Laserfiche WebLink
TKDA <br />Engineers -Architects -Planners <br />PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS <br />FINAL <br />Estimate No. 3 Period Ending September 28 , 20 06 Page 1 of 1 Proj. No. 13186.000.003 <br />Contractor G M Contractine Inc Original Contract Amount $359.049.86 <br />Project Water System Interconnect - Phase II <br />Location Citv of Lake Elmo Minnesota <br />Total Contract Work Completed <br />Total Approved Credits <br />Total Approved Extra Work Completed $ 0.00 <br />Approved Extra Orders Amount Completed <br />Total Amount Earned This Estimate <br />Less Approved Credits $ 0.00 <br />Less 0 % Retained $ 0.00 <br />Less Previous Payments $ 350,518.21 <br />Total Deductions <br />Amount Due This Estimate <br />Contractor <br />G.M. Contracting, Inc. <br />Date <br />$ 368,966.54 <br />$ 0.00 <br />$ 0.00 <br />$ 368,966.54 <br />$ 350,518.21 <br />$ 18,449.33 <br />Engineer Date September 29 2006 <br />Thomas D. Prew, P.E. <br />