STAFF REPORT <br />DATE: March 7, 2023 <br /> REGULAR <br /> <br />AGENDA ITEM: Approve Plans and Specifications and Order Advertisement for Bids for the 2023 <br />Street Improvements <br />SUBMITTED BY: Jack Griffin, City Engineer <br />REVIEWED BY: Kristina Handt, City Administrator Marty Powers, Public Works Director <br /> Chad Isakson, Assistant City Engineer <br /> <br /> <br />ISSUE BEFORE COUNCIL: Should the City Council approve the Plans and Specifications and Order <br />the Advertisement for the 2023 Street Improvements? <br /> <br />BACKGROUND: On November 15, 2022, following a Public Improvement Hearing, the City Council <br />ordered the improvements and preparation of the plans and specifications for the 2023 Street Improvements. <br />The project was initiated as part of the City’s annual Capital Street Improvement Program. <br /> <br />The project includes street and drainage improvements within the Tana Ridge neighborhood and the Fields <br />of St. Croix 2nd Addition, consisting of approximately 12,300 feet (2.3 miles) of local streets. The proposed <br />improvements include a full-depth reclamation of the existing pavement and aggregate base materials to a <br />depth of approximately 8 inches to provide a renewed recycled aggregate base to support a new bituminous <br />surface. Excess aggregates materials would be hauled off site. The existing bituminous curb will be replaced <br />with a combination of new B418 and new surmountable concrete curb and gutter to improve drainage, <br />improve the construction quality, and provide edge control to protect and extend the service life of the new <br />bituminous surface. No geometric alterations are proposed for either neighborhood. The proposed project <br />will maintain the reconstructed street at or very near the existing centerline and pavement widths to <br />minimize the construction grading and drainage impacts to adjacent properties. A short section in Tana <br />Ridge is proposed to be widened slightly to maintain a consistent road width through the neighborhood. <br />There is also minor widening proposed to the separated entrance lanes at the south entrance to Fields of St <br />Croix 2nd. In both subdivision areas, the storm sewer and drainage systems will be repaired to restore the <br />original drainage function within each neighborhood and storm sewer castings will be replaced. <br /> <br />The final design scope of improvements remains generally consistent with the feasibility report that was <br />approved by the City Council on October 18, 2023, as recommended for the street and drainage <br />improvements. Hydrant nozzles will be replaced and new hydrant flags will be installed as part of the <br />project. <br /> <br />PROPOSAL DETAILS/ANALYSIS: The plans and specifications have been completed for the <br />improvements and are ready to be advertised for contractor bids. A bid date has been scheduled for April <br />6, 2023. Contractor bids will be received and reviewed by staff with a tentative staff recommendation for <br />award of contract to be presented for council consideration at the April 18, 2023 council meeting. <br />As part of the street improvement design, the street width and geometrics were evaluated with Public Works <br />and the Fire Department in accordance with the Parking restriction guidelines. As a result of this evaluation, <br />the following post construction parking recommendations have been incorporated into the project plans <br />(see attached exhibits): <br />