HomeMy WebLinkAboutItem 16 Keats Project SchedulePROJECT SCHEDULE
FOCUS ENGINEERING, inc.
Cara Geheren, P.E. 651.300.4261
Jack Griffin, P.E. 651.300.4264
Ryan Stempski, P.E. 651.300.4267
Chad Isakson, P.E. 651.300.4283
Project Title: Keats MSA Street and Trunk Watermain Improvements
Client: City of Lake Elmo
Project No.: 2012.129
Date: Revised April 9, 2013
October 2, 2012 Improvement Hearing. Council authorizes the preparation of Plans and
Specifications.
November 7, 2012 Council approves selection of Engineering Consultant for design services.
December 11, 2012 Workshop on Trunk Watermain Lateral Benefit Assessments.
March 5, 2013 City Engineer presents Plans and Specifications for Council approval.
April 9, 2013 Receive Contractor Bids.
April 16, 2013 City Council accepts bids and awards Contract.
May 27, 2013 Issue Notice to Proceed. Contractor begins Work.
August 30, 2013 Substantial Completion date for Work [includes paving and restoration].
October 4, 2013 Final Completion date for Work [including all punch list items].