FISCAL IMPACT: The total estimated project cost is $150,000 versus the CIP estimate of $50,000. Site <br />conditions including overhead power and telecommunication poles on the same property which increases <br />constructability efforts. The project is funded by the Water Enterprise Fund. <br /> <br />RECOMMENDATION: Staff is recommending the City Council accept quotes and award a contract to <br />Iseler Demolition, Inc. in the amount of $100,700. The Recommended motion is as follows: <br /> <br />Motion to approve accept quotes and award a contract to Iseler Demolition, Inc. in the amount of <br />$100,700 for the Demolition of Water Tower No. 1. <br /> <br />ATTACHMENTS: <br /> <br />1. Location Plan <br />2. Engineer’s Letter of Recommendation