Mayor Benson called the Work Session of the Lino Lakes City
Council to order, Monday, February 27, 1989 at 6:00 P.M.
Council Members present: Neal, Bohjanen, Reinert, Bisel.
Council Members absent: None. City Engineer, Ron Stahlberg;
Planner, John Miller and Clerk- Treasurer Marilyn Anderson
were also present.
DISCUSSION OF FIRE STEERING COMMITTEE MEETING OF TUESDAY,
FEBRUARY 21, 1989
Mr. Reinert gave a brief report of the meeting held on
February 21, 1989 with the Circle Pines and Centerville
representatives of the Steering Committee. He noted that
there is more opposition from Centerville than Circle Pines
to the suggestion that the funding formula be changed. He
also explained that the three Administrators from the three
communities met on Friday and there was no further progress.
He asked if the Steering Committee cannot get past the
funding issue, where would this Council like their
representatives to go. A Steering Committee meeting has been
set for Monday, March 6, 1989 here.
Mr. Neal told the Council that he had received a telephone
call from Mr. Bruen, Fire District Chairman who explained
that if rescue calls were the problem, they could be stopped
in Lino Lakes. Mr. Reinert said this was not the issue. He
said that there should be an agreement that the Fire
Department has a certain dollar value for each community
whether it is part of the district or a city owned
department. Then the percentage factor would be added.
Neither Circle Pines or Centerville has offered any
alternatives.
Mayor Benson asked if the negotiators should bend on this
issue. He noted that they have offered to separate
residential considerations from the commercial. Mayor Benson
has also asked that Mr. Schumacher prepare some five and ten
year cost projections for what a Lino Lakes Fire Department
would cost. This calculation should take into consideration
the expected population increase in Lino Lakes. This would
be useful in explaining to the other two cities that Lino
Lakes could be financially better off by starting their own
fire department at this time. Mr. Bisel explained that this
was his concern from the beginning.
Mayor Benson explained that if Circle Pines and Centerville
budge on the financial issue, they would ask for a long term
agreement from Lino Lakes. Mr. Reinert noted that it usually
takes several meetings to come to a "meeting of thought ". He
said he is looking forward to a more open acceptance at the
next meeting.
-Mr. Bisel asked Mr. Reinert and Mayor Benson to find out what
'
the-other two Cities are thinking and not budge at this point
COUNCIL WORK SESSION
FEBRUARY 27, 1989
FEBRUARY 27, 1989
and update the Council at the March 13, 1989 meeting. He
also asked for a presentation from Centerville and Circle
Pines. He noted that they may have a better alternative.
Mr. Neal said he would support Mayor Benson and Mr. Reinert
in whatever they decided was best.
PLAN REVIEW OF SUNRISE MEADOWS
Mr. Stahlberg showed overhead maps of this subdivision that
showed final locations of the water and sewer mains. He
noted that three property owners adjoining Sunrise Meadows on
the west have petitioned for utilities so that they can
subdivide their property. He suggested that the water main
be looped from the trunk line west on Gladstone, north on
Sunrise Drive to Green Briar Drive then east to the trunk
lines. Sunrise Drive would be restored to its current
status. He noted that the residents on the west side of
Sunrise Drive could be notified that the services were
available and they could petition for the services if they
desired. This would be similar to the situation on Laurene
Avenue and-the Woodridge Estates development. There was
discussion regarding going all the way up Sunrise Drive and
then looping to connect with the main trunk lines. Mr.
Reinert was concerned that this would cause delay of the
entire project since residents in the Sunrise area have been
so opposed to any sewer and water improvements. Mr. Miller
explained that he is going to suggest to the Council later
that the entire MUSA boundary be re- assessed. The one area
he is considering eliminating from the MUSA boundary is the
Lexington Park Lakeview area. If they are removed from the
MUSA area, utilities will not be available to them.
Mr. Reinert said that he felt the primary goal is to get the
trunk lines north to the prison. He suggested that any
change of this type could substantially delay the project
past the construction season. The lot subdivisions must go
through the P & Z Board and the matter of supplying services
can be dealt with at that time. The plans for Sunrise are to
remain as submitted and any revisions are to be made after
the formal procedures are followed for replatting and
petitions received for utility extension.
Mr. Stahlberg explained the drainage pattern for Sunrise
Meadows. He noted that Mr. Volk had recommended that the
drainage of Gladstone Drive be tied into the storm sewer
because of the pattern of water flow. This has been
incorporated into the drainage plan. Mr. Stahlberg explained
that he and Mr. Volk have spent a lot of time talking to the
residents on the south end of Ulmer's Rice Lake Addition
regarding drainage and feels it was time well spent.
