additional hauling, and extra disposal costs. An initial estimate of the additional costs is between <br />$50,000.00 and $200,000.00. "I'hese extra costs will be billed as time and material and a change <br />order for such will be submitted to the Owner. <br />Park Construction Company attempted to discuss this issue in good faith with the Owner before it <br />escalated to this level, but the Owner refused to do so. <br />It therefore behooves the Owner to understand the difference between disposal and stockpile and to <br />realize that any restrictions added after a project is bid and awarded are considered changes. He <br />further needs to rescind the citations and have all records of such expunged. <br />Park Construction Company would like to have the opportunity to present this issue to the Council <br />and reach an agreement beneficial to all parties. <br />If you have any questions, do not hesitate to contact us. <br />Sincerely, <br />Project Manager <br />763-717-6208 Direct <br />612-770-2383 Cell <br />mallen@parkconstructionco.com <br />