stahlberg; TKDA
representative, Jim Voyen and Clerk - Treasurer, Marilyn
Anderson were also present. City Attorney, Bill Hawkins
arrived later in the Work Session.
Mayor Benson explained the purpose of the Work Session is
for consultant performance review.
CITY ENGINEER - RON STAHLBERG
Mayor Benson reviewed the December 27, 1988 Work Session
regarding consultant evaluations and explained that the good
and bad things regarding the City Engineer must be assessed.
Mr. Schumacher explained that he had prepared a check type
format for evaluation of the City Engineer and City
Attorney. This format was briefly addressed at the December
27th meeting and Mr. Schumacher proceeded to go through the
evaluation form and explained how he had prepared the form
for the City Engineer.
Mr. Schumacher explained that there is a long way for Mr.
Stahlberg to go in the area of public relations because of
sensitivity of the citizens. Mr. Neal noted a recent
neighborhood meeting in which he felt Mr. Stahlberg had not
answered the questions asked by some of the citizens. He
felt that since Mr. Stahlberg is so knowledgeable in
engineering matters he may have difficulty understanding
that the citizens have no background in this area. In some
instances Mr. St.ahlberg stopped in the middle of an
explanation probably assuming that the citizens knew what he
was trying to say.
Mr. Neal referred to the communication problem that arose
regarding the Rustic Lane situation. Surveyors were on
private property and the staff at city hall did not know why
they were there. Mr. Bohjanen noted that there is a policy
that the Administrator is to direct the City Engineer to let
the people and the staff know before he goes out to do field
work. Mayor Benson rephrased the policy by saying that
where there is to be on -site field work in areas where there
PAGE 1
1
1
1
1
COUNCIL WORK SESSION JANUARY 9, 1989
are homes, there is to be coordination between the
engineering firm and the staff so all know why there are
people in the field.
Mr. Bisel told Mr. Stahlberg that he feels Mr. Stahlberg has
done a lot of good for the City, good ideas, good plans,
however he also felt that the Council does not get enough
options on a particular project and referenced the 2nd
Avenue project. He also noted that the Council did not get
another option regarding the manner in which the Main Street
improvement was assessed. He also referred to the location
of the lift station on Lake Drive near Highway #49 and the
crossing of Rice Creek as other examples. Regarding the
Main Street assessment, Mayor Benson noted that everyone was
assessed equally although some areas did not get curb or
gutter. Another method of assessing this improvement could
have made the residents more satisfied. Regarding the pipe
line across Rice Creek, he said the Council should have
looked at this more thoroughly. Mr. Stahlberg explained the
testing process on that project and felt if he errored it
was on the side of trying to save money. Mr. Bisel said
that the engineering firm is hired to give the Council the
best information or options and he felt that Mr. Stahlberg
has not always given the Council all the options available.
Mr. Stahlberg noted that two and one half years ago, the
attitude of the Council was different, the Council was
reluctant to do additional soils work that could not be
billed to the developer.
Mr. Voyen told the Council that what has occurred here is
not much different than what happens in most developing
communities.. As the community gains experience they look
beyond the immediate project to detemine a broader effect.
Mr. Bisel noted that Mr. Stahlberg is looking in this
direction and noted the water management plan as an example.
Mr. Bohjanen referred to the Main Street improvement and
noted that the Council should have ordered that the entire
length of the project be improved with curb and gutter. Mr.
Reinert noted that was discussed but the matter failed in
Council - action. Mr. Bisel said that the improvement project
should have been stopped until it could be completed
properly.
Mr. Voyen said that he was speaking for the firm in saying
that TKDA is extremely interested in the Lino Lakes'
account. TKDA is desirous of providing what is needed for
Lino Lakes and will make whatever adjustments this City
PAGE 2
4or COUNCIL, WORK SESSION JANUARY 9, 1989
feels are necessary. Mayor Benson noted that there appears
to be a problem at TKDA in that there is not enough time
scheduled for Mr. Stahlberg to complete the matters the
Council and staff have requested. He noted that. Lino Lakes
will continue to grow and a great deal of time will have to
be devoted to Lino Lakes. Mr. Schumacher also noted that Mr.
Stahlberg appeared to be stretched too far. Also Mr.
Schumacher noted that this City does not want to lose the
inspector assigned to Lino Lakes.
Mr. Schumacher noted that in the area of oral presentation,
Mr. Stahlberg should keep his presentations simple and start
by laying some ground work. Mr. Stahlberg noted that the
question of costs comes up during the consideration of
improvements. He explained that it is difficult to get a
handle on costs unless more investigation or groundwork is
completed.
Mr. Schumacher suggested that he get together with Mr.
Stahlberg and staff and put together a policy for Mr.
Stahlberg to follow. The policy would include sending
letters to the affected residents prior to a survey crew
going into the field and establishing a specific time frame
for sending notifications.
Mr. Bisel explained that communications are very important.
He stressed that Mr. Stahlberg work with the staff and the
staff keep the Council informed.. He explained that if TKDA
has a vehicle in Lino Lakes, be sure that the staff is aware
of who it is and why they are there.
Mayor Benson said that a procedure would be established for
the City Engineer to follow.
CITY ATTORNEY, BILL HAWKINS
Mr. Schumacher explained that the same format was used for
the City Attorney as was used for the City Engineer. Mr.
Schumacher ran through the check form noting that there has
not been a problem regarding prosecutions which are handled
by Barry Robinson. He is firm and the police officers like
this. Mr. Schumacher noted that costs have risen
considerably in this area, however so has the activity in
the Police Department. He explained some of the changes in
the past couple of years that have had an influence on this
matter.
PAGE 3
1
1
1
COUNCIL WORK SESSION JANUARY 9, 1989
Mr. Schumacher suggested that Mr. Hawkins present some legal
issues at regular Council meetings and asked that he keep
the Council up to date regarding legislative action and
present other periodic reports on current appropriate
matters. Mr. Hawkins explained that there has not been a
lot of legal civil issues affecting this City but noted he
could update if the Council so wishes. He noted that most
of the legislative action is covered in the League Magazine.
He also noted that the problems facing Lino Lakes are very
similar to the problems facing other cities of similar size
and location. There is nothing unique.
Mayor Benson referred to the issue regarding the Centennial
Fire District and suggested that Mr. Hawkins could have been
helpful by guiding the Council as to what can be done. Mr.
Hawkins explained that the Fire District is a unique
situation and until the budget problem occurred, he did not
know that there was a problem. He noted that the Joint
Powers Agreement was a working document and was intended to
be updated from time to time. Mr. Bohjanen said he expected
that Mr. Hawkins would keep the Council abreast of legal
actions affecting the City and its citizens. He referred to
the Roland Ford matter.
Mr. Bohjanen moved to adjourn at 6:58 P.M. Mr. Neal
seconded the motion. Aye.
PAGE 4
These minutes were considered and approved at a regular
council meeting on January 23rd 1989.
ARIL G. ANDERSON BE J.A IN G.—BEN ON
Clrk- Treasurer