Mr. Stahlberg noted that the portion of 2nd Avenue abutting
-Sunrise Meadow on the east will be constructed to state aid
standards utilizing MSA funds. Mr. Bisel asked if there was
2 2 9
COUNCIL WORK SESSION FEBRUARY 27, 1989
FEBRUARY 27, 1989
any chance that Sunrise Drive could be constructed to state
aid standards. Mr. Stahlberg explained that the problem is
that there is a county state aid road two blocks to the west.
He has reviewed this with the state aid engineer.
Mr. Stahlberg explained that Mr. Menkveld has already started
grading the area and moving dirt to the low areas for fill.
There will be a substantial change in the area.
PLAN REVIEW OF WEST CENTRAL TRUNK SEWER AND WATER
Mr. Stahlberg outlined the route of the trunk lines beginning
at the Lino Industrial Park west through the property owned
by Tilsen and south to the freeway. He displayed a proposed
plat by Tilsen for the area south of the prison and north of
35 W and the area south of Marvy Street and north of 35 W.
He noted that in the area zoned Light Industrial, Tilsen is
proposing a buffer of single family homes. This would
require a rezone of a portion of this Light Industrial
property.
Mr. Stahlberg continued by explaining where the trunk lines
would go under 35 W south through St. Joseph Church property.
He also displayed a preliminary plat of the Tilsen property
west of the church. The trunk lines will then continue south
of Elm Street through another parcel owned by the church to
the Menkveld subdivision of Sunrise Meadows. Mr. Stahlberg
explained that a ghost plat of the church property was
designed so that the trunk lines could be properly placed.
The trunk lines will continue south through Sunrise Meadow
into the Strauss property and the Begenisich property.
Easements will be needed through all of these properties and
the easement through the Strauss and Begenisich property will
be used for street purposes in the future as well as the
utility lines at this time. He also noted that a lot of
trees will be removed during construction.
Mr. Neal asked if there will be a gravel road over the
utility easement on the back side of the Rustic Lane lots.
Mr. Stahlberg explained that was the original plan but Mr.
Volk has requested that the hard surface be removed and the
area restored to its natural condition. He explained that
Mr. Volk was with him and the survey crew and talked to the
residents. Mr. Reinert asked if it was possible to put in a
good base but also have grass. Mr. Stahlberg said yes,
however he will replace what is there as Mr. Volk has
requested.
HISTORICAL SOCIETY E. A. W. COMMENTS
Mr. Stahlberg explained a letter from the Historical Society
-dated February 17, 1989 is requesting an archaeological
survey of the area south of Sunrise Park to Lake Drive. He
COUNCIL WORK SESSION
FEBRUARY 27, 1989
FEBRUARY 27, 1989
has received a proposal from Cristina Harrison who has
completed several surveys in Lino Lakes. He noted that the
survey would take about three working days and another one or
two days to complete a final report. She would probably
start the survey about the first of April. He also noted
that a survey would'`probably be required for any improvement
within 1,000 feet of the chain of lakes. This requirement is
for Lino Lakes because of the historic significance of the
lakes.
MINNESOTA POLLUTION CONTROL AGENCY REQUEST FOR PREPARATION OF
EAW
The Minnesota Pollution Control Agency (PCA) has requested
that Lino Lakes withdraw the EAW from the review process and
submit the necessary materials to them so that they can start
the EAW review process. PCA explained that the EAW process
is their responsibility not Lino Lakes. Mr. Stahlberg will
submit all of the material to this agency and also try to
talk them out of requiring that Lino Lakes withdraw their
EAW. Mr. -Bisel asked why this route was not followed in the
beginning and Mr. Stahlberg explained that he thought that
the City was responsible for this as was the situation in
Andover about two years ago. However, PCA says it is their
responsibility . Mr. Stahlberg did not feel PCA would be
difficult to deal with.
Mr. Stahlberg has submitted a schedule for the West Central
Trunk improvement. If plans and specifications are approved
this evening, the archaeological study can begin about April
1, 1989. The PCA will publish the EAW on March 20, 1989,
bids can be taken on March 31, 1989 and awarded on April 10,
1989. The bond consultant will look at the bids prior to the
awarding of the bid. Bids cannot be awarded prior to formal
action by MPCA on the EAW.
Mr. Bisel asked if anything was missed regarding the PCA
responsibility and what will it cost the project in time?
Mr. Stahlberg said a procedural step was missed. It should
set the project back about two to four weeks. Mr. Bisel
noted that time is critical at this point.
The remaining items on this agenda were delayed to the
regular Council meeting.
Mayor Benson closed the Work Session at 7:18 P.M.