CITY OF LINO LAKES
RESOLUTION NO. 99 -125
RESOLUTION APPROVING PAYMENT NO. 2 (FINAL) AND CHANGE
ORDERS NO. 1 AND 2 FOR THE LILAC STREET TRUNK UTILITIES PHASE 2
PROJECT
WHEREAS, the construction of the Lilac Street Trunk Utilities Phase 2 Project
has been completed by S.R. Weidema, Inc., and;
WHEREAS, the one-year warranty period for this project will begin with the final
payment.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF LINO LAKES, MINNESOTA:
1. Payment number 2 (final) in the amount of $11,654.07 is approved for a total
contract amount of $102,974.72.
2. Change Orders No. 1 and 2 for $6,025.22 and $2,934.60 respectively, are
approved.
Adopted by the City Council this 13th d
µ
Ry- heI Gaustad, City Clerk
livan, Mayor
The motion for adoption of the foregoing resolution was duly seconded by
Council Member rfj'eSo and upon vote being taken
thereon, the following voted4n favor thereof:
The following voted against same: NefkA
Whereupon said resolution was declared passed and adopted.
CERTIFICATION
I hereby certify that the above is a correct copy of a resolution duly passed,
adopted and approved by the City Council on ecember 13, 1999.
VACCiafr
RlyChel Gaustad, City Clerk
TKDA
TOLTZ, KING. DUVALL, ANDERSON
AND ASSOCIATES, INCORPORATED
'NGINEERS • ARCHITECTS • PLANNERS
1500 PIPER JAFFRAY PLAZA
444 CEDAR STREET
SAINT PAUL, MINNESOTA 55101-2140
PHONE:651/292-4400 FAX:651/292-0083
.Comm. No. 11494
Cert. No. 2 St. Paul, MN, November 5 , 19 99
Owner
, Contractor
To City of Lino Lakes, Minnesota
This Certifies that S. R. Weidema
For Lilac Street Trunk Utilities
Is entitled to Eleven Thousand Six Hundred Fifty Four and 07/100 ( $
being 2nd estimate for partial payment on contract with you dated
Received payment in full of above Certificate.
CONTRACTOR
,19
11,654.07 )
October 12
, 19 98
TOLTZ, KING, DUVALL, ANDERSON AND ASSOCIATES, INC.
ENGINEERS -ARCHITECTS -PLANNERS
Paul T. Hornby P.E.
November 5, 1999
RECAPITULATION OF ACCOUNT
_
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
94,014.90
All previous payments
$ 91,320.65
All previous credits
Extra No. Change Order No. 1
6,025.22
" " Compensating Change Order No. 2
2,934.60
H II
It el
Credit No.
11 "
" II
II II
AMOUNT OF THIS CERTIFICATE
11,654.07
Totals
102,974.72
102,974.72
Credit Balance
T' -Are will remain unpaid on contract after
nent of this Certificate
0.00
102,974.72
102,974.72
An Equal Opportunity Employer
TOLTZ, KING, DUVALL, ANDERSON AND ASSOCIATES, INCORPORATED
Engineers -Architects -Planners Saint Paul, Minnesota 55101
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
Estimate No. 2 Period Ending November 5 , 19 99 Page:1 of 1 Comm. No. 11494
Project Lilac Street Trunk Utilities - Phase 2 Original Contract Amount
Location Lino Lakes, Minnesota $ 94,014.90
Contractor S.R. Weidema, Inc.
Total Contract Work Completed $ 96,949.50
Total Approved Credits $
Total Approved Extra Work Completed $ 6,025.22
Approved Extra Orders Amount Completed $ 6,025.22
Total Amount Earned This Estimate
$ 102,974.72
Less Approved Credits $ 0.00
Less 0 % Retained $ 0.00
Less Previous Payments $ 91,320.65
Total Deductions $ 91,320.65
Amount Due This Estimate $ 11,654.07
Contractor Date
Enginee
Date NitAi b ti 10194
CHANGE ORDER
TOLTZ, KING, DUVALL, ANDERSON
AND ASSOCIATES, INCORPORATED
Engineers -Architects -Planners
Saint Paul, MN November 5 19 99 Comm. No. 11494 Change Order No. 1
To S. R. Weidema
for Lilac Street Trunk Utilities
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
October 12 , 19 98 . The change and the work affected thereby is
subject to all contract stipulations and covenants. This Change Order will
(increase) (dccreasc) (not changc) the contract sum by Six Thousand Twenty Five
and 22/100 ( $ 6,025.22 ).
