CITY OF LAKE ELMOOLD VILLAGE PHASE 7 STREET & UTILITY IMPROVEMENTSPROJECT NO. 2022.119Feasibility Report Estimate of CostPost BidAlternate B (Recommendation)Estimate of Cost Post BidAlternate A Estimate of Cost Total Project Cost$2,820,000 $3,022,959 $3,049,559Street and Storm Sewer$944,000 $985,318 $983,502Assessment Amount$9,800 $9,800 $9,800Assessed Parcels29 29 29Assessment Revenue (2 city parcels included)$284,200 $284,200 $284,200City Share$659,800 $701,118 $699,302Sanitary Sewer$1,368,000 $1,581,095 $1,610,556Assessment Amount$13,100 $13,100 $13,100Assessed Parcels22 22 22Assessment Amount$288,200 $288,200 $288,200City Share$1,079,800 $1,292,895 $1,322,356Watermain (Water Enterprise Fund)$508,000 $456,546 $455,501