COUNCIL WORK SESSION OCTOBER 22, 1994
MINUTES
LINO LAKES CITY COUNCIL
DATE: OCTOBER 22, 1994
TIME STARTED: 9:06 A.M.
TIME ENDED: 12:40 P.M.
MEMBERS PRESENT: Reinert, Neal, Kuether, Elliott, Bergeson
MEMBERS ABSENT: None
OTHERS PRESENT: R. Schumacher, Al Ross
1. Capital Facility Study, John Bergeson
Mr. Bergeson presented the October 1994 City of Lino Lakes Facilities Study Update
for the Council's consideration. He explained that the Winsor/Faricy study conducted
in 1989 was updated, with additional potential sites identified for city facilities. Mr.
Bergeson said it was apparent the city needs more space, and sites are becoming
scarce.
Mr. Bergeson outlined the important points in the update:
1. Winsor/Faricy projected the population to reach 14,000 by 2004. The
city has already reached 13,000. The city's growth was double the
projection.
2. The Winsor/Faricy study compared the average amount of staff of
municipalities the size of Lino Lakes with the amount of space per
employee and projected the city currently needs 74,742 square feet, and
will need 81,950 square feet by 2004. The city currently has 19,771
existing square feet. Assistant City Administrator Dan Tesch coordinated
the update of the Winsor/Faricy study and based his assumptions on a
fully developed city with a population of 25,000 by the year 2009. With
those assumptions the city will conservatively need 61,681 square feet
of facility space by 1999, and 68,295 square feet by 2009.
3. The Winsor/Faricy study recommended three sites: a) the existing Main
Street site; b) the Lino Industrial site; and c) Birch Street and Highway
49. The updated study includes: a) Lake Drive south of I -35W; b) Birch
Street and Centerville Road; c) I -35E corridor; d) Ash Street Sports
Complex; and e) Lake Drive north of 1-35W.
'2141
COUNCIL WORK SESSION OCTOBER 22, 1994
4. The total cost of 68,000 square feet of facilities, without land or
furnishings, is estimated to be $5 million, based on an assumed cost of
$100/square foot for office and public space, and $50/square foot for
garages and storage. Mr. Reinert said he considered $100/square foot
low, because of state mandated requirements.
Mr. Bergeson introduced the results of a staff mini -survey which indicated a strong
preference to see city hall combined with other facilities. The opinions differ on what
those other facilities should be. Lake Drive/south of I -35W and Birch Street/Hwy. 49
tied for first place for location preference. A combined city hall, police and public
works was first choice of respondents. Ms. Kuether noted that maintenance would
be cheaper if all city departments were under one roof.
Mr. Bergeson informed the Council that the Centennial School Superintendent has
proposed that the school district offices be located in the new city hall. The school
district needs approximately 10,000 square feet of space for about 10 years. As
school enrollment decreases, the district would return to space within a school
building, and the city could take over the vacated space. Mr. Bergeson said this was
worth exploring if a mutually beneficial agreement could be reached.
Mr. Bergeson added that Mary LaForest, economic development assistant, is working
on a study on the concept of creating a downtown as part of coursework for a class
she is taking. The results of the study can be useful in evaluating the town center
concept for municipal facilities.
During discussion of the facilities study Mr. Reinert said combining city facilities into
a campus -like setting could be an anchor for other facilities, such as a community
center. He added he hoped the city would build high quality facilities, because it
would be here for many years, and would be an element of community pride. He said
his first preference is a campus setting on Birch Street, with public works located at
another site. Mr. Schumacher said it was critical to focus on land, which would
amount to approximately 6 percent of the project cost. Ms. Elliott stated her
preference was Birch Street and Centerville Road because of potential growth of the
area. Ms. Kuether said she felt a Birch Street/Hwy. 49 location would take good land
off the tax rolls. She said she preferred something centrally located, anywhere north
of Lilac Street that was not residential or commercial. Mr. Schumacher said a city
facility near the correctional facility would project a different image than a facility
located elsewhere. Other possible sites discussed were the Cardinal Farm, Lake Drive,
behind Fina Mart, with an entrance road from Lake Drive, and behind Rehbein's on
77th Street near Schwans. Mr. Reinert suggested city hall might attract commercial
businesses. Ms. Kuether said the Council needed input from Brian Wessel. Members
agreed to focus on sites, cost for purchase of a site, and how the city would pay for
it.
1
1
1
1
COUNCIL WORK SESSION OCTOBER 22, 1994
Mr. Bergeson noted this study is just a start in the capital improvement plan. He
estimated it would cost another $1 million for land and furnishings. Mr. Reinert
estimated 40 acres of land would cost $300,000.
