4 <br /> <br />REVIEW COMMENTS <br />City Engineer (Memo dated 1/9/2023) <br />1. Final Construction Plans must be prepared in accordance with the Engineering and Design <br />Standards Manual, dated January 2022. <br />2. No construction on the Project may begin until the applicant has received City Engineer <br />approval for the Final Construction Plans; the applicant has obtained and submitted to the <br />City all applicable permits, easements and permissions needed for the project; and a <br />preconstruction meeting has been held by the City’s engineering department. All off‐site <br />permanent or temporary construction easements required to construct the project must be <br />shown on the plans and must be provided prior to scheduling a preconstruction meeting. <br />3. Upper 33rd Street N does not meet the minimum city standards for road width and right of <br />way width. <br />4. No on street parking is allowed along Upper 33rd Street N. Parking must be kept internal to <br />the site. <br />5. No sidewalk or trail currently exists along Upper 33rd Street due to the narrow roadway. <br />6. A 10-ft drainage and utility easement must be provided along the property frontage. <br />Minimum lot easements should be included along the side and rear property lines as well. <br />7. Revise the existing conditions plan to show a minimum distance of 150 ft outside the <br />property boundary in all directions. <br />8. Site grading must be revised to meet all city minimum and maximum allowable grades. <br />9. The grading plans must be revised, as may be required, to meet city design standards <br />10. The proposed site plan is subject to a storm water management plan (SWMP) meeting State, <br />Valley Branch Watershed District (VBWD) and city rules. <br />11. In order to comply with VBWD and city rules, the applicant is requesting to divert <br />stormwater runoff that currenting discharges north from the property, and to proposed <br />southerly discharge location. This stormwater diversion has been found to be acceptable to <br />the city. <br />12. The soils investigations performed on the site determined that infiltration is not feasible. <br />Therefore, the developer intends to purchase credits from Lake Elmo’s Downtown Regional <br />Infiltration Basin Volume Control credit bank to meet volume control requirements. <br />13. The storm water management facilities constructed for this development will be privately <br />owned and maintained. The applicant will be required to execute and record a Stormwater <br />Maintenance and Easement Agreement in the City’s standard form of agreement. The <br />stormwater drainage and utility easements must be shown on the site plans, utility plans and <br />grading plans. A Homeowner’s association would be required for the development to provide <br />for the ongoing ownership and maintenance <br />14. Municipal water supply is available to the site. <br />15. Sanitary sewer service is available to the site. <br /> <br /> <br />Fire Department (Memo dated 1/6/2023) <br />1. The fire sprinkler system shall be installed compliant with provisions of 2016 NFPA <br />Standard 13D, Installation of Sprinkler Systems in One- and Two-Family Dwellings or IRC <br />P2904. City permit required prior to initiation of work. <br />2. Building address numbers shall be plainly visible from the street fronting the property and <br />shall be a contrasting color from the background. Size and placement of address numbers <br />shall be approved by the fire and planning departments. <br />