HomeMy WebLinkAboutCC 12-07-2010 I-94 to 30th Street Sewer SCHED OPT 1CITY OF LAKE ELMO LAKE ELMO TRUNK SANITARY SEWER EXTENSION PROJECT I-94 TO 30TH STREET PROPOSED PROJECT SCHEDULE – OPTION 1
August 17, 2010 Council approves lift station location and authorizes TKDA to complete final design.
December 7, 2010 Council directs staff to prepare plans and specifications, work with property owners and acquire easements to incorporate an add/alternate bid option for gravity sewer south of 10th street.
March 1, 2011 Presentation of Plans and Specifications to the City Council. Council approves Plans and Specifications and orders Advertisement for Bids
March 3, 2011 Placement of Advertisement for Bids – Oakdale-Lake Elmo Review. Publication date of March 9 and 16.
March 3, 2011 Placement of Advertisement for Bids – Finance and Commerce. Publication date of March 4.
March 31, 2011 Receive Contractor bids
April 5, 2011 City Council accepts bids and awards Contract
April 12, 2011 Process and send out Contract Documents April 20, 2011 Receipt of Contractor’s Bonds/Legal Review and Issue Notice to Proceed April 26, 2011 Conduct Pre-construction Meeting
May 1, 2011 Contractor begins work
September 2011 Substantial Completion November 2011 Final Completion