CITY OF LINO LAKES
RESOLUTION NO. 99 - 124
RESOLUTION APPROVING PAYMENT NO. 8 (FINAL) AND CHANGE
ORDERS NO. 2 AND 3 FOR THE LILAC STREET UTILITY EXTENSION
PROJECT
WHEREAS, the construction of the Lilac Street Utility Extension Project has
been completed by S.R. Weidema, Inc., and;
WHEREAS, the one-year warranty period for this project will begin with the final
payment.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF LINO LAKES, MINNESOTA:
1. Payment number 8 (final) in the amount of $10,278.06 is approved for a total
contract amount of $227,978.57.
2. Change Orders No. 2 and 3 for $5,835.19 and -$3,048.17 respectively, are
approved.
Adopted by the City Council this 13th d
4L ��1
Ry, hel Gaustad, City Clerk
Divan, Mayor
The motion for adoption of the foregoing resolution was duly seconded by
and upon vote being taken
Council Member Da h
thereon, the following voted in favor thereof: (:lAa.v<i vwoc_s
The following voted against same: no, e
Whereupon said resolution was declared passed and adopted.
CERTIFICATION
I hereby certify that the above is a correct copy of a resolution duly passed,
adopted and approved by the City Council on pecember 1 1999.
Ry+Chel Gaustad, City Clerk
TKDA
TOLTZ, KING, DUVALL, ANDERSON
AND ASSOCIATES, INCORPORATED
ENGINEERS • ARCHITECTS • PLANNERS
1500 PIPER JAFFRAY PLAZA
444 CEDAR STREET
SAINT PAUL. MINNESOTA 55101-2140
PHONE:651/292-4400 FAX:651/292-0083
.Comm. No. 11404
Cert. No. 8 Final St. Paul, MN, November 12 , 19 99
Owner
, Contractor
To City of Lino Lakes, Minnesota
This Certifies that S. R. Weidema, Inc.
For Lilac Street Utility Extension
Is entitled to Ten Thousand Two Hundred Seventy Eight and 06/100 ($ 10,278.06 )
being 8th Final estimate for partial payment on contract with you dated March 23
Received payment in full of above Certificate.
CONTRACTOR
, 19 98
TOLTZ, KING, DUVALL, ANDERSON AND ASSOCIATES, INC.
ENGINEERS -ARCHITECTS -PLANNERS
19 Paul T. Hornby, P.E.
November 16, 1999
RECAPITULATION OF ACCOUNT
An Equal Opportunity Employer
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
203,082.55
All previous payments
-
$ 217,700.51
All previous credits
Extra No. Change Order No. 1
22,109.00
" " Change Order No. 2
5,835.19
" " Compensating Change Order No. 3
(3,048.17)
" "
Credit No.
" ,,
" „
AMOUNT OF THIS CERTIFICATE
10,278.06
Totals
227,978.57
227,978.57
Credit Balance
There will remain unpaid on contract after
r -hent of this Certificate
0.00
227,978.57
227,978.57
An Equal Opportunity Employer
TOLTZ, KING, DUVALL, ANDERSON AND ASSOCIATES, INCORPORATED
Engineers -Architects -Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Final
Estimate No. 8 Period Ending November 12 , 19 99 Page 1 of 1 Comm. No. 11404
Project Lilac Street Utility Extension Original Contract Amount
Location City of Lino Lakes, Minnesota $ 203,082.55
Contractor S. R. Weidema, Inc.
Total Contract Work Completed $ 200,034.38
Total Approved Credits $ 0.00
Total Approved Extra Work Completed
Change Order No. 1 and 2 $ 27,944.19
Approved Extra Orders Amount Completed $ 27,944.19
Total Amount Earned This Estimate $ 227,978.57
Less Approved Credits $ 0.00
Less 0 % Retained $ 0.00
Less Previous Payments $ 217,700.51
Total Deductions $ 217,700.51
Amount Due This Estimate
Contractor
Engineer
S. R. Weidema, Inc.
Paul T. Hornby, P.E.
Date
Date
$ 10,278.06
CHANGE ORDER
TOLTZ, KING, DUVALL, ANDERSON
AND ASSOCIATES, INCORPORATED
Engineers -Architects -Planners
Saint Paul, MN November 12 19 99 Comm. No. 11404 Change Order No. 2
To S. R. Weidema, Inc.
for Lilac Street Utility Extension
for City of Lino Lakes, MN
You are hereby directed to make the following change to your contract dated
March 23 , 19 98 . The change and the work affected thereby is
subject to all contract stipulations and covenants. This Change Order will
(increase) (dccrcooc) (not changc) the contract sum by Five Thousand Eight
Hundred Thirty Five and 19/100 ( $ 5,835.19 ).
