July 25, 1973
Mr. Marier said there must be a decision as to whether there is an over -lap
in December of 1974. These bonds are due and payable on Nov. 4, 1974 and
before that date we must either pay or issue bonds for resale to cover the
balance.
Mr. Zelinka asked if the interceptor would ease the situation. Mr. Busch
said it would. At the present time, Twin City Federal is not interested
in areas that are not serviced by sewer. The main hold up is how much or
how little the County is going to take in the Open Space Program.
Mr. Zelinka felt that once this decision is made and the boundary lines on
the Open Space is set, then things should be speeded up as to construction
in that area.
There was discussion of the sewer situation being cleared, but Mr. Busch said
that as far as he knew, there had been no action by the Metro Sewer Board
on the installation of the interceptor. Mr. Busch seemed to feel that the
biggest problem to selling the area is the uncertai n i ty of the Open Space
program.
There was more discussion on the retirement of the bonds. Mr. Zelinka said
we should aim at paying off with funds available as much as possible of
present bonds, and prior to 11 -4 -74, work with Mr. Springsted to sell new
bonds to pay the balance.
Mr. Locher said there would be a balance of about $250,000.00 and this was
exactly what had been planned in the original sale. It takes about 6 weeks
to 2 months to float the bonds.
Mr. Marier was concerned that we should realize that we have this bill to
pay and, if the project becomes deficit, the V i I l age is st i I I I i ab l e for
payment of these bonds. There is a potential of $300,000.00 being available
this should be paid on the original and the remainder resold. The Council
should make a move before the due date to avoid overlapping these bonds.
There was some question as to the effect the reissue of bonds would have on
the bonding powers of the Vi I lage. Are these kinds of bonds governed by the
bonding limits as other bonds are? Mr. Locher is to check this out.
Mr. Jaworski moved that no later than August 1, 1974, we start the process
to sell bonds to pay off the $550,000.00, with the stipulation that the
Village not exceed bonding indebtness. Seconded by Mr. Zelinka.
Mr. Marier amended the motion to read "pay off difference between cash on
hand and amount of bonds ". Motion carried.
Mr. Marier moved to adjourn at 10:20 P.M. Seconded by Mr. Jaworski. Aye
The minutes were approved at the meeting of Aug. 13, 1973. L _.
July 31, 1973
Clerk- Treasurer
The special meeting of the Lino Lakes Vi I l age Council was called to order at
8:15 P.M. on July 31, 1973 by Mayor Bohjanen. Counci Imen present; Jaworski,
Zelinka. Absent; Cardinal, Marier. Mr. Carley and Mr. Gotwald were also present.
9
180
July 31, 1973
Mr. Bohjanen stated that this special meeting had been called for the purpose
of discussing the extension of mains and laterals within the Vi Ilage after
the interceptor has been constructed. Mr. Bohjanen also reported that from all
indications the Metro Sewer Board would go the route recommended by Mr. Carley
and Mr. Gotwlad for a full gravity system and along the route they had suggested.
Mr. Carley said that Mr. Bohjanen had made the position of the Village quite
clear at the NSSSB meeting in Fridley. He felt that we must have this inter-
ceptor and that the comprehensive plan submitted by the Village Engineers was
the one that would serve best for this area.
Mr. Carley explained that in order to get this project off the ground,
the Village must order a feasibility study for the area to be added to
the system and then hold public hearings in order for the people to be
heard. At the present time Shenandoah is set to go, Country Lake wi 11
hook in and the area to be considered as recommended by the Engineers,
is from the Westerly edge of the Village along County Road "J" to Highway
#49, then North on Highway #49 to Birch Street, then along the Southeast
edge of Baldwin Lake to the Westerly edge of the Village. Mr. Carley also
felt that the PCA would order the Baldwin Lake Trai ler Court to hook into
the interceptor.
There was discussion on the possibi 11ty of parts of this area being deleted
as being unfeasible to service at the present time. Mr. Carley said parts
can be eliminated at a public hearing, but you cannot add to the area.
