<br />STANTEC – 5/30/2025 WORK CHANGE DIRECTIVE 06 <br />173420153 Lake Elmo Well No. 2 PFAS WTP PAGE C-940- 1 <br />SECTION C-940 – WORK CHANGE DIRECTIVE 06 <br />Owner: City of Lake Elmo, Minnesota Owner’s Project No.: 2023.115 <br />Engineer: Stantec Engineer’s Project No.: 173420153 <br />Contractor: Magney Construction Contractor’s Project No.: 616 <br />Project: Well No. 2 PFAS WTP <br />Contract <br />Name: <br />Date Issued: 5/30/2025 <br />Effective Date of Work Change <br />Directive: 5/30/2025 <br />Contractor is directed to proceed promptly with the following change(s): <br />Description: <br />Remove and replace existing copper house water line that was cracked. <br />Attachments: <br />RFP 006 – Copper Water Line Replacement (provided by Magney) <br />Purpose for the Work Change Directive: <br />Replace and reconfigure house water line. <br /> <br /> <br /> <br /> <br />Directive to proceed promptly with the Work described herein, prior to agreeing to change in <br />Contract Price and Contract Time, is issued due to: <br />☐ Non-agreement on pricing of proposed change. ☒ Necessity to proceed for schedule or other <br />reasons. <br />Estimated Change in Contract Price and Contract Times (non-binding, preliminary): <br />Contract Price: $890.18 increase <br />Contract Time: 0 days no change <br />Basis of estimated change in Contract Price: <br />☒ Lump Sum ☐ Unit Price ☐ Cost of the Work ☐ Other <br /> Recommended by Engineer Authorized by Owner <br />By: Brian Lintgen, Stantec Marty Powers, City of Lake Elmo <br />Title: Project Manager Public Works Director <br />Date: 5/30/2025 5/30/2025 <br />