HomeMy WebLinkAbout2003-035 Council ResolutionCITY OF LINO LAKES
RESOLUTION NO. 03-35
RESOLUTION AUTHORIZING THE PREPARATION OF PLANS AND SPECIFICATIONS FOR
THE 2003 WEARING COURSE.
WHEREAS, the City Engineer has prepared plans and specifications for 2003 Wearing Course
and has presented such plans and specifications to the council for approval;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO
LAKES, MINNESOTA:
1. The City Engineer is des gnated as the engineer for this improvement and he is directed to
prepare plans and specifications for the 2003 Wearing Course.
Adopted by the Lino Lakes City Council this 10th day of March, 2003.
Ann J. BI�i� City Clerk
John . Ber 9 e on, Mayor
AGENDA ITEM 7E.
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: March 10, 2003
TOPIC: Resolution No. 03 - 35, Authorizing Preparation of Plans and
Specifications for 2003 Wearing Course
Vote Required: Simple Majority
BACKGROUND:
The City undertakes a paving project each year to place the final layer of
bituminous, known as the wearing course, in those developments where the
majority of the lots have been built on. The funding for this work is provided by
assessments to the respective subdivisions. The subdivisions receiving wearing
course this year include Clearwater Creek 3rd Addition, Clearwater Creek 4th
Addition, and Bluebill Ponds.
The schedule for this project is as follows:
City Council Authorizes Plans and Specifications
City Council Approves Plans and Specifications
City Council Authorizes Ad for Bids
Open Bids
City Council Awards Contract
Construction Begins
March 10, 2003
April 14, 2003
April 14, 2003
May 15, 2003
May 27, 2003
June, 2003
OPTIONS:
1. Return to staff for further review.
2. Adopt Resolution Number 03 - 35, authorizing the preparation of plans and
specifications for the 2003 Wearing Course Project.
3. Not adopt Resolution Number 03 — 35.
RECOMMENDATION:
Option No. 2 - Staff recommends that Resolution Number 03 - 35 be adopted.