HomeMy WebLinkAbout2014-052 Council ResolutionCITY OF LINO LAKES
L. RESOLUTION NO. 14-52
RESOLUTION AUTHORIZING THE PREPARATION OF PLANS AND
SPECIFICATIONS FOR WELL NO. 6 PUMPING FACILITY.
WHEREAS, in accordance with the Water System Comprehensive Plan, construction of
Well House No. 6 is planned to meet City demands; and
WHEREAS, the proposed project is necessary, cost-effective, and feasible; and
WHEREAS, the City's Engineer, WSB & Associates, Inc., shall perform such services;
and
WHEREAS, the City proposes to use Trunk Area & Unit funds for all of the cost of the
improvements,
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
1. WSB & Associates, Inc. is designated as the engineer for this project and is directed
to prepare plans and specifications for the Well No. 6 Pumping Facility for a cost not
to exceed $155,250.
L.
Adopted by the Lino Lakes City Council this 9th day of June, 2014.
The motion for the adoption of the foregoing resolution was introduced by Council
Member
Roeser and was duly seconded by Council Member Raf fertand upon vote
being taken thereon,fthe following voted in favor thereof:
TheiollovGingvoteea agaihst same:
none (Absent - Stoesz, Kusterman
ATTEST:
L.,
uh. e Bartell, City C -rk
A.
J rff Reinert, Mayor
AGENDA ITEM 5B
STAFF ORIGINATOR: Rick DeGardner, Public Services Director
MEETING DATE: June 9, 2014
TOPIC: Resolution No. 14-52, Authorizing Preparation of Plans
and Specifications for Well No. 6 Pumping Facility.
VOTE REQUIRED:
3/5
BACKGROUND:
In accordance with the Water System Comprehensive Plan, construction of Well House
No. 6 is planned to meet City demands. The location of this pumping facility will be
adjacent to Birch Park on property that was acquired within "The Preserve" development.
Staff recommends utilizing WSB & Associates, Inc. to prepare the Plans and
Specifications for the Well No. 6 Pumping Facility. The scope of services includes:
• Prepare Preliminary and Final Design of Well House
• Develop Contract Documents for Bidding
• Distribute, Review, Tabulate, and Recommend Award of Construction Contract
• Construction Administration and Inspection
Please refer to the attached letter dated June 2, 2014 for more detailed information on
what services this contract will include. It is staffs recommendation to authorize the
preparation of Plans and Specifications for the Well No. 6 Pumping Facility for a Not -To -
Exceed amount of $155,250. The City proposes to use Trunk Area & Unit funds for all
costs of this improvement project.
The projected timeline:
Well House Design October - December 2014
MDH Review, Bidding December 2014 - January 2015
Award Contract February 2015
Well House Construction Completed Summer 2015
OPTIONS:
1. Adopt Resolution No. 14-52, Authorizing the Preparation of Plans and Specifications
for Well No. 6 Pumping Facility.
2. Return to staff for further review.
RECOMMENDATION:
Option No. 1 - Staff recommends that Resolution No. 14-52 be adopted.
ATTACHMENTS:
WSB & Associates, Inc. letter dated June 2, 2014
WSB
A:osrr
engineering• planning• environmental. construction
June 2, 2014
Rick DeGardner
City of Lino Lakes
600 Town Center Parkway
Lino Lakes, MN 55014
Re: Proposal to Provide Professional Engineering Services for the
Design and Construction Management of Well No. 6 Pumping Facility
Dear Mr. DeGardner:
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763-541-4800
Fax: 763-541-1700
WSB is pleased to submit this proposal to provide professional engineering services related to
the design and construction of a municipal well pumping facility. Our proposal will be presented
in the following six sections:
• Project Approach/Scope of Services
• City's Tasks
• Proposal Assumptions
• WSB Sub -consultants
• Fee
• Schedule
A delineation of tasks to be performed by WSB & Associates, Inc. and by the City follows
directly. Assumptions related to these same items are also defined in a subsequent section.
PROJECT APPROACH/SCOPE OF SERVICES
WSB's project approach/scope of services is based on our understanding of the project and our
experience on similar projects. The following are the major tasks that will be performed in
completing the project.
St. Cloud • Minneapolis • St. Paul
Equal Opportunity Employer
wsbeng.com
M:IWaterWastewatertlino Lakes1WeR 61LTR PROP-LL-060214-WeR6 '
Mr. Rick DeGardner
June 2, 2014
Page 2
Design and construction of Well House 6
Task 1 — Well House Preliminary Design
• Provide site surveying and base map preparation.
• Discuss site constraints with Minnesota Department of Health personnel.
• Prepare a preliminary site and building layout and discuss with City personnel.
Task 2 — Well House Final Design
• Prepare final construction drawings and specifications based upon preliminary design
discussions with the City.
• Review final construction drawings and specifications with City personnel.
• Provide an opinion of probable construction cost to reflect specified equipment, structural
components, and any modifications made during final design.
• Review opinion of probable construction cost with City personnel.
• Submit two (2) copies of the final construction drawings and specifications to the
Minnesota Department of Health (MDH) for review. Respond to questions and
comments from the MDH and receive approval for the drawings and specifications.
• Prepare and provide technical criteria, written descriptions, design data, final opinion of
probable construction cost, and forms for the City's use in filing applications for
governmental design approvals.
• Assist City in consultations with governmental agencies, if needed.
Task 3 — Well House Bidding
• Print construction drawings and specifications (Bidding Documents).
