HomeMy WebLinkAboutItem 6 2013-125 Well#4 Project SchedulePROJECT SCHEDULE  PRODUCTION WELL NO. 4  PROJECT NO. 2013.125  FOCUS ENGINEERING, inc.  Cara Geheren, P.E.  651.300.4261 Jack Griffin, P.E.               651.300.4264  Ryan Stempski, P.E. 651.300.4267  Chad Isakson, P.E. 651.300.4283  Revised April 2013               February 5, 2013 Council authorizes the Preparation of plans and specifications.    February 11, 2013 Project kickoff meeting.    April 16, 2013 Approve Plans and Specifications and Authorize Advertisement for Contractor Bids.  (estimated 8 weeks)    May 16, 2013  Accept Contractor Bids    May 21, 2013  Contract Award.    May 24, 2013 Process and send out Contract Documents.    June 7, 2013 Receipt of Contractor’s Bonds / Legal Review.    June 11, 2013 Conduct Pre‐construction Meeting and Issue Notice to Proceed.    October, 2013 Production Well Contractor Work is substantially complete (estimated 19 weeks).    November, 2013 Final Completion Date. Record As‐builts; Testing Results; and Close‐out Documents.