Mr. Schumacher pointed out that space has become a serious issue at city hall. He
said there is a variety of funding sources for a new facility, and he will identify sites
and examine the financial options, based on the premise the city would build in 3-5
years. Council members agreed they were not willing to use eminent domain to obtain
a site; they had enough options without resorting to that.
A meeting was set for Nov. 12 at 9 a.m. to further address the site issue.
2. Administration/Staff Communication, Bergeson, Kuether
Mr. Reinert explained that Ms. Kuether and Mr. Bergeson had met with Darrell
Schneider and Don Volk before they left the city, and they indicated there was a lack
of communication with the city administrator. Mr. Reinert said he believed the
relationship of the Mayor, City Council and staff is misunderstood. According to the
city charter, the mayor's position is ceremonial and defines no administrative
responsibility. The City Council is responsible for administration of the city, and for
the job description of the city administrator, who is the chief administrative officer of
the organization. Mr. Reinert said it was his opinion that Mr. Schneider's decision to
leave was based on an opportunity to move where he had built a home and had
family, although he also had concerns about personal liability. He told Mr. Reinert the
city engineer position was a good one for the city. Mr. Reinert said he felt Mr. Volk
was unhappy, and perhaps the Council was at fault for not tracking the problems
more closely after the reorganization of positions.
Mr. Bergeson said he and Ms. Kuether talked to several staff members, and from
those discussions they had concerns about morale. It is their understanding that key
people are looking for new positions. The city lost two of its best staff members, and
should find ways to avoid losing more. Mr. Bergeson said the City Council has no way
to evaluate the city administrator, and a system needs to be put in place. He added
that since the Council has little day-to-day knowledge of staff activity, the evaluation
could include both Council and staff feedback. A professional may be needed to
establish an evaluation process.
Ms. Kuether added that she felt the low morale was evident in all departments. Mr.
Bergeson said Mr. Schumacher needs to make an effort to turn morale around. He
suggested regular meetings with key people. Mr. Reinert said the council needs to deal
with these problems together, and that Mr. Kuether and Mr. Bergeson should share
with the other Council members who they talked to and what they learned. The
charter is specific about how the Council administers and members have an obligation
2I •
:
(
COUNCIL WORK SESSION OCTOBER 22, 1994to
share the information. Ms. Kuether said Mr. Schneider had indicated that he hadn't
wanted to leave the city when he did. Mr. Volk was unhappy about department
reorganization, and felt his longevity should have counted more than it did.
Mr. Bergeson said that in summary he identified the morale issue as a lack of
communication, feedback, respect and appreciation. Ms. Elliott said Mr. Schumacher
has detailed his process for feedback and evaluations, and she thinks the problem
stems from the union issue. Setting up the union has reached a stalemate and
everybody is looking for someone to blame. Progress in negotiations will help the
morale issue. Ms. Kuether said from the people she talked to, she believes the morale
problem went beyond the supervisors. Mr. Bergeson added that if other people are
looking for new jobs, it would be irresponsible for the Council to ignore it.
Mr. Reinert said he believes departments heads sometimes have difficulty assessing
what decisions should be made on their own. When a job gets more complex than
what they are used to, Mr. Schumacher needs to communicate better with them. Mr.
Neal added that most of the people he talks to are happy. Mr. Reinert said the Council
must honor the system. If there is a problem, staff should go to the department head,
and the department head should solve the problem if possible. The department head
should come to the Council. Mr. Neal suggested employees be given a questionnaire
to fill out when they leave.
Mr. Schumacher said he agreed there are morale problems, and any system can
always use improving. Lino Lakes was experiencing growth, transitions and systems
changes, and was becoming more of a business that required more accountability.
These changes are hard on employees. Mr. Schumacher said the union issues are
causing infighting among employees. When the union was certified he hired a
professional negotiator to maintain his working relationship with employees. He said
he stands by his evaluation of the reorganization that was approved by the Council,
and it's time to look to the positive things going on in the city. He added that he
already meets monthly with department heads.
Mr. Neal said Lino Lakes is behind other cities in wages. Mr. Bergeson said the union
issue was going to make it difficult to hire new employees because they won't know
what their salary will be. Mr. Schumacher said that employees have told him
something must be done. They are now set for arbitration.
Mr. Bergeson explained how Bethel College hired a company that performed an
evaluation among employees that kept local personalities out of the process, and this
might work for the city administrator evaluation. Mr. Reinert directed Mr. Schumacher
COUNCIL WORK SESSION OCTOBER 22, 1994
1
1
1
1
to bring his job description to the next work session. Mr. Schumacher said he would
look at the issues and bring back some options to address.
These minutes were considered, corrected and approved at a regular Council meeting
held on Monday, December 12, 1994.
Mary La rest, Vernon F. Reinert,
Economic Development Assistant Mayor