• Distribute Bidding Documents to prospective bidders.
• Maintain bidders list.
• Respond to bidder questions.
• Issue addenda to Bidding Documents, if required.
• Attend bid opening and prepare bid tabulation sheets.
• Evaluate bids.
• Assess proposed substitute materials and equipment.
• Recommend award of construction contract.
Task 4 — Well House Construction
• Organize, coordinate, lead, and attend preconstruction conference and regular progress
meetings during construction. Provide and distribute meeting minutes.
• Establish reference points for construction staking of the project by Contractor (one
time).
• Review Contractor submittals (shop drawings) for products and equipment.
• Issue contract document clarifications as required.
• Process contract change order requests.
/, 0IW'aterWastewaterlLino LakeslWell 61LTR PROP-LL-0602/4-Well6.Aac
Mr. Rick DeGardner
June 2, 2014
Page 3
• Review contractor -submitted construction progress schedules.
• Process contractor pay requests.
• Provide substantial completion punch list for contractor and issue certificate of
substantial completion when appropriate for the well house construction.
• Assist the City with start-up of the well house.
• Review final submittal from Contractor with respect to conformance with the contract
documents.
• Process final pay request and project close-outs.
Task 5 — Well House Post Construction
• Provide record drawings.
• Provide an operation and maintenance manual for the facility.
• Visit the project to observe any apparent defects in the completed work and assist the
City in working with the Contractor to correct defects.
THE CITY'S TASKS
In order to complete our tasks, we will need The City to provide the following:
• Provide a designated project contact person.
• Provide answers to specific project questions, provide requested information, and make
decisions regarding project direction during the course of the project.
• Choose a well house configuration and site plan early in the project.
• Pay permitting and review fees that may be necessary.
• Pay for necessary testing services as defined in the contract documents.
• Pay additional testing costs that may be necessary.
• Attend construction progress meetings when requested.
PROPOSAL ASSUMPTIONS
WSB tasks and estimated fees are based on the following assumptions:
• This proposal assumes design of the well house will be similar to the recently toured
Hugo Well House No. 6.
• This proposal includes a generator receptacle to connect a portable generator and
conduits to be stubbed out from the well house for a potential future standby generator. It
does not include the design of a portable generator.
• This proposal includes design of radiant in floor heat for the well house.
• This proposal does not include preparation of a wellhead protection plan or update.
• This proposal does not include amending the City's water appropriation permit.
• An operation and maintenance manual, beyond the information contained in contractor -
supplied shop drawings, is not included in the project.
.il: 6V'aterWastewaler Lino LakeslWell 6ILTR PROP-LL-060114-Wel16.doc
Mr. Rick DeGardner
June 2, 2014
Page 4
• The architectural finishes of the well house are to be determined during the preliminary
design phase of the project.
• The well house will be connected to the existing SCADA systems.
• Potential bidders will be charged a fee for each copy of the Bidding Documents. WSB
will retain this fee.
WSB SUB -CONSULTANTS
WSB subconsultants and their area of responsibility are indicated below:
• Barr Engineering Company — Former Kaeding and Associates Personnel
(electrical/instrumentation and control)
• Wentz Associates, Inc. (plumbing and HVAC)
• Oertel Architects (architectural)
Our scope includes the management of the subconsultants and their efforts. Subconsultant
billings pass through WSB without mark-up.
FEE
WSB & Associates, Inc. will provide the scope of services for as proposed herein on an hourly
basis with a not -to -exceed fee of $155,250. A breakdown according to phase and tasks follows
directly below:
Design and Construction of Well House 6
Task
No.
Task Description — Phase 2 -
Well House/Pump No. 6
WSB
Barr
Wentz
Oertel
Estimated
Fee
2A
Well House Preliminary Design
$5,000
$1,000
$1,000
$2,000
$9,000
2B
Well House Final Design Phase
$43,500
$11,150
$4,000
$12,500
$71,150
2C
Well House Bidding
$6,500
$1,800
$1,000
$1,000
$10,300
2D
Well House Construction
$48,000
$5,300
$4,000
$2,000
$59,300
2E
Well House Post Construction
$5,500
$5,500
Total Phase 2
S108,500
$19,250
$10,000
S17,500
$155,250
WSB's fee includes civil, water and structural design/overall project
management/survey/construction administration/permitting.
M• iWaierWartewaierTiao LakeslWell 6ILTR PROP-LL-060114-Wetl6.doc
Mr. Rick DeGardner
June 2, 2014
Page 5
SCHEDULE
A preliminary schedule for completing the work is as follows:
Well House Design
MDH Review, Bidding
Award Contract
Well House Construction Completed
October — December 2014
December 2014 — January 2015
February 2015
Summer 2015
This letter represents our total understanding of the project and proposed scope of services. If
you are in agreement with the scope of services, please have the City acceptance block of this
letter signed and return a copy to WSB. Our receipt of an executed copy will be WSB's
authorization to proceed. Should the City request additional services outside of the scope of
services outlined above, we will work with you to establish a revised scope and fee.
Please contact me at your convenience at 763-541-4800 if you have any questions or concerns
relating to this proposal as presented. We appreciate the opportunity to assist you and your staff
with the completion of this project.
Sincerely,
WSB & Associates, Inc.
J - Wardr/PE
roject Manager
ACCEPTED:
City of Lino Lakes
By:
Title:
Date:
n Wedel, PE
ity Engineer