CHANGE ORDER NO. 1
This Change Order is for Labor and Materials for the installation of sanitary sewer
and watermain services for Lot 14, Block 3 at Behm's Century Farm 5th Addition.
NET CHANGE = $ 6,025.22
Amount of Original Contract $ 94,014.90
Additions approved to date (Nos. ) $ 0.00
Deductions approved to date (Nos. ) $ 0.00
Contract amount to date $ 94,014.90
Amount of this Change Order (Add) $ 6,025.22
Revised Contract Amount $ 100,040.12
Approved City of Lino Lakes, MN TOLTZ, KING, DUVALL, ANDERSON
Owner AND ASSOCIATES, INCORPORATED
By
Approved S. R. Weidema
Paul T. Hornby, P.E.
White - Owner
Contractor Pink - Contractor
Blue - TKDA
By
CHANGE ORDER
TOLTZ, KING, DUVALL, ANDERSON
AND ASSOCIATES, INCORPORATED
Engineers -Architects -Planners
Compensating
Saint Paul, MN November 5 19 99 Comm. No. 11494 Change Order'No. 2
To S. R. Weidema
for Lilac Street Trunk Utilities
for City of Lino Lakes
You are hereby directed to make the following change to your contract dated
October 12 , 19 98 . The change and the work affected thereby is
subject to all contract stipulations and covenants. This Change Order will
(increase) (dccrcaoc) (not changc) the contract sum by Two Thousand Nine Hundred
Thirty Four and 60/100 ( $2,934.60 ).
COMPENSATING CHANGE ORDER NO. 2
This change order shows the actual quantities installed at the unit price bid
amounts (See attached itemization):
NET CHANGE = $ 2,934.60
Amount of Original Contract $ 94,014.90
Additions approved to date (Nos. Change Order No. 1) $ 6,025.22
Deductions approved to date (Nos. ) $ 0.00
Contract amount to date
Amount of this Change Order (Add)
Revised Contract Amount
Approved City of Lino Lakes, MN
$ 100,040.12
$ 2,934.60
$ 102,974.72
TOLTZ, KING, DUVALL, ANDERSON
Owner AND ASSOCIATES, INCORPORATED
By
Approved S. R. Weidema
By
Paul T. Hornby, P.E
White - Owner
Contractor Pink - Contractor
Blue - TKDA
By
AGENDA ITEM 6 G
STAFF ORIGINATOR: John Powell, City Engineer
COUNCIL MEETING DATE: December 13, 1999
TOPIC: Resolution No. 99 -125, Approve Payment No. 2 (final) and
Change Orders No. 1 and 2, Lilac Street Trunk Utilities Phase 2
VOTE REQUIRED: Simple Majority — 3/5
BACKGROUND:
The Contractor for the Lilac Street Trunk Utilities Phase 2, S.R. Weidema, Inc., is
requesting City approval of Payment No. 2 (final) in the amount of $11,654.07.
The Withholding Affidavits and Consent of Surety have been submitted to the
City which meet the requirements of the Construction Contract.
The project included the installation of utilities along Mustang Lane to serve
Behm's Century Farm 5th Addition. The final contract amount is summarized as
follows:
Original Bid Amount $ 94,014.90
Change Order No. 1 $ 6,025.22
Change Order No. 2 $ 2,934.60
Final Contract Amount $102,974.72
OPTIONS:
1. Return to staff for further review.
2. Approve Resolution 99 -125 approving Payment No. 2 (final) and Change
Orders Nos. 1 and 2 for the Lilac Street Trunk Utilities Phase 2.
RECOMMENDATION:
Staff recommends that Resolution 98 - 125 be approved.