WILDFLOWER AT LAKE ELMO 4TH ADDITION Time of Performance: August 31, 2022DEVELOPMENT AGREEMENT AMOUNTSCATEGORY CONSTRUCTION 125% REMARKS #1 #2 #3 #4 #5 #6Sanitary Sewer $257,538 $321,92375%$241,442Watermain $218,620 $273,27575%$204,956Streets & Sidewalks $1,240,903 $1,551,12975%$775,564 $387,782Storm Sewer $238,267 $297,83475%$148,917 $74,458Erosion Control $38,975 $48,719Surface Water Facilities (BMPs) $12,460 $15,575Trails $50,907 $63,634Street Lighting $24,000 $30,000Street Signs and Traffic Control Signs $5,219 $6,524Landscaping $5,000 $6,250Tree Preservation and Restoration NA NAWetland Mitigation and Buffers NA NAMonuments $4,100 $5,125Private Utilities NA NARecord Drawings $5,000 $6,250TOTALS $2,100,989 $2,626,236RELEASED AMOUNTS:$446,398 $924,481 $462,241CUMMULATIVE AMOUNTS:$446,398 $1,370,879 $1,833,120SECURITY AMOUNT REMAINING:$2,179,838 $1,255,357 $793,116DATE:1/17/2023 12/5/2023 1/2/2024REDUCTIONS
|