CHANGE ORDER NO. 2
This Change Order addresses the additional cost to remove excess material from the
site, perform additional culvert work, and permanently plug sanitary service wyes
due to existing well conflicts.
1. Remove excess material from site (Time)
2. Connect 12" culvert to 15" culvert (Time
3. Remove and Replace 18" culvert (Time and
Permanently plug services
NET CHANGE =
700 CY El $5.00 =
1 LS =
1 LS =
1 LS =
and Materials)
Materials)
(Time and Materials)
Amount of Original Contract
Additions approved to date (Nos. Change Order No. 1)
Deductions approved to date (Nos.
Contract amount to date
Amount of this Change Order (Add)
Revised Contract Amount
Approved City of Lino Lakes, MN
Owner
By
Approved S. R. Weidema
Contractor
By
$3,500.00
$ 587.19
$ 437.00
$1,311.00
$ 5,835.19
$ 203,082.55
$ 22,109.00
$ 0.00
$ 225,191.55
$ 5,835.19
$ 231,026.74
TOLTZ, KING, DUVALL, ANDERSON
AND ASSOCIATES, INCORPORATED
Paul T. Hornby, P.E.
White - Owner
Pink - Contractor
Blue - TKDA
CHANGE ORDER
TOLTZ, KING, DUVALL, ANDERSON
AND ASSOCIATES, INCORPORATED
Engineers -Architects -Planners
Compensating
Saint Paul, MN November 12 19 99 Comm. No. 11404 Change Order No. 3
To S. R. Weidema, Inc.
for Lilac Street Utility Extension
for City of Lino Lakes, MN
You are hereby directed to make the following change to your contract dated
March 23 , 19 98 . The change and the work affected thereby is
subject to all contract stipulations and covenants. This Change Order will
(incrca3c) (decrease) (not changc) the contract sum by Three Thousand Forty
Eight and 17/100 ( $ 3,048.17 ).
COMPENSATING CHANGE ORDER NO. 3
This change order shows the actual quantities installed at the unit price bid
amounts (See attached itemization):
NET CHANGE =
Amount of Original Contract
Additions approved to date
Deductions approved to date
Contract amount to date
Amount of this Change Order
Revised Contract Amount
$ (3,048.17)
$ 203,082.55
(Nos. Change Order No.'s 1 and 2) $ 27,944.19
(Nos. ) $ 0.00
$ 231,026.74
(Deduct) $ (3048.17)
$ 227,978.57
Approved City of Lino Lakes, MN
TOLTZ, KING, DUVALL, ANDERSON
Owner , AND ASSOCIATES, INCORPORATED
By
Approved S. R. Weidema.
By
Contractor
By
Paul T. Hornby, P.E.
White - Owner
Pink - Contractor
Blue - TKDA
AGENDA ITEM 6 F
STAFF ORIGINATOR: John Powell, City Engineer
COUNCIL MEETING DATE: December 13, 1999
TOPIC: Resolution No. 99 -124, Approve Payment No. 8 (final) and
Change Orders No. 2 and 3, Lilac Street Utility Extension
VOTE REQUIRED: Simple Majority — 3/5
BACKGROUND:
The Contractor for the Lilac Street Utility Extension project, S.R. Weidema, Inc.,
is requesting City approval of Payment No. 8 (final) in the amount of $10,278.06.
The Withholding Affidavits and Consent of Surety have been submitted to the
City which meet the requirements of the Construction Contract.
The project included the installation of utilities along Lilac Street from fourth
Avenue to Apollo Drive. The final contract amount is summarized as follows:
Original Bid Amount
Change Order No. 1
Change Order No. 2
Change Order No. 3
Final Contract Amount
$203,082.55
$ 22,109.00
$ 5,835.19
$ (3,048.17)
$227,978.57
OPTIONS:
1. Return to staff for further review.
2. Approve Resolution 99 -124 approving payment no. 8 (final) and Change
Order Nos. 2 and 3 for the Lilac Street Utility Extension project.
RECOMMENDATION:
Staff recommends that Resolution 98 - 124 be approved.