HomeMy WebLinkAbout2015-081 Council ResolutionCITY OF LINO LAKES RESOLUTION NO. 15-81 RESOLUTION APPROVING CHANGE ORDER NO. 1 2015 STREET RECONSTRUCTION PROJECT (SHENANDOAH AREA) WHEREAS, pursuant to resolution 15-36 of the Council adopted on April 13, 2015, awarding the contract for the 2015 Street Reconstruction Project (Shenandoah Area) to Arnt Construction Company, Inc.; and WHEREAS, a complete summary of costs are detailed in Change Order No. 1; NOW, THEREFORE, BE IT RESOLVED by the City Council of Lino Lakes, Minnesota that Change Order No. 1 is approved in the amount of ($28,560). BE IT FURTHER RESOLVED Adopted by the Council of the City of Lino Lakes this 10th day of August, 2015. The motion for the adoption of the foregoing resolution was introduced by Council Member Roeser and was duly seconded by Council Member Kusterman and upon L vote being taken thereon, the following voted in favor thereof: Roeser, Kusterman, Rafferty, Stoesz, Reinert The following voted against same: none ATTEST: e Bartell, C. Cler CITY COUNCIL AGENDA ITEM 6B STAFF ORIGINATOR: Diane Hankee MEETING DATE: August 10, 2015 TOPIC: Consider Resolution No. 15-81, Approving Change Order No. 1, 2015 Street Reconstruction Project (Shenandoah Area) VOTE REQUIRED: 3/5 INTRODUCTION Staff is requesting council approval of Change Order No. 1 for the 2015 Street Reconstruction Project (Shenandoah Area). BACKGROUND On April 13, 2015, the City awarded the above-mentioned project to Arnt Construction Company, Inc. in the amount of $2,227,975. The Contractor requested a specification change resulting in a reduced project costs. Staff has reviewed the request with our engineering specialists and recommends the enclosed contract modification reducing the project costs by ($28,560). This results in a reduced contract price of $2,199,415. RECOMMENDATION Staff is recommending approval of Resolution No. 15-81 for Change Order No. 1 for the 2015 Street Reconstruction Project (Shenandoah Area). ATTACHMENTS 1. Resolution No. 15-81 2. Change Order No.1 CHANGE ORDER NO. 1 2015 STREET RECONSTRUCTION PROJECT CITY OF LINO LAKES, MN WSB PROJECT NO. 2029-85 July 17, 2015 OWNER: CITY OF LINO LAKES TOWN CENTER PARKWAY LAKES, MN 55014-1182 CONTRACTOR: 600 ARNT CONSTRUCTION CO. LINO 2190 PHELPS ROAD HUGO, MN 55038 YOU ARE DIRECTED TO MAKE THE FOLLOWING CHANGES IN THE CONTRACT DOCUMENT DESCRIPTION: Reduce the unit price of item no 24: AGGREGATE BASE by $1.40, making the new unit price $10.00. IT IS UNDERSTOOD THAT THIS CHANGE ORDER INCLUDES ALL ADDITIONAL COSTS AND TIME EXTENSIONS WHICH ARE IN ANY WAY, SHAPE, OR FORM ASSOCIATED WITH THE WORK ELEMENTS DESCRIBED ABOVE. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME: ORIGINAL CONTRACT PRICE: PREVIOUS CHANGE ORDERS: NO. 1 ")NTRACT PRICE PRIOR TO THIS CHANGE ORDER: �, cT DECREASE OF THIS CHANGE ORDER: CONTRACT PRICE WITH ALL APPROVED CHANGE ORDERS: RECOMMENDED BY: �,s� BRAD REIFSTECK, PE, ROJECT MANAGER WSB & ASSOCIATES, INC. ENGINEER $2,227,975.18 $0.00 $2,227,975.18 ($28,560.00) $2,256,535.18 ORIGINAL CONTRACT TIME: NET CHANGE FROM PREVIOUS CHANGE ORDERS: CONTRACT TIME PRIOR TO THIS CHANGE ORDER: NET INCREASE OF CHANGE ORDER: CONTRACT TIME WITH APPROVED CHANGE ORDERS: APPROVED BY: 7 10/16/2015 NONE 10/16/2015 NONE 10/16/2015 CONTRACTOR SIGNATURE ARNT CONSTRUCTION CO. CONTRACTOR APPROVED BY: CITY ENGINEER ATE CITY ADMINISTRATOR DATE K:102029.8501AdminlConslruclion Admin1Pay Vouchers) Page 1 of 2 2029.85 C01 071715C0 2 CHANGE ORDER NO. 1 2015 STREET RECONSTRUCTION PROJECT JULY 17, 2015 CITY OF LINO LAKES, MN WSB PROJECT NO. 2029-85 ADDED ITEMS Item No. Mat. No. Description Qty Unit Price Extended Amount TOTAL ADDED ITEMS CHANGE ORDER NO. 1 DELETED ITEMS Item No. Mat. No. Description Qty Unit Price Extended Amount 85 2211.501 AGGREGATE BASE CLASS 5 20400 TON 41.40 -$28,560.00 TOTAL DELETED ITEMS CHANGE ORDER NO. 1 428,560.00 Page 2 of 2 K:102029-850AdminlConstructlon AdmintPay Voucheral 2029-85 CO1 071715C0 2 Detail