CITY OF LINO LAKES
RESOLUTION NO. 00-77
RESOLUTION ORDERING THE IMPROVEMENT AND PREPARATION OF PLANS
AND SPECIFICATIONS — MAIN STREET TRUNK UTILITIES
WHEREAS, a resolution of the City Council adopted the 24th day of July, 2000, fixed a
date for a council hearing on the proposed improvement of Main Street by constructing
trunk sanitary sewer and watermain.
WHEREAS, ten days' mailed notice and two weeks' published notice of the hearing was
given, and the hearing was held earlier this evening, at which time all persons desiring
to be heard were given an opportunity to be heard thereon,
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
1. The City Engineer, John Powell, is hereby designated as the engineer for this
improvement. The engineer shall prepare plans and specifications for the making of
such improvement.
Adopted by the Lino Lakes City Council this 28th •- of August, 2000.
John+. Ber:eson, Mayor
(4,LU /0-(7-0
-el Gaustad, CMC City Clerk
The motion for adoption of the foregoing resolution was duly seconded by Council
Member (ThOC t.L. and upon vote being taken thereon, the following voted in
favor thereof:
The following voted against same:
Whereupon said resolution was duly passed and adopted.
CERTIFICATION
I hereby certify that the above is a correct copy -of a resolution duly passed, adopted and
approved by the City Council on August 28, 2000.
tt0\11 faktal:
Ry-Chel Gaustad, CMC City Clerk
AGENDA ITEM 7J
STAFF ORIGINATOR: John Powell, City Engineer
COUNCIL MEETING DATE: August 28, 2000
TOPIC: PUBLIC HEARING, Main Street Trunk Utilities
VOTE REQUIRED: 3/5 Vote required to close the hearing
BACKGROUND:
This feasibility report was prepared in response to a petition from the Bluebill
Ponds subdivision. The Main Street Trunk Utilities project involves the extension
of trunk sanitary sewer and watermain along Main Street from just west of Nancy
Drive to Wood Duck Trail to serve Bluebill Ponds. On July 24, 2000, the City
Council received the feasibility report for this project and set a date for a Public
Hearing. The only change to the feasibility report is the schedule that has been
revised to reflect Spring, 2001 construction. A copy of the revised schedule is
attached. I will present the information contained in the feasibility report at the
Public Hearing.
OPTIONS:
1. Close the public hearing.
2. Continue the public hearing.
RECOMMENDATION:
Option No. 1 - Staff recommends dosing the public hearing.