<br /> WORK CHANGE DIRECTIVE 07 <br />STANTEC – 6/20/2025 <br />173420153 Lake Elmo Well No. 2 PFAS WTP PAGE C-940- 1 <br />SECTION C-940 – WORK CHANGE DIRECTIVE 07 <br />Owner: City of Lake Elmo, Minnesota Owner’s Project No.: 2023. 115 <br />Engineer: Stantec Engineer’s Project No.: 173420153 <br />Contractor: Magney Construction Contractor’s Project No.: 616 <br />Project: Well No. 2 Water Treatment Plant <br />Contract <br />Name: <br />Date Issued: 6/20/2025 <br />Effective Date of Work Change <br />Directive: 6/20/2025 <br />Contractor is directed to proceed promptly with the following change(s): <br />Description: <br />Hi-E Dry dehumidifier purchase and installation. <br />Attachments: <br />RFP 007 – HI E Dry Unit <br />Purpose for the Work Change Directive: <br />One Hi-E Dry dehumidification unit is needed inside the PFAS vessel room to reduce <br />condensation on the process pipes and vessels. Provide the unit in the attached RFP. <br /> <br /> <br /> <br /> <br />Directive to proceed promptly with the Work described herein, prior to agreeing to change in <br />Contract Price and Contract Time, is issued due to: <br />☐ Non-agreement on pricing of proposed change. ☒ Necessity to proceed for schedule or other <br />reasons. <br />Estimated Change in Contract Price and Contract Times (non-binding, preliminary): <br />Contract Price: $ 4,309.09 increase <br />Contract Time: 0 days No change <br />Basis of estimated change in Contract Price: <br />☒ Lump Sum ☐ Unit Price ☐ Cost of the Work ☐ Other <br /> Recommended by Engineer Authorized by Owner <br />By: Brian Lintgen, Stantec Marty Powers, City of Lake Elmo <br />Title: Project Manager Public Works Director <br />Date: 6/20/2025 6/20/2025 <br />