  <br />     <br />  <br />PROJECT SCHEDULE  <br />CITY OF LAKE ELMO  <br />STILLWATER AREA SCHOOL DISTRICT  <br />UTILITY IMPROVEMENTS  <br />PROJECT NO. 2024.113  <br />  <br />  <br />  <br />MAY 8, 2024  City receives Petition to connect the Oak‐Land Middle School to public water and  <br />sewer, and the new Elementary School to public sewer.  <br />  <br />MAY 21, 2024  Council accepts the Petition from the Stillwater Area Public School District (District)  <br />and authorizes the preparation of a Feasibility Report.  <br />  <br />OCOTBER 15, 2024  Council accepts the Feasibility Report and Calls for Public Hearing.  <br />  <br />NOVEMBER 19, 2024  Public  Improvement  Hearing.  Council  receives signed  Waiver  Agreement  from  <br />Stillwater Area School District.  Council Orders the Improvement and authorizes the  <br />preparation of Plans and Specifications.  <br />  <br />MARCH 4, 2025  Council approves Plans and Specifications and orders Advertisement for Bids.  <br />  <br />APRIL 3, 2025      Project Bid Date: Receive contractor Bids.  <br />  <br />APRIL 15, 2025  Council accepts Bids and awards Contract.   <br />  <br />APRIL 28, 2025    Conduct Pre‐Construction meeting and issue Notice to Proceed.  <br /> AUGUST 29, 2025    Substantial Completion.  <br /> SEPTEMBER 26, 2025    Final Completion.  <br />  <br />*Final Assessment Hearing Schedule TDB (if applicable)