Laserfiche WebLink
CSAH 15 & 30th St IntersectionCity of Lake ElmoCounty/City Cooperative Agreement #14787Cost splits through PE 212/14/2022Estimated Cost Share (Post Bid) Current Costs Previously PaidCurrent Amount Due  Construction517,944.00$                    522,901.02$          51,794.40$             471,106.62$           Design Engineering128,011.00$                    128,011.00$          12,801.10$             115,209.90$           Construction Engineering/Contract Administration39,512.00$                      41,832.08$             3,951.20$               37,880.88$              County Furnished Material41,450.00$                      39,754.21$             4,145.00$               35,609.21$            Total Costs 726,917.00$                   732,498.31$          72,691.70$            659,806.61$