Mr. Carley said the first step is to order the feasibi lity study, check
it, accept the report and set a date for public hearings. Mr. Carley
had hoped that the Council would order the report at this meeting. It
will take a couple of weeks to get the report ready.
The Council questioned the cost of such a study.
Mr. Carley said the cost of the study works out to about 1.1% of the total
cost of the project. This amount is payable as the project progresses and
ultimately becomes part of the total Engineering fee. This fee is part of
the overall cost and is figured into the total assessments. Mr. Carley
said that Centervi I le had ordered their study and hope to set hearings
for the first week in September. He would l i ke to present this as a joint
effort between Centervi Ile and Lino Lakes. Mr. Carley felt this would
make a greater impact on the Metro Sewer Board.
Mr. Bohjanen said that this was the impression that he had gotten -that
the Metro Sewer Board is looking for a joint effort on the part of the two
Villages.
Mr. Carley felt the best way to handle something like this was to have a
joint Council meeting -For the purpose of duscussing this project and then
each Council to pass a joint resolution for presentation to the Metro Sewer
Board. This would be done after the hearings.
Mr. Jaworski asked about servicing the area around Acton and the inter-
section of the Freeway and County Road 14. Mr. Carley explained the plans
of Centervi I le for construction in that direction and felt there could be
some definite action in that area by Spring.
There was discussion on the area indicated by the Engineers as to be the
1
1
1
July 31, 1973
first area served. Mr. Carley asked if the Counci I felt there was too much
or too little. The general feeling of the Council was too much had not
been included since the area can be cut back according to the wishes of
the people at the p u b l i c hearings.
Mr. Carley said i f you order a public hearing for this enti re area, then
the people can make their- wishes known at the hearing if sewer isn't
wanted in certain areas by the people, then that area can be deleted. But,
if you do not order a hearing for a certain area, and these people want
to be included, then it must be done by petition or possibly anot er,
hearing. Mr. Carley felt that the wise thing to do would be to tie
study/and hearing for the entire area and delete from it as the people
i n d i cate.
There was more discussion as to the area covered by this study. What could
be deleted or what areas it might not be feaible to service at this time.
There was also discussion on the points of hookup to the interceptor and
which areas would flow into which lines.
Mr. Zelinka moved to authorize Carley Engineering to make a feasibi l ity
study for the ViIlage on the area bounded by Baldwin Lake Road To County
Road 'J' East on County Road 'J' to highway #49, North on Highway #49
to Birch Street, then along the Southeasterly edge of Baldwin Lake to the
Westerly edge of the Vi I lage. Seconded by Mr. Jaworski. Motion carried.
Mr. Jaworski moved to adjourn at 9:00 P.M. Seconded by Mr. Zelinka. Aye
Minutes approved at the meeting of Aug. 13, 1973.
Clerk-Treasurer
August 13, 1973
The regular meeting of the Lino Lakes Village Council was cal led to order
at 8:05 P.M. by Mayor Bohjanen. Councilmen present; Cardinal, Jaworski.
Absent; Marier, Zelinka. Mr. Locher and Mr. Gotwald were present.
The minutes of the July 23, 1973 meeting were corrected as follows: Page
5, first line, change "Jaworksi" to "Cardinal ". Mr. Cardinal moved to
approve the minutes as corrected. Seconded by Mr. Jaworski. Motion carr-
ied.
There was not a quorum for the approval of the minutes of the special
meetings. These minutes were held until such time as Counci 'men
necessary for approval are present.
A gentleman representing the Forest Lake Masonic Lodge appeared before
the Council seeking a 3.2 beer permit for August 26, 1973 in connection
with a horse show that w i l l held at Rehbe i n's Arena. The Counci I re-
minded him the Vi I I age must have a copy of their I i ab i I i ty insurance.
The gentleman said there will be a copy mai led to the office.
Mr. Card i an I moved to approve the 3.2 Beer permit contingent on proper
insurance papers. Seconded by Mr. Jaworski. Motion carried.
Mr. Zelinka arrived at 8:20 P.M.