HomeMy WebLinkAboutCC 12-07-2010 Rain Garden 09-10 CO #2 CHANGE ORDER
TKDA
Engineering-Architecture-Planning
Saint Paul,MN November 23 20 10 Proj.No. 14504.001 Change Order No. 2
To All Weather Services
for 2009 &2010 Street Improvement Raingarden Proiect
for City of Lake Elmo,Minnesota
You are hereby directed to make the following change to your contract dated
September 22 ,20 10 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will(increase)(4eefease)(not-ela )the contract sum by One Thousand Eight Hundred
Forty Five Dollars and 00/100 1$1 845.00
This change order includes the cost to perform additional soil correction to the under laying soils and to install an underdrain
to the raingarden located at 8879 Jane Road North.
NET CHANGE= $ 1,845.00
Amount of Original Contract $ 27,688.75
Additions approved to date(Change Order Nos. 1) $ 400.00
Deductions approved to date(Nos. )
Contract amount to date $ 28,088.75
Amount of this Change Order(Add)(Deduct)(N ) $ 1,845,00
Revised Contract Amount $ 29,933,75
Approved Washington Conservation District
City of Lake Elmo
By By
Rusty Schmidt
Approved
All Weather Services
By