TREATMENT STRATEGIES <br />1)Crack Sealing (non-structural). Hot rubberized sealant placed in cracks after routing and <br />cleaning. <br />2)Seal Coating (non-structural). Always completed with crack sealing. An emulsified <br />asphalt spread over the pavement followed by uniform cover of crushed trap rock. <br />3)Mill and Overlay (structural): Removal of a portion of the bituminous layer followed by <br />paving 1-1/2 to 2-inch new bituminous. <br />4)Full Depth Reclamation (FDR) – with and without new concrete curb and gutter. <br />5)Reconstruction. Removal and replacement of full roadway section. <br />Maintenance or Construction Cost Total Project Cost <br />Rehabilitation Method Unit Cost ($/SF) Unit Cost ($/SF) <br />Seal Coating $ 0.24 $ 0.30 <br />Mill and Overlay $ 1.60 $ 2.00 <br />Reclamation – No curb $ 5.20 $ 6.50 <br />Reclamation – New curb $ 8.15 $11.00 <br />Reconstruction $14.